Appendix C
Closure Planning and Implementation
Table C-1 lists activities that are likely relevant to closure of any industrial or government facility. Not all of the activities are necessarily applicable to a particular closure situation. The indented items in the table are primarily illustrative and are not intended to be all inclusive, but rather to indicate the types of activities required at those stages of the closure process under which they appear.
The planning phase consists of (1) an assessment and decision-making period in which general overall objectives and criteria are formulated and (2) a closure plan development period when plans are formulated and written. In practice, there can be considerable overlap between assessment and decision making as a detailed plan is developed.
The implementation phase can be viewed as a period of actual closure operations, followed by facility closeout (postmortem). Here, too, there may be some overlap of the two activities. Finally, the facility site may undergo postclosure activities in accordance with agreed-upon regulatory requirements.
TABLE C-1 Closure Planning and Implementation Activities
Planning Phase |
Field Implementation Phase |
|||
Assessment and Decision Making |
Closure Plan Development |
Closure Operation |
Facility Closeout |
Postclosure Activities |
Establish closure objectives Determine facility end use Establish regulatory requirements Establish cost and schedule goals Characterization Obtain samples and analyses Identify technology needs Evaluate closure alternatives Decision making Select closure alternative Establish schedule and funding profile Establish public and community communications program |
Finalize end-state requirements Establish acquisition strategy Complete engineering plans Technical baseline Permits and licenses Waste quantities and management plan Decontamination plan Sampling and analysis plan D&D sequence Develop schedule baseline Develop cost baseline and manpower estimates Develop health and safety plan Develop special technology Prepare facility closure plan Implement quality assurance plan |
System decontamination Removal of systems, structures, and components Monitoring of areas, workers, and materials Waste management activities Concurrent coprocessing Program closure activities and operations Enforce worker safety Install special systems (e.g., CMS) Partial release of areas to EPA closure criteria |
Perform area sampling and analyses Issue closure report and facility certification Regulatory reviews Facility released for end use Publish lessons learned |
Periodic monitoring and sampling per regulatory requirements |