Appendix C
Closure Planning and Implementation

Table C-1 lists activities that are likely relevant to closure of any industrial or government facility. Not all of the activities are necessarily applicable to a particular closure situation. The indented items in the table are primarily illustrative and are not intended to be all inclusive, but rather to indicate the types of activities required at those stages of the closure process under which they appear.

The planning phase consists of (1) an assessment and decision-making period in which general overall objectives and criteria are formulated and (2) a closure plan development period when plans are formulated and written. In practice, there can be considerable overlap between assessment and decision making as a detailed plan is developed.

The implementation phase can be viewed as a period of actual closure operations, followed by facility closeout (postmortem). Here, too, there may be some overlap of the two activities. Finally, the facility site may undergo postclosure activities in accordance with agreed-upon regulatory requirements.

TABLE C-1 Closure Planning and Implementation Activities

Planning Phase

Field Implementation Phase

Assessment and Decision Making

Closure Plan Development

Closure Operation

Facility Closeout

Postclosure Activities

Establish closure objectives

Determine facility end use

Establish regulatory requirements

Establish cost and schedule goals

Characterization

Obtain samples and analyses

Identify technology needs

Evaluate closure alternatives

Decision making

Select closure alternative

Establish schedule and funding profile

Establish public and community communications program

Finalize end-state requirements

Establish acquisition strategy

Complete engineering plans

Technical baseline

Permits and licenses

Waste quantities and management plan

Decontamination plan

Sampling and analysis plan

D&D sequence

Develop schedule baseline

Develop cost baseline and manpower estimates

Develop health and safety plan

Develop special technology

Prepare facility closure plan

Implement quality assurance plan

System decontamination

Removal of systems, structures, and components

Monitoring of areas, workers, and materials

Waste management activities

Concurrent coprocessing

Program closure activities and operations

Enforce worker safety

Install special systems (e.g., CMS)

Partial release of areas to EPA closure criteria

Perform area sampling and analyses

Issue closure report and facility certification

Regulatory reviews

Facility released for end use

Publish lessons learned

Periodic monitoring and sampling per regulatory requirements

Suggested Citation:"Appendix C: Closure Planning and Implementation." National Research Council. 2002. Closure and Johnston Atoll Chemical Agent Disposal System. Washington, DC: The National Academies Press. doi: 10.17226/10349.
×
This page in the original is blank.
Suggested Citation:"Appendix C: Closure Planning and Implementation." National Research Council. 2002. Closure and Johnston Atoll Chemical Agent Disposal System. Washington, DC: The National Academies Press. doi: 10.17226/10349.
×
Page 51
Suggested Citation:"Appendix C: Closure Planning and Implementation." National Research Council. 2002. Closure and Johnston Atoll Chemical Agent Disposal System. Washington, DC: The National Academies Press. doi: 10.17226/10349.
×
Page 52
Next: Appendix D: JACADS Sampling and Analysis Plan Maps and Photographs »
Closure and Johnston Atoll Chemical Agent Disposal System Get This Book
×
Buy Paperback | $29.00 Buy Ebook | $23.99
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF
  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!