Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project (2003)
Board on Infrastructure and the Constructed Environment (BICE)
National Academy of Engineering (NAE)
Transportation Research Board (TRB)

Citation Manager

. "2. Cost and Schedule Procedures." Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project. Washington, DC: The National Academies Press, 2003.

Please select a format:

BibTeX EndNote RefMan


Page
14
bottomleft bottomright

The following HTML text is provided to enhance online readability. Many aspects of typography translate only awkwardly to HTML. Please use the page image as the authoritative form to ensure accuracy.


FIGURE 2.2 Cost History and Scope Evolution, in millions of dollars (Source: W.Edwards, “Project History,” Presentation to the Committee on October 21, 2002)

FIGURE 2.3 Project Schedule Escalation (Source: W.Edwards, “Project History,” Presenation to the Committee on October 21, 2002)