FCF DEMONSTRATION PROGRAM, REVISED SCOPE, JANUARY 1996

FY 1996

Complete NEPA review

02/96

DOE authorization to operate

02/96

Process first batch of 4 driver assemblies

03/96

Initiate cold large-scale mineral waste form tests

03/96

Produce first low-enriched uranium storage ingot

06/96

Complete electrometallurgical treatment of 16 driver assemblies

09/96

FY 1997

Complete electrometallurgical treatment of 48 driver assemblies

09/97

Install high-throughput electrorefiner in FCF

09/97

Initiate hot mineral waste form sample production

09/97

FY 1998

Complete electrometallurgical treatment of 36 driver assemblies

03/98

Complete electrometallurgical treatment of 25 blanket assemblies

09/98



The National Academies | 500 Fifth St. N.W. | Washington, D.C. 20001
Copyright © National Academy of Sciences. All rights reserved.
Terms of Use and Privacy Statement



Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter. Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.

Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.

OCR for page 17
ELECTROMETALLURGICAL TECHNIQUES FOR DOE SPENT FUEL TREATMENT: A STATUS REPORT ON ARGONNE NATIONAL LABORATORY'S R&D ACTIVITY B FCF DEMONSTRATION PROGRAM, REVISED SCOPE, JANUARY 1996 FY 1996 Complete NEPA review 02/96 DOE authorization to operate 02/96 Process first batch of 4 driver assemblies 03/96 Initiate cold large-scale mineral waste form tests 03/96 Produce first low-enriched uranium storage ingot 06/96 Complete electrometallurgical treatment of 16 driver assemblies 09/96 FY 1997 Complete electrometallurgical treatment of 48 driver assemblies 09/97 Install high-throughput electrorefiner in FCF 09/97 Initiate hot mineral waste form sample production 09/97 FY 1998 Complete electrometallurgical treatment of 36 driver assemblies 03/98 Complete electrometallurgical treatment of 25 blanket assemblies 09/98