ied secondary waste materials including halogenated waste is still required. These changes and improvements may require several iterations before satisfactory results are achieved.


Recommendation 6-4. A test plan should be prepared for all design changes identified for the MPT but not verified in the TRRP tests. This test plan should be conducted at the fabrication facility and should include time for the repeated trials needed to arrive at acceptable performance for the overall full-scale MPT. A similar test plan should be prepared for testing the integrated full-scale off-gas treatment system for the MPT at BGCAPP. This test plan should include the testing of a full range of secondary, energetics batch hydrolyzer, and closure waste at the full-scale design rates.