TABLE 2-1 Status of Closure Planning Documentation for Each Baseline Chemical Agent Disposal Facility

Planning Component

Anniston Chemical Agent Disposal Facility (ANCDF)

Pine Bluff Chemical Agent Disposal Facility (PBCDF)

Tooele Chemical Agent Disposal Facility (TOCDF)

Chemical Agent Munitions Disposal System (CAMDS)

Umatilla Chemical Agent Disposal Facility (UMCDF)

Site Facility Closure Plan (FCP)

The RCRA FCP has been submitted, approval expected in January 2011. Final plan will follow this approval, estimated for March 2011.

The Facility Closure Plan (PB-PL-110) was issued in February 2010.

The FCP is scheduled for issuance in September 2010.

Scope is captured in the Facility Decontamination and Disposition Plan (FDDP) issued in March 2010.

The FCP is included in the Decommissioning Plan (UM-PL-108) issued in May 2010.

Closure Planning Implementation Strategy (CPIS)

The ANCDF CPIS was issued in November 2008.

The CPIS is included in the FCP (PB-PL-110) and in the Decommissioning Plan (PB-PL-108) issued in February 2010.

The CPIS is included in the FCP that is scheduled for issue September 2010 and in the Decommissioning Plan (scheduled for issue in August 2010). For the preparation of the CPIS TOCDF used the Capstone document that was developed during the Programmatic Closure Project, the CMA closure guide, and other programmatic documents as a basis.

Scope is captured in the FDDP and was issued in March 2010.

The CPIS is included in the Decommissioning Plan (UM-PL-108) issued in May 2010.

Decommissioning Plan

The ANCDF Decommissioning Plan is included in the Facility Disposition Plan issued on March 29, 2010.

The PBCDF Decommissioning Plan (PB-PL-108) was issued in February 2010.

The Decommissioning Plan is part of the FDDP. The FDDP is scheduled for issuance in August 2010.

This scope is captured in the FDDP issued in March 2010.

The Decommissioning Plan (UM-PL-108), rev. 1, was issued in May 2010.

Decontamination Plan

ANCDF is updating the Decontamination Plan that was included in the Permit modification that was submitted to ADEM for review on April 29, 2010. Approval is expected by March 2011.

The Decontamination Plan (PB-PL-118) was issued on February 12, 2010.

The Decontamination Plan is part of the FDDP. The FDDP is scheduled for issuance in July 2010.

This scope is captured in the FDDP issues in March 2010.

Content on decontamination was included in the RCRA FCP. ODEQ approval of the FCP is expected in September 2010.

Demolition Plan

In lieu of a separate distinct Demolition Plan ANCDF will provide detailed demolition scope of work in the Closure Work Proposal and Engineering Work Packages for the areas to be demolished along with an Estimate and a Request for Proposal to be put out for bid to qualified demolition contractors. The detailed packages for the MDB and the Pollution Abatement Areas (the only areas to undergo mass demolition) are due to be issued by June 1, 2011.

The Demolition Plan will be addressed in the Final Site Decontamination Decommissioning and Demolition (DDD) Package (DDD-16-040). Issuance of this plan is estimated in January 2011.

The TOCDF Demolition Plan is part of the Demolition and Disposition Plan. Issuance on this plan is estimated in September 2010.

The CAMDS Demolition Plan is being developed with the TOCDF Demolition and Disposition Plan and is scheduled to be issued in September 2010.

Content on demolition was included in the RCRA FCP. This plan is currently under review by ODEQ. (PMR-09-006). Approval is expected in September 2010.