Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 33
4
Design and Development
This chapter considers three key aspects of industrial engineering
methods for system design and development: (1) the need to assess the
technological maturity of subsystems and components prior to insertion
in a defense system in development, (2) the need to use objective metrics
for assessment, and (3) the advantages of staged acquisition. These topics
were discussed at the panel’s workshop (see Appendix B).
THE IMPORTANCE OF TECHNOLOGICAL MATURITY
Consequences of Using Immature Technology
Conclusion 4: The maturity of technologies at the initiation of an
acquisition program is a critical determinant of the program’s suc -
cess as measured by cost, schedule, and performance. The U.S.
Department of Defense (DOD) continues to be plagued by prob-
lems caused by the insertion of immature technology into the criti-
cal path of major programs. Since there are DOD directives that are
intended to ensure technological readiness, the problem appears
to be caused by lack of strict enforcement of existing procedures.
There are many studies that describe problems caused by insert-
ing insufficiently mature technologies in the critical path of acquisition
programs for both DOD and commercial companies (see, e.g., National
Research Council [2010a]): see Box 4-1. This is a primary cause of schedule
33
OCR for page 34
34 INDUSTRIAL METHODS FOR EFFECTIVE DEVELOPMENT AND TESTING
BOX 4-1
Use of Immature Technologies: Consequences
Four examples of conclusions from major studies of the consequences of using
immature technologies are noteworthy.
1. The “Streamlining Study” of the Defense Science Board was never pub-
lished, but the Institute for Defense Analysis (1991) produced IDA Paper
P-2551, which covered some 100 major defense acquisition programs,
reached a firm conclusion that failure to identify technical issues, as well
as real costs, before entering into full-scale development—now referred to
as engineering and manufacturing development—was the overwhelming
cause for subsequent schedule delays and the resulting cost increases.
2. The U.S. General Accounting Office (1992:49) stated: “Successful programs
have tended to pursue reasonable performance objectives and avoid the
cascading effects of design instability. . . .”
3. More than a decade later, the U.S. Government Accountability Office (2004:2)
found: “FCS [Future Combat System] is at significant risk for not delivering
required capability within budgeted resources. Three-fourths of FCS needed
technologies were still immature when the program started. The first proto-
types of FCS will not be delivered until just before the production decision.
Full demonstration of FCS ability to work as an overarching system will not
occur until after production has begun.” The report also concluded that based
upon the experiences of past programs, the FCS strategy was likely to result
in cost overruns and delays. In fact, the FCS program was terminated about
6 years later.
4. At a November 30, 2005, meeting of the Naval Studies Board of the National
Research Council, the then newly appointed Department of the Navy acqui-
sition executive, Dr. Delores Etter reported that she had just attended her
first Defense Acquisition Board review, which was for the DDG-1000 (guided
missile destroyers) program. She had anticipated that technologies for the
program would be an issue with the Undersecretary of Defense (AT&L),
DOD’s top acquisition executive but they were not. The acquisition team
had identified 10 high-risk areas that would have to mature in parallel for
the acquisition program to meet its performance goals, and the program
was approved for entry into engineering and manufacturing development.
About 3-1/2 years later, in the summer of 2008, the Department of the
Navy requested, and received approval for, termination of the prohibitively
expensive program after having spent $10 billion on the first two ships.
slippage and cost growth in DOD program acquisition, and it often results
from the overly optimistic confidence of developers in their abilities to
convert technological advances into developing reliable components and
subsystems and doing so in a timely manner. The terminations of the FCS
(the Army’s future combat system) and DDG-1000 (the Navy’s Zumwalt
class of guided missile destroyers) programs years after their entry into
OCR for page 35
35
DESIGN AND DEVELOPMENT
engineering and manufacturing development are strong evidence of the
very adverse result of incorporating multiple immature technologies in
the critical paths of large complex product developments.
The dangers of immature technology are just as critical in the com -
mercial sector. Globalization and rapid advances in technology have put
immense pressure on industry to offer “on-going” new products with the
latest technological features. This pressure in turn has led to shorter prod-
uct development cycles, increasing the risk of introducing immature and
infeasible new technologies. Unlike the situation in DOD, product launch
dates in many parts of the commercial sector, such as the automotive
industry, are sacred. Any slippage in a product launch date has serious
financial implications for automotive companies: they range from mil -
lions of dollars in lost revenues for every day’s delay in product launch
to inflicting major chaos in the entire supply chain, with a supplier who
may be 10,000 miles away, to the marketing group that has already made
extensive plans and commitments. And launching a product that is not
fully ready also has serious cost implications, including high warranty
costs and, more importantly, lost customer goodwill. Clearly, a major slip
in quality at launch has severe consequences; the product may never be
able to sell at planned volumes, resulting in major losses for the company.
Faced with the above challenges, top management in the commercial
sector is increasingly approving “pre-spend” money for major programs.
This pre-spend money is spent on conducting technical feasibility stud-
ies on perceived program challenges while the program details are still
being finalized for program approval.1 The challenges can include a wide
range of activities, such as establishing feasibility of aggressive exterior
styling, kicking off die development for major body panels that have long
lead times, and studying the feasibility of adapting a new powertrain
and getting better cost estimates on the project. The pre-spend money is
often 1-2 percent of the cost of the overall program. In recent years, major
industry programs have been cancelled or delayed on the basis of the
results of the technical feasibility analysis conducted through pre-spend
money, thereby enabling the automakers to prevent major losses later in
the process.
Speakers at the workshop emphasized the importance of getting
considered opinions from qualified domain experts about the adequate
maturity of new technologies or about new applications of existing tech -
nologies. It was evident that the commercial sector also places a great deal
1DOD has provided analogous funding for reducing major defense acquisition program
technology risks and for demonstrating the value of new technologies in separately funded
“advanced technology demonstrations” and now in the new technology development phase
of major defense acquisition programs.
OCR for page 36
36 INDUSTRIAL METHODS FOR EFFECTIVE DEVELOPMENT AND TESTING
of emphasis on not risking failure by including an unproven technology
advance in a critical path of a new program.
There are indeed examples in DOD where programs have managed
this issue successfully,2 so the department has exhibited the capability to
properly assess technological maturity. What is needed is a way to instill
a willingness to acquire independent expert input and a collaborative
spirit in those leading future programs. Such a culture is the responsibil -
ity of the most senior DOD acquisition executives and of the secretary of
defense. The problems result from the different cultures and practices of
the different participants in the requirements development process, the
acquisition process, and the resource allocation process—not in stated
DOD policies and procedures contained in DOD directives.
The Technology Readiness Assessment Deskbook
The current U.S. Department of Defense Instruction (DODI) 5000.02 of
December 8, 2008 (which is consistent with the current DODI 5000.01 cer-
tified current as of November 20, 2007) contains the following guidance/
requirement regarding technology for acquisition programs3:
Technology for use in product development (starting at Milestone B) “shall
have been demonstrated in a relevant environment or, preferably, in an
operational environment [emphasis added] to be considered mature enough
to use for product development. . . . If technology is not mature, the DOD
component shall use alternative technology that is mature and that can
meet the user’s needs or engage the user in a dialog on appropriately
modifying the requirements.” In addition, the current 2009 Technology
Readiness Assessment (TRA) Deskbook (p. C-5) defines “hardware” readiness
levels as follows:
• TRL 7 as “System prototype demonstrated in an operational environment”
and
• TRL 6 as “System/subsystem model or prototype demonstrated in a rel-
evant environment.”
2A recent report on the F-A-18E/F Super Hornet Development Program is an example of
the Navy’s ability to control the technological maturity in a major DOD acquisition program.
As noted in the report (Center for Naval Analysis, 2009:16), the program “did not over reach
on technology or capability demands.” The collaboration of all the parties “ allowed the E/F
program to develop a clear and focused set of requirements that was simply stated and
understood by all. The technology for all requirements was either already in hand, or all
agreed to defer the requirement to a later block upgrade when the technology was ready”
(p. 28).
3See DODI 5000.02 Enclosure 2, paragraph 5.d. (4). Available: http://www.dtic.mil/whs/
directives/corres/pdf/500002p.pdf [August 2011].
OCR for page 37
37
DESIGN AND DEVELOPMENT
The current (2009) Technology Readiness Assessment (TRA) Deskbook
does not refer to the “preferred TRL 7” when describing the readiness
assessment process for evaluating technology readiness for Milestone B.
Rather, it is Title 10 of the U.S. Code (Section 2366b) that requires that the
milestone decision authority (the person so designated for each program)
certify technologies used at Milestone B have been demonstrated to per-
form at level TRL6.4 This was not true in the previous version of the TRA
Deskbook, which followed the DODI 5000.02 guidance.5
The current 2009 TRA Deskbook also describes an elaborate process
for the preparation of technology readiness assessments involving a sug -
gested schedule of 11 months and the selection of an integrated product
team consisting of a balanced set of subject matter experts (SMEs) from
DOD components, other government agencies, and possibly, nongovern-
ment entities. Significant attention and space are devoted to the authori-
ties of various parties, the “equitable processes” for selecting subject
matter experts, and the desire to arrive at a single agreed-on readiness
assessment. However, how to deal with different interpretations of, or
opinions on, technological maturity is not a significant subject in the
Deskbook.
The panel concludes that the philosophy behind DODI 5000.02 is
adequate and that the statements about the preferred levels of technology
readiness (i.e., TRL 7) for approval at Milestone B are appropriate. How-
ever, we have two concerns. One is that the guidance for implementation
in the 2009 TRA Deskbook is not adequate (i.e., the sole focus on TRL 6 for
Milestone B approval). The second is the insufficient discipline exhib-
ited by most program managers and most DOD acquisition executives,
with regard to both the technological maturity for individual compo -
nents and the integration of multiple components involving interrelated
technologies.
Implementation of DOD Instructions and Directives
The panel also concludes that there is a significant weakness in DOD’s
implementation of its own Directive and Instruction for acquisition pro-
4See DOD Technology Readiness Assessment (TRA) Deskbook, Section 1, paragraph 1.3.1.
Available: http://www.dod.gov/ddre/doc/DoD_TRA_July_2009_Read_Version.pdf [Au -
gust 2011].
5The 2003 TRA Deskbook stated (available: http://www.dod.mil/ddre/doc/May2005_
TRA_2005_D0D.pdf [August 2011]):
• central theme of the acquisition process is that technology employed in system devel-
a
opment should be “mature” before system development begins (see p. ES-1);
• for Milestone B, readiness levels of at least TRL6 are typical (TRL 7 preferred); and
• for Milestone C, readiness levels of at least TRL 8 are typical (TRL 9 preferred).
OCR for page 38
38 INDUSTRIAL METHODS FOR EFFECTIVE DEVELOPMENT AND TESTING
grams. The proposed solution should not lower the standard in DOD’s
instruction to the level of just what is required by the U.S. Code (i.e., what
happened in the revision of the TRA Deskbook from 2003 to 2009). Good
industry practices as well as past successful (in contrast with unsuccess-
ful) DOD acquisition programs support a higher level of technological
readiness than has been, and is being, exhibited in most recent and cur-
rent DOD acquisition programs. This view is strongly supported by the
report of the first Director of Defense Research and Engineering (DDR&E)
to Congress on the technical maturity and integration risk of major DOD
acquisition programs.6
The comments from industry participants at the workshop and from
several GAO reports (U.S. General Accounting Office, 1999; U.S. Govern -
ment Accountability Office, 2006) indicate that, in general, technological
readiness levels for commercial products are higher than they are for
DOD programs. There are several possible reasons for this difference. One
is that commercial products are vulnerable to product liability lawsuits
and product warranties, both of which drive comprehensive performance
and reliability testing prior to product introduction on the market. In
contrast, with very few exceptions, DOD does not require warranties, nor
is the original equipment manufacturer (the contractor) held liable for
deficiencies, as are commercial manufacturers. Additionally, most DOD
products are at the leading edge of technology in the hope of providing
a competitive edge over potential adversaries. Notwithstanding these
differences, DOD places too little attention, in general, on technological
readiness prior to beginning system development.
Some of the industry participants at the panel’s workshop suggested
that the real problem might be the lack of adherence to criteria in the
assessment of new technological readiness. In addition, it was noted that
there may be poor risk assessment of the effects of technology insertion
and integration on systems.
Recommendation 2: The U.S. Department of Defense (DOD) Under
Secretary for Acquisition, Technology, and Logistics (USD-AT&L)
6This report (U.S. Department of Defense, 2010) was written to comply with the Weap -
ons Systems Acquisition Reform Act of 2009 (Public Law 111-23), which requires that the
DDR&E submit an annual report. The report, covering 2009, was critical of the technological
readiness levels assigned to technologies in the Joint Tactical Radio System and wideband
networking waveform, as well as the technological readiness levels used in the Army’s
first increment of its brigade combat team modernization effort. The particular programs
reported on are not as important as the fact that the DDR&E’s critical assessment was either
not available to the relevant acquisition decision authority before Milestone B or it was
available to, but not appropriately acted on by, the cognizant decision authority before or at
the Milestone B decision point.
OCR for page 39
39
DESIGN AND DEVELOPMENT
should require that all technologies to be included in a formal acqui-
sition program have sufficient technological maturity, consistent with
TRL (technology readiness level) 7, before the acquisition program
is approved at Milestone B (or earlier) or before the technology is
inserted in a later increment if evolutionary acquisition procedures
are being used. In addition, the USD-AT&L or the service acquisi-
tion executive should request the director of defense research and
engineering (DOD’s most senior technologist) to certify or refuse to
certify sufficient technological maturity before a Milestone B deci-
sion is made. The acquisition executive should also
• eview the analysis of alternatives assessment of technological
r
risk and maturity;
• btain an independent evaluation of that assessment, as required
o
in DODI 5000.02; and
• nsure, during developmental test and evaluation, that the mate-
e
riel developer assesses technical progress and maturity against
critical technical parameters that are documented in the test and
evaluation master plan.
We are aware that a substantial part of the above recommendation
is currently required by law or by DOD instructions. In particular, DODI
5000.02 obligates DDR&E to perform an independent technology readiness
assessment of major defense acquisition programs prior to Milestones B
and C. The director of developmental test and evaluation is supposed to
provide an assessment of the test process and results to support this readi-
ness review. Furthermore, DODI 5000.02 requires a cost assessment and
program evaluation. In addition, all of the military services currently per-
form an operational test readiness review and must certify that the system
is ready for dedicated initial operational test and evaluation. These certi -
fications, required by DODI 5000.02, have varying degrees of depth and
credibility. Recently, the USD-AT&L began performing an independent
assessment of operational test readiness, and the director of developmental
test and evaluation is tasked to support this effort.
But the panel believes that DOD has been moving in the wrong direc-
tion regarding enforcement of an important and reasonable policy as
stated in DODI 5000.02. The recommendation of an earlier report (National
Research Council, 2006) was also concerned with immature technologies.
Our recommendation supports and modifies the earlier one. Our intent is
to make it more difficult for advocates to incorporate immature technolo-
gies into the critical paths of major DOD acquisition programs.
OCR for page 40
40 INDUSTRIAL METHODS FOR EFFECTIVE DEVELOPMENT AND TESTING
USE OF OBJECTIVE METRICS FOR ASSESSMENT
Conclusion 5: The performance of a defense system early in devel-
opment is often not rigorously assessed, and in some cases the
results of assessments are ignored; this is especially so for suit -
ability assessments. This lack of rigorous assessment occurs in the
generation of system requirements; in the timing of the delivery of
prototype components, subsystems, and systems from the devel -
oper to the government for developmental testing; and in the deliv-
ery of production-representative system prototypes for operational
testing. As a result, throughout early development, systems are
allowed to advance to later stages of development when substantial
design problems remain. Instead, there should be clear-cut decision
making during milestones based on the application of objective
metrics. Adequate metrics do exist (e.g., contractual design speci -
fications, key performance parameters, reliability criteria, critical
operational issues). However, the primary problem appears to be a
lack of enforcement.
There should be clear-cut decision making during milestones based
on objective metrics. Adequate metrics do exist (e.g., contractual design
specifications, key performance parameters, reliability criteria, critical
operational issues). However, the primary problem, once again, appears
to be lack of enforcement by the component and Office of the Secretary of
Defense senior managers responsible for acquisition program oversight.
More than one speaker at the workshop said that it is key that defense
systems should not pass milestones unless there is objective, quantitative
evidence that major design thresholds, key performance parameters, and
reliability criteria have been met or can be achieved with minor product
changes.
The lack of consistent use of objective, quantitative metrics occurs at
many points during defense acquisition:
• the generation of system requirements (see Chapter 3);
• the timing of the delivery of prototype components, subsystems,
and systems from the developer to the government for develop-
mental testing;
• the delivery of production-representative system prototypes for
operational testing; and
• the passage of systems into full-rate production.
The transition from developmental testing to dedicated initial opera -
tional test and evaluation (IOT&E) is often driven by schedules rather
than the availability of production-representative articles with mature
OCR for page 41
41
DESIGN AND DEVELOPMENT
systems. Articles should not be delivered to IOT&E until the system is
performing at a level that will meet operational requirements, as deter-
mined by a disciplined operational test readiness review, noted above.
It is counterproductive to place a system into operational testing when
its reliability is 20 percent or 30 percent below what is required, with the
hope that enough failure modes will be discovered during operational
testing to raise the reliability to the required level. More often than not,
such a system will need further development and its operational testing
will likely need to be repeated.
The passage of systems into full-rate production is typically justified
on the basis of the results of a comprehensive operational test, which
includes assessment of both effectiveness and suitability. From 2001
through 2006, DOT&E found that 15 of 28 systems undergoing IOT&E
either were not operationally suitable or were suitable with limitations. Of
these 28 systems, 9 were found to be either not effective or effective with
significant deficiencies. However, all these systems were fielded, often
with the deficiencies that had been identified during initial operational
test and evaluation (see Defense Science Board, 2008).
Although the decision as to which systems in development are and
are not fielded is complex, having a greater degree of rigor in decisions
would reduce the chance of systems being delivered to the field and fail -
ing to meet their requirements. Such failure is particularly common with
respect to system suitability. In such cases, systems often do not go back
to development. Rather, a greater number of systems are purchased to
ensure adequate availability—since systems may fail in the field or be
under repair—thereby greatly increasing the life-cycle costs.7
STAGED DEVELOPMENT WITH AN EMPHASIS ON SOFTWARE
As noted in another NRC report (2010:1): “Current fielding cycles
are, at best, two to three times longer than successful commercial equiva-
lents . . . representing multiyear delays in delivering improved IT systems
to warfighters and the organizations that support them. As a result, the
DOD is often unable to keep pace with the rate of IT innovation in the
commercial marketplace. . . .” A particular issue is the growing impor-
7Adolph (2010:53) provides an excellent discussion of these issues: “Rigorous enforcement
of key requirement thresholds, along with emphasis on performance in the intended mission
environment, should be the norm when entering System Development and Demonstration.
Issues that need to be addressed in relation to requirements setting include technology
readiness, the translation of requirements into design criteria, with attention to testability
at the subsystem and system levels, as well as defining thresholds for key performance
parameters.”
OCR for page 42
42 INDUSTRIAL METHODS FOR EFFECTIVE DEVELOPMENT AND TESTING
BOX 4-2
Benefits of Agile Development
In examining current DOD processes for acquiring IT systems and compar-
ing them with the processes adopted by leading-edge firms in the commercial
sector, the committee found stark differences. DOD is hampered by a culture and
acquisition-related practices that favor large programs, high-level oversight, and a
very deliberate, serial approach to development and testing (the waterfall model).
Programs that are expected to deliver complete, nearly perfect solutions and that
take years to develop are the norm in DOD. In contrast, leading-edge commercial
firms have adopted agile approaches that focus on delivering smaller increments
rapidly and aggregating them over time to meet capability objectives. Moreover,
DOD’s process-bound, high-level oversight seems to make demands that cause
developers to focus more on process than on product, and end-user participation
often is too little and too late. These approaches are counter to agile acquisition
practices in which the product is the primary focus, end users are engaged early
and often, oversight of incremental product development is delegated to the low-
est practical level, and the program management team has the flexibility to adjust
the content of the increments in order to meet delivery schedules. The committee
concluded that the key to resolving the chronic problems with DOD acquisition
of IT systems is for DOD to adopt a fundamentally different process—one based
on the lessons learned in the employment of agile management techniques in
the commercial sector. Agile approaches have allowed their adopters to outstrip
established industrial giants that were beset with ponderous, process-bound, in-
dustrial-age management structures. Agile approaches have succeeded because
their adopters recognized the issues that contribute to risks in an IT program and
changed their management structures and processes to mitigate the risks . . . for
the DOD to succeed in adopting new approaches to IT acquisition, the first step
is to acknowledge that simply tailoring the existing processes is not sufficient.
DOD acquisition regulations do permit tailoring, but the committee found few
examples of the successful application of the current acquisition regulations to IT
programs, and those that were successful required herculean efforts or unique cir-
cumstances. Changes broader than tailoring are necessary; they must encompass
changes to culture, redefinition of the categories of IT systems, and restructured
procurement, development, and testing processes as identified in this report. In
the aggregate, these changes must realign processes that today are dominated by
deliberate approaches designed for the development of large, complex, hardware-
dominated weapons systems to processes adapted to the very different world of
software-dominated IT systems.”
SOURCE: National Research Council (2010a:ix-x).
OCR for page 43
43
DESIGN AND DEVELOPMENT
tance of software (sub)systems, and the functionality of defense systems
is increasingly dependent on extremely complicated software.
Conclusion 6: There are substantial benefits to the use of staged
development, with multiple releases, of large complex systems,
especially in the case of software systems and software-intensive
systems. Staged development allows for feedback from customers
that can be used to guide subsequent releases.
The workshop speakers on software systems emphasized staged
development as part of “agile” development processes: see Box 4-2. In
the panel’s view, many elements of the agile processes are not new. What
is needed, however, is a systematic approach that ensures that these prac -
tices are consistently used throughout system development. If properly
implemented, these practices would ensure that defects and weaknesses
in a system are detected early so that they can be addressed inexpensively.
Staged development appears to be natural for large-scale complex
software systems. The use of staged development may also be appropriate
for some hardware systems: two examples of situations in which substan-
tial upgrades to fielded systems provided a substantial increase in war
fighting capability are the Apache helicopter and the M-1 tank.
A good example of the applicability of agile development to hardware
systems is that of the F-A-18E/F, a twin-engine carrier-based multirole
fighter aircraft mentioned in footnote 3, where it was stated that the tech-
nologies were not inserted in a release until they were determined to be
fully ready. This approach is consistent with the agile philosophy. How-
ever, each of the stages must retain the functionality that all the predeces-
sor systems had, at the very least to satisfy the natural expectations of the
customer over time. We note, however, that with fluid requirements, the
most challenging job is to select the systems architecture in a way that
can accommodate the likely changes in requirements over the several
anticipated stages of development. Meeting this challenge requires fore -
sight as to what capabilities may ultimately be requested and in designing
the architecture in a way that does not make the ultimate system overly
complicated, heavy, or expensive.
OCR for page 44