4
Cost Assessment
The statement of task for this study (see Appendix A) requested that the committee address the methodologies
used in the current cost estimates for a reusable booster system (RBS), including the modeling methodology used
to frame the business case for an RBS. This chapter addresses the results of the committee's review and assessment
of these issues.
The basic premise behind a new RBS for future space launch of Air Force space systems is that if such a
reusable launch system, including all associated infrastructure and support services can be developed, flight-
certified, and operated at an "affordable" cost (meaning substantially less costly than a present Evolved Expendable
Launch Vehicle [EELV]), subsequent implementation of the new space launch system would bring a large reduc-
tion in space launch costs and, therefore, overall life cycle costs (LCC). As discussed in Chapter 2, the savings
associated with use of an RBS for a national security payload manifest of 8 to 10 launches per year is estimated
to be up to 50 percent of the current prices being paid by the Air Force for EELV services.
If an affordable RBS can be developed, these significant cost savings can be realized. This logical conclusion is
supported using the cost history for fully developed EELVs--that is, recurring cost per launch. This cost history data-
base includes the experience with the previous family of Air Force expendable launches--Delta II, Atlas II and III,
Titan IV, Delta IV and Atlas V (the last two being part of the current EELV launcher family provided by United
Launch Alliance). Review of the recurring cost histories of these launchers indicates that on average about 70 per-
cent of the recurring costs arise from the expendable vehicle hardware that is "thrown away" during each launch. 1
The rest of the launch services cost consists of operations, engineering support, and management. The 70 percent
hardware cost is a weighted approximation average for all expendable launch vehicles listed above. The hardware
costs actually range from a low of about 55 percent (Titan IV) to a high of about 85 percent (Delta II). This strongly
suggests that reuse of the first-stage flyback booster for an RBS for, say, 50 to 100 times, with a scheduled overhaul
after 10 flights and engine replacement every 20 flights, could readily result in significant cost savings, maybe
upwards of 50 percent as predicted by the Aerospace Corporation cost analysis. 2
1 R.L. Sackheim, Overview of United States space propulsion technology and associated space transportation systems, Journal of
Propulsion and Power 22(6):1315, 2006.
2Air Force Space and Missile Systems Center (AFSMC), "Reusable Booster System Costing, SMC Developmental Planning," presentation
to the Committee for the Reusable Booster System: Review and Assessment, February 15, 2012. Approved for Public Release.
53
OCR for page 54
54 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
The following subsections present the results of this assessment with the baseline cost modeling approach
described and an assessment of the individual models, where possible. The chapter concludes with a discussion
of the overall RBS business case.
4.1 BASELINE COST MODELING APPROACH AND ASSESSMENT OVERVIEW
The Air Force cost modeling approach uses a mixture of models and methodologies for estimating the various
RBS elements. The configurations shown in Figure 4.1 represent the baseline flight vehicle designs examined by
the committee. These include the reusable booster demonstrator (RBD) to be used to demonstrate and validate
various aspects of the reusable booster design and operation as well as the RBS, which includes a heavy-lift variant
to support larger payloads. The costs associated with the Air Force Research Laboratory's (AFRL's) funding of
technology development efforts, including the Pathfinder small-scale demonstrator, are not included in the baseline
costing, but they are relatively small.
The committee considered a number of scenarios for RBS system development. Four of them formed the
basis for the analysis:
· Scenario 1: Baseline. The EELV program is assumed to end in 2031, and RBS development occurs in a time
frame that would support the entire launch manifest. RBS development includes the mid-scale RBS demonstrator and
SES-2 Modeled as Castor 30 Solid Motor
SES-3 Modeled as Star 63D Solid Motor
Star 63D
LES
LES
1 RS-25E Engine
Star 63D
Castor 30
RBD RBS RBS RBS
1 NK-33 Engine 5 AJ-26 Engines
FIGURE 4.1 RBS flight hardware elements. Major elements include the RBD, the LES, the SES, and RBS. NOTE: LES, large
expendable stage; RBD, reusable booster demonstrator; RBS, reusable booster system; SES, small expendable stage. SOURCE:
Air Force Space and Missile Systems Center, SMC Developmental Planning, "Reusable Booster System Costing," presentation
to the committee, February 15, 2012. Approved for Public Release.
Figures 2-1 and 4-1
R02338
vector editable
OCR for page 55
COST ASSESSMENT 55
assumed use of the "Americanized" version of the Russian NK-33 oxygen-rich staged combustion (ORSC) engine
(i.e., a domestic AJ-26 engine). Under this baseline scenario, the time frame of the AFRL-funded hydrocarbon-fueled
booster technology development does not significantly impact the booster main propulsion system.
· Scenario 2: Extended EELV. The EELV program is extended with operations until 2040, which allows
completion of the AFRL-funded hydrocarbon-fueled booster technology development and development of an
RD-180 replacement engine for the Atlas V. This engine would be of the thrust class of the RD-180 and would be
built using technology currently under development in the AFRL Hydrocarbon Boost Technology program. This
same replacement engine would be used in an RBS system. The mid-scale RBD is again assumed in the develop-
ment program.
· Scenario 3: Accelerated RBS. This scenario was explored to examine implications of accelerating the end
of the EELV program to 2025. This scenario uses the domestic version of the AJ-26 engine but eliminates the
mid-scale RBD and proceeds directly to full-scale RBS development.
· Scenario 4: Commercial partnership. This scenario assumes a government-funded program to develop and
conduct the RBD using the domestic AJ-26 engine, with the full-scale RBS developed by industry to support both
Air Force and commercial spacelift needs.
Additional variations were explored within each of these four scenarios, including options to not include the
heavy-lift vehicle in either the RBS development or its operations. These options were explored because the com-
mittee believes that the heavy-lift requirement places great challenges on a system that is already challenged by
the technical risks discussed in Chapter 3. The requirement for a dual-reusable booster heavy-lift configuration
adds significantly to the complexity of the launch system with respect to balancing structural loads, conducting
safe separation, and simultaneously managing two autonomous reusable boosters in the same airspace. Given
ongoing trends for smaller electronics and emerging desires and capabilities for disaggregation of large satellites,
the committee believes that the heavy-lift requirement should not drive the basic conceptual design for the RBS,
because this requirement may disappear in the future or be addressed with alternative space lift capabilities. Thus,
the committee explored cost options that pose no heavy-lift requirement for the RBS.
An additional factor that requires consideration is the existing Air Force requirement for two independent
launch capabilities to meet its assured-access-to-space goal. The scenarios described above are all based on the
assumption that the current EELV launch systems would be fully retired and that the RBS satisfies the complete
Air Force launch manifest. In this case, a problem identified in the RBS system could potentially jeopardize the
entire Air Force launch capability. One possibility for avoiding this possibility would be to maintain the Delta IV
production capability and use this launch system to satisfy the heavy-lift requirement.
The evaluations to follow principally focus on Scenarios 1 and 4. Scenario 2 allows for development of the
hydrocarbon engine technology prior to proceeding with RBS development, so any decision regarding RBS devel-
opment would be delayed for several years. This use of an RD-180 replacement engine would complicate the RBS
vehicle design by requiring large engine throttling, as discussed in Chapter 3. Scenario 3 was also not addressed
in detail as it was viewed by the committee as being too risky given the existing concerns about the rocketback
return-to-launch-site (RTLS) maneuver. In the evaluations that follow, a subdesignation "-A" is used for a modi-
fication to the baseline scenario that does not include the RBS-heavy variant. In these scenarios, the implications
of carrying the alternative heavy launch system were not factored into the cost analysis.
The costing analysis covers a 47-year life cycle (2014-2061), with EELV costs provided by the Air Force's
Space and Missile Systems Center (SMC) Launch and Range Systems Directorate and RBS costs estimated by
the SMC's Developmental Planning Directorate. The approaches used for the RBS cost estimates are shown in
Table 4.1. The NASA/Air Force Cost Model (NAFCOM) is used for the costs of design, development, test and
evaluation (DDT&E), and production and contractor proprietary approaches are used for cost estimations of the
vehicle and engines. The Aerospace Corporation's operations design model and its facilities model are used for
operations and facilities.
A conservative approach was taken to the flight rate assumption. Air Force analyses are based on only eight
flights per year, with one heavy-lift payload every year, and commercial markets were not considered. The mission
model for the assumed flight rate is provided in Table 4.2.
OCR for page 56
56 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
TABLE 4.1 Summary of Reusable Booster System Cost Estimating Approaches
Cost Category Cost Model/Method
DDT&E
RBD (Except NK-33 Engine) NAFCOM
RBS NAFCOM
AJ-26 Engine Development Contractor estimate + OGC
LES NAFCOM
RS-25E Engine Development N/A--NASA developed
Castor 30 (Mods for Side Mounting) NAFCOMa
Star 63D (Mods for Side Mounting) NAFCOMa
DDDT&E (After Flight Test Program) NAFCOM
Production
RBS NAFCOM
AJ-26 Engines Contractor estimate + OGC
LES NAFCOM
RS-25E Engines Contractor estimate + OGC
Castor 30 NAFCOM
Star 63D NAFCOM
Facilities
SLC-2W for RBD (VAFB) VAFB estimate + OGC
SLC-3E (VAFB) Facilities modelb
SLC-41 (CCAFS) Facilities modelb
New Facility (CCAFS) Facilities modelb
Operations and Sustainment
RBD Flight Test Program ODMb
RBS Flight Test Program ODMb
RBS Launch Operations ODMb
RBS Mission Integration Based on EELV data
RBS Transportation Based on EELV data
Range Costs Based on EELV data
Sustainment Based on EELV data
a Used first unit production cost as mod estimate
b Aerospace model
NOTE: CCAFS, Cape Canaveral Air Force Station; DDT&E, design, development, test and engineering; EELV, Evolved Expendable Launch
Vehicle; NAFCOM, NASA/Air Force Cost Model; ODM, Operations Design Model; OGC, Other Government Costs; VAFB, Vandenberg Air
Force Base.
SOURCE: Air Force Space and Missile Systems Center, SMC Developmental Planning, "Reusable Booster System Costing," presentation
to the committee, February 15, 2012. Approved for Public Release.
Other key assumptions in the cost assessment include these:
· A production learning rate of 95 percent for the RBS and large expendable stage (LES) and 98 percent for
the solid motors,
· A 10-flight interval between depot maintenance (with engine replacement after every 20 flights), and
· A 5-year overlap of RBS operations with EELVs.
4.2 ASSESSMENT OF BASELINE COST MODELING
To assess the approach used for cost modeling, RBS costs have been divided into four areas: vehicle, engine,
facilities, and operations. The cost estimates for each are based on different approaches, as described below.
While there is a strong interrelationship among these elements, the linkages are captured only to the degree that
OCR for page 57
COST ASSESSMENT 57
TABLE 4.2 Basis for Reusable Booster System Flight Rate
Satellite Type Orbit Requirement EELV Used Average Annual Rate
Communications GTO Atlas V 531 0.64
Meteorological GTO Atlas V 501 0.25
SSO Delta IV M 0.32
Navigation MEO Atlas V 401 1.96
Missile warning GTO Atlas V 411 0.31
SSO Delta IV M 2.12
Intelligence LEO (high inclination) Delta IV M+(4,2) 0.20
LEO (high inclination) Delta IV H 0.29
LEO (high inclination) Atlas V 541 0.20
HEO Atlas V 551 0.29
Polar Delta IV H 0.29
Polar Atlas V 401 0.16
GTO Delta IV M+(5,4) 0.50
GEO Delta IV H 0.50
Average annual launch rate 8.00
NOTE: EELV, Evolved Expendable Launch Vehicle; GEO, geosynchronous Earth orbit; GTO, geosynchronous transfer orbit; HEO, high
Earth orbit; LEO, low Earth orbit; MEO, medium Earth orbit; SSO, Sun-synchronous orbit.
SOURCE: Air Force Space and Missile Systems Center, SMC Developmental Planning, "Reusable Booster System Costing," presentation
to the committee, February 15, 2012. Approved for Public Release.
the lower-level models can identify them. All models are largely based on historical expendable vehicles and are
therefore significantly handicapped by the lack of good analogous data for unmanned RBS-type reusable systems.
4.2.1 Vehicle
The vehicle estimates cover DDT&E and production costs for all flight hardware except the engines. The
flight hardware includes the RBD, the RBS, and LES subsystems (less engines).
4.2.1.1 Models
The NASA/Air Force Cost Model (NAFCOM)3 was used for all vehicle estimates. NAFCOM is a parametric
cost estimating model based on a database of historical NASA and Air Force launch and space systems. The com-
mittee believes that NAFCOM is an appropriate tool for this application and the maturity level of the concept,
although a bottoms-up cost estimating approach would further enhance credibility of the cost estimates.
4.2.1.2 Inputs and Assumptions
The inputs to NAFCOM include subsystem-level masses and other system characteristics. For the baseline
RBS concept, the system masses are shown in Table 4.3. The other system inputs that serve as NAFCOM inputs
include factors accounting for system maturity and program management approach. The cost implications of these
factors are based on historical programs. Specific input factors include the following:
· Manufacturing method. This factor accounts for the identification and maturity of the manufacturing
methods used in the production process and aims to address the level of use of advanced manufacturing techniques.
3 J. McAfee and G. Culver, SAIC, and M. Naderi, NASA Marshall Space Flight Center, "NAFCOM Capabilities and Results," presentation
at the 2011 Joint Army Navy NASA Air Force (JANNAF) Modeling and Simulation/Liquid Propulsion /Spacecraft Propulsion Joint Meeting,
Huntsville, Al., December 5, 2011, available at http://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20120002891_2012002403.pdf.
OCR for page 58
58 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
TABLE 4.3 Reusable Booster System Mass Breakdown to Support NASA/Air Force Cost Model Estimates
Elements RBD RBS LES Castor 30 Star 63D
Weight (lb) Weight (lb) Weight (lb) Weight (lb) Weight (lb)
Structures and Mechanisms 14,673 60,180 22,866 246 0
Vehicle Structures and Mechanisms 10,271 42,567 12,742 - -
Tank Structures and Mechanisms 4,402 18,243 10,124 - -
Thermal Control 0 0 949 37 9
Reaction Control Subsystem 303 1,143 118 74 44
Main Propulsion System (less engines) 1,825 9,423 3,611 - 0
Electrical Power and Distribution 1,697 3,876 999 222 91
Command, Control, and Data Handling 1,672 1,672 236 259 60
Guidance, Navigation, and Control 293 293 177 123 30
Landing System 1,884 6,002 - - -
Rocket Engines/Motors 3,079 22,221 8,835 1,503 370
Dry Weight 25,426a 105,441a 37,790a 2,464 604
Gross Lift Off Weight (GLOW) 176,955 992,857 397,890 37,343 7,771
Dimensions (ft) Dimensions (ft) Dimensions (ft) Dimensions (ft) Dimensions (ft)
Length 63.0 108.4 130.3 29.7 12.0
Wingspan 35.0 60.1 - - -
Diameter 9.5 16.1 15.0 7.7 7.7
Height (landing gear up) 20.0 33.8 - - -
Height (landing gear down) 23.7 40.9 - - -
a Includes 25% dry weight margin.
NOTE: LES, large expendable stage; RBD, reusable booster demonstrator; RBS, reusable booster system.
SOURCE: Air Force Space and Missile Systems Center, SMC Developmental Planning, "Reusable Booster System Costing," presentation
to the committee, February 15, 2012. Approved for Public Release.
The use varies from minimum to maximum use of manufacturing techniques such as just-in-time delivery, bar
coding, robotics, commercial-off-the-shelf items, and outsourcing.
· Engineering management. This factor accounts for the variation in management approaches, from stream-
lined activities with minor expected changes to a widely distributed team with formalized procedures and managed
interfaces. At one end of the spectrum is the assumption of a minimum number of design changes, with the design
team making maximum use of the highly efficient Skunk Works approach with integrated product teams, rapid
prototyping, design to cost, and the like. At the opposite end of the spectrum is the assumption of a distributed
design team just waiting for major technology advances and hoping they will bring frequent major requirement
and design changes.
· Design level. This factor accounts for the maturity of the vehicle design and depends on what is inherited
from previous projects. A high design level value indicates that the system has little inheritance from previous
projects, and vice versa. Choices for the design level range from very low values, which represent the reflight of an
existing vehicle, to moderate values, which represent significant modifications to an existing design, and through
high values, which represent a totally new design.
· Funding availability. This factor accounts for the potential of program development delays due to fund-
ing limitations, which create inefficiencies in execution. Choices for funding availability include these: funding
is assured and no delays are expected; delays are possible but infrequent; or funding is constrained and delays
are likely.
· Test approach. This factor accounts for variation in the degree of testing required during system devel-
opment and reflects the amount of risk being accepted and indicated by the planned test program. Choices for
test approach include minimum testing, with qualification using simulation and analysis; moderate testing, with
qualification at the prototype/protoflight level; or maximum use of testing with qualification at component level.
OCR for page 59
COST ASSESSMENT 59
· Program interfaces. This factor accounts for the degree to which interfaces external to the development
program impact launch system design and development and reflects the expected number of interfaces with multiple
contractors and/or centers. Options include low or high number of major interfaces involving multiple contractors
and/or centers.
· Pre-development study. This factor accounts for the depth of analysis supporting the vehicle design and
reflects the level of study efforts that were conducted or are being conducted before the start of design and devel-
opment. Choices for the predevelopment study level include two or more study contracts in phases A and B, with
more than 9 months of study; one study contract with between 9 and 18 months of study; and less than 9 months
of prephase C and D study.
Two factors not considered by the NAFCOM costing methodology are the breadth of the supplier base, par-
ticularly the implications of relying on single-source suppliers, and the degree to which the commercial market
may influence future launch costs. The implications of reusable boosters for the U.S. launch industry are difficult
to predict. The baseline RBS program assumes eight boosters would satisfy Air Force needs over the entire RBS
life cycle. Cost models for the sustainment of these vehicles and the associated industrial support that will be
required are largely absent. The potential implications for the commercial market are addressed in the next section.
The committee evaluated the NAFCOM inputs used by the Air Force in its costing analysis for the other system
characteristics, which are shown in Figure 4.2. The committee agrees that these input factors are appropriate given
the state of the RBS concept.
Ø Selected based on vehicle design and programmatic considerations:
§ Manufacturing Method
· RBD Maximum Methods Significant Methods Moderate Methods Minimal Methods Limited Methods
· RBS Maximum Methods Significant Methods Moderate Methods Minimal Methods Limited Methods
§ Engineering Management
· RBD Minimum Changes Few Changes Moderate Changes Dedicated Team Distributed Team
· RBS Minimum Changes Few Changes Moderate Changes Dedicated Team Distributed Team
§ Design Level
· RBD Level 1 Level 2 Level 3 Level 4 Level 5 Level 6* Level 7 Level 8
· RBS Level 1 Level 2 Level 3 Level 4 Level 5 Level 6 Level 7 Level 8
§ Funding Availability
· RBD No Delays Infrequent Delays Possible Delays Likely
· RBS No Delays Infrequent Delays Possible Delays Likely
§ Test Approach
· RBD Minimum Testing Moderate Testing Maximum Testing
· RBS Minimum Testing Moderate Testing Maximum Testing
§ Program Interfaces
· RBD Minimal Interfaces Moderate Interfaces Extensive Interfaces
· RBS Minimal Interfaces Moderate Interfaces Extensive Interfaces
§ Pre-Development Study
· RBD 2 or More Study Contracts One Study Contract <9 months of Study
· RBS 2 or More Study Contracts One Study Contract <9 months of Study
FIGURE 4.2 Additional NASA/Air Force Cost Model inputs for other characteristics. NOTE: RBD, reusable booster demon-
strator; RBS, reusable booster system. SOURCE: Air Force Space and Missile Systems Center, SMC Developmental Planning,
"Reusable Booster System Costing," presentation to the committee, February 15, 2012. Approved for Public Release.
Figure 4-2
R02338
vector editable
OCR for page 60
60 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
4.2.1.3 Results, Sensitivities, and Uncertainty Ranges
Sensitivities of vehicle cost to assumed design heritage and engineering management are shown in Figure 4.3.
Clearly, DDT&E costs are significantly reduced as a result of the RBD effort, which results in a higher confidence
in the RBS vehicle design as the program enters full-scale development. Potential variations in the RBS assump-
tions used for the NAFCOM inputs covering design heritage (design levels 1-8) and engineering management
(management levels 1-5) appear to show a potential for RBS DDT&E estimates to increase by 50-100 percent,
although the assumptions used for the baseline cost appear reasonable.
4.2.2 Engines
The engine estimates cover DDT&E and production. For the RBD, a NK-33 engine is used with Castor 30
and Star 63D solid motors in the second stage. The RBS uses five AJ-26 engines in the reusable first stage and an
RS-25E engine for the expendable second stage. The reusable AJ-26 engines are assumed to be refurbished every
10 flights and replaced every 20 flights.
4.2.2.1 Models
The models and methodologies used to generate cost estimates for the engines are contractor-proprietary.
These models are generally accurate when based on similar applications, although they rely on assumptions about
reusability requirements, which carry some uncertainty.
Eng Mgmt
Level
300% 5
275% 4
250% 3
2
225% 1
Cost %
200%
175%
150%
RBS DDT&E
125%
Without RBD
100%
75%
RBS DDT&E
50%
25%
0%
1 2 3 4 5 6 7 8
Existing Existing Design Existing Design Existing Design Existing Design New Design New Design New Design
"Flight-Proven" w/Minor Mods, w/Minor Mods ~50% Major >50% Major w/Prototype w/Components w/Components
Design No Requal and Requal Mods Mods Validated in Validated in Validated in
With Requal With Requal Relevant Environ Relevant Environ Lab Environ
Design Level
FIGURE 4.3 Sensitivities to NASA/Air Force Cost Model inputs normalized to the baseline RBS design, DDT&E program.
Sensitivity of cost to the design maturity (e.g., whether or not requalification of an existing design, Requal, is needed) and
Engineering Management Level needed for program execution. NOTE: DDT&E, development, test, and evaluation; RBD,
reusable booster demonstrator; RBS, reusable booster system. SOURCE: Air Force Space and Missile Systems Center, SMC
Developmental Planning, "Reusable Booster System Costing," presentation to the committee, February 15, 2012. Approved
for Public Release.
Figure 4-3
R02338
vector editable
OCR for page 61
COST ASSESSMENT 61
4.2.2.2 Inputs and Assumptions
The specific inputs and assumptions for cost modeling of the engines were not provided to the committee
because they are proprietary.
4.2.2.3 Results, Sensitivities, and Uncertainty Ranges
Engine cost estimates were provided to the committee and were included in its analyses. However, the data
are considered sensitive and raw data are not included in this report.
4.2.3 Facilities
The facility estimates cover the costs of the initial construction/modification efforts to support all RBD and
RBS operations.
· Models. The Aerospace Corporation's facility model4 was used to generate all facility estimates. This model
accounts for the sharing of common items at each launch site, includes site preparation/utilities/activation costs,
and also accounts for site-specific cost differences.
· Inputs and assumptions. For the RBD, modifications to the Vandenberg Air Force Base (VAFB) SLC-2W
launchpad represent the only facility investment. For the RBS, one new launchpad and modifications to the
SLC-41 are planned at Cape Canaveral Air Force Station (CCAFS), as well as modifications to the SLC-3E
launch pad at VAFB.
· Results, sensitivities, and uncertainty ranges. Facility estimates were evaluated by the committee. These
estimates appear to reasonably reflect the assumptions used, but there is some uncertainty about the impact of
reusability requirements, as discussed in Chapter 3.
4.2.4 Operations
Operations estimates cover all labor and support required for flight operations and vehicle turnaround tasks.
Costs for expendable hardware and RBS vehicle refurbishment add to operation costs but are estimated using
different methodologies.
· Models. The Aerospace Corporation's operability design model5 was used to estimate operations costs. The
general approach is depicted in Figure 4.4.
· Inputs and assumptions. Estimates are based on a buildup from 188 shuttle-like tasks needed to prepare
the reusable booster for its next launch. The effort needed to support each of these tasks is based on an expected
level of operability improvement attributable to a design or approach difference.
· Results, sensitivities, and uncertainty ranges. Table 4.4 shows the staffing results from the Air Force
analysis. In the opinion of the committee, these staffing levels seem slightly below what would be expected in that
they are slightly below those existing EELV operations. In the committee's view, it was not clear that the require-
ments associated with reusability, such as postflight checkout and refurbishment, were adequately reflected in the
staffing analysis. The experience that will be gained from the RBD effort is likely to help in better refining these
estimates. Table 4.5 shows cost estimate sensitivity to turnaround time. This sensitivity is not significant, unlike in
past studies of reusable launch systems, largely because the relatively low assumed flight rate does not put great
pressure on the launch vehicle processing schedule.
4 AFSMC, "Reusable Booster System Costing, SMC Developmental Planning," 2012. Approved for Public Release.
5 AFSMC, "Reusable Booster System Costing, SMC Developmental Planning," 2012. Approved for Public Release.
OCR for page 62
62 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
ALGORITHMS
VEHICLE CONFIGURATION PROCESSING TASKS
SUBSYSTEM DESCRIPTIONS TASK DURATIONS
ACCESSIBILITY CRITERIA VEHICLE RELIABILITY
DEVELOPMENT TEST PLAN MEAN-TIME-TO-REPAIR
DESIGN MARGINS OPERATIONS COSTS
DESIGN LIFE
DATA BASE
INPUTS OUTPUTS
FIGURE 4.4 Aerospace Corporation's operability design model. SOURCE: Air Force Space and Missile Systems Center, SMC
Developmental Planning, "Reusable Booster System Costing," presentation to the committee, February 15, 2012. Approved
for Public Release.
TABLE 4.4 RBS Staffing Estimatesa Figure 4-4
R02338
RBS Personnel Estimates
vector editable
Category CCAFS VAFB Common Atlas I/II Delta II Titan IV
Vehicle processing ("Hands-On Labor") 43 43 --
Vehicle engineering -- -- 15
Payload Integration 8 8 4
Flight Operations/Mission Operations 7 7 5
Flight Software Engineering -- -- 12
Logistics 8 8 5
Launch Support Equipment 18 18 6
Facilities Maintenance 14 14 8
Landing Site Ops 22 22 --
Administration 6 6 --
Total 126 126 55
307 325b 175b 1,336b
a Assumes all contractor workforce.
b From C.L. Whitehair, Cost of Space Launch Systems, Aerospace Corporation, June 1994.
NOTE: CCAFS, Cape Canaveral Air Force Station; VAFB, Vandenberg Air Force Base.
SOURCE: Air Force Space and Missile Systems Center, SMC Developmental Planning, "Reusable Booster System Costing," presentation
to the committee, February 15, 2012. Approved for Public Release.
TABLE 4.5 Cost Sensitivity to Launch Processing Time
Launch Average Operations Cost
Processing Variable Operations Cost Per Launch Total Cost Including
Crew-Hours (at 8 per year) Fixed Operations Cost (at 8 per year) Production
1X 1X 1X 1X 1X
2X 1.06X 1.05X 1.06X 1.02X
5X 1.28X 1.13X 1.22X 1.07X
10X 1.50X 1.23X 1.38X 1.12X
SOURCE: Air Force Space and Missile Systems Center, SMC Developmental Planning, "Reusable Booster System Costing," presentation
to the committee, February 15, 2012. Approved for Public Release.
OCR for page 63
COST ASSESSMENT 63
4.2.5 Cost Modeling Assessment Summary
A high-level qualitative assessment of the committee's cost confidence for the various RBS elements is sum-
marized in Figure 4.5. Without a grassroots-type cost estimate to balance the uncertainties in a NAFCOM-based
approach, it is difficult to have much confidence in the estimates. Estimates for the engines may be considered
comparable to a grassroots cost estimate, since the providing organizations developed the estimates but uncertain-
ties related to the impacts of reusability requirements somewhat reduce confidence.
These estimates appear to be based on somewhat optimistic assumptions regarding the reuse of existing
infrastructure and the need for new facilities to support reusability. Labor estimates for operations appear lower
than would be expected for a reusable system, as they are nearly the same as those applied for EELVs, which one
would expect to have lower operability requirements since the entire launch vehicle is expendable.
4.3 RBS BUSINESS CASE
4.3.1 Approach and Assumptions
For this study, the RBS business case compares the costs for the RBS system, using the Air Force cost meth-
odology, with the projected costs for competing expendable launch vehicles, including commercial vehicles. It is
noted that the very conservative launch rate (eight launches per year) can strongly impact the economic attractive-
ness of reusable concepts.
4.3.2 Results, Sensitivities, and Uncertainty Ranges
Figure 4.6 compares estimated cumulative costs for RBS under these scenarios to current cost projections
for EELVs, with each scenario supporting eight flights per year. This comparison assumes RBS initial operating
capability (IOC) in 2032, so that is where costs for the EELV also begin in this comparison. The costs used for the
EELV are today's costs adjusted for inflation. Scenarios 1, 1A, and 4A were considered, the red curves illustrate
the resulting variations in cumulative costs, with the 4A scenario represented by the lower curve. It can be seen
that removing the heavy-lift requirement for the RBS does not have a first-order impact using the existing costing
approach, but the committee believes that the heavy-lift requirement will indeed introduce significant technical
risks that are not captured in the cost models.
Note that the development costs for the RBD and the full-scale RBS occur in parallel with existing EELV
operations (ongoing costs associated with EELV during RBS and RBS development are not shown in Figure 4.6),
so that they have a claim on funding beyond that required for planned operations. Also, note that the cost break-even
point for RBS is reached relatively soon after IOC independent of the scenario evaluated. Thus, once the sustained
investment has been made in developing the RBS capability, the savings relative to EELV are realized fairly quickly.
Low Nominal High
Vehicle X
Engines X
Facilities X X
Operations X
FIGURE 4.5 Summary of confidence in assessments of cost.
Figure 4-5
R02338
vector--created with InDesign
OCR for page 64
64 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
EELV
Total Cost
RBD RBS Variaon in RBS
Costs for Scenarios
1, 1A, and 4A
Today RBS IOC
FIGURE 4.6 Comparison of reusable booster system costs to EELV costs. NOTE: EELV, Evolved Expendable Launch Vehicle;
IOC, initial operational capability; RBD, reusable booster demonstrator; RBS, reusable booster system.
These results are largely in agreement with the cost modeling presented to the committee by the Air Force and
Figure
The Aerospace Corporation, although it is noted that these 4-6
cost trends do not account for the Air Force requirement
for two independent launch systems. If some version of R02338 was maintained to satisfy that requirement, the
the EELV
slope of the red curves would be steeper and the break-even costs relative to those for the EELV system would
vector editable
push to later dates.
edits madethe
There are varying degrees of uncertainty regarding as estimates
requested for each of the RBS elements, especially
with respect to the technical risk areas identified in Chapter 3. These uncertainties mean the amount of funding
required to reach IOC has a reasonable likelihood of growing significantly. Also, if the costs required to support
each flight increase, this would further increase the slope of the cumulative funding curve, potentially pushing the
potential break-even point further out. There would be improvement in the confidence of the cost picture if RBS
operability improvements could be validated and especially if costs for EELVs continue to grow beyond inflation.
4.3.3 Impact of Commercial Activities
The greatest cost uncertainty affecting the RBS business case is from impacts of commercial activities. Adver-
tised pricing for a SpaceX Falcon 9 EELV medium-class commercial launch is currently $54 million (in fiscal year
2010 dollars). Also, SpaceX has a contract with NASA for 12 launches to the International Space Station (ISS)
for $1.6 billion, which works out to about $133 million per launch. While many ISS-unique requirements do not
typically apply to unmanned payloads, this latter cost may be considered representative of a commercial effort
with substantial government oversight. The expected expendable launch costs for Department of Defense missions,
with anticipated levels of government oversight typical of those for meeting the mission assurance requirement,
are expected to be still higher. Conversely, development of a commercial launch capability that can satisfy Air
Force launch requirements may lead to true competition and lower overall costs.
Figure 4.7 compares several hypothetical cases along with the information that was shown in Figure 4.6. The
green lines now represent the costs for satisfying the Air Force launch manifest with either a commercial expendable
launch vehicle operating on commercial principles or the expendable launch vehicle operating with government
oversight, as represented by NASA missions to the ISS. Significantly, the costs of the expendable system never
cross the RBS cumulative cost curve. There are probably several reasons for this. First, the Air Force would not
have paid for vehicle development in the case of the commercial vehicles, so the latter expendable vehicles would
begin with a cost advantage in cases where their development costs are expected to be recapitalized across a cus-
OCR for page 65
COST ASSESSMENT 65
Shaded area represents EELV
range of uncertainty
in expendable launch
Total Cost
vehicle costs
RBS
Commercial
Expendable w/
RBD RBS NASA Oversight
Commercial
Expendable
Today RBS IOC
FIGURE 4.7 RBS cost compared to costs of EELVs, commercial, and other options. NOTE: EELV, Evolved Expendable
Launch Vehicle; IOC, initial operational capability; RBD, reusable booster demonstrator; RBS, reusable booster system.
tomer base larger than just the Air Force. Second, this comparison is being conducted between an existing system
and a conceptual RBS design, and the NAFCOM costing models provide factors to account for design immaturity.
Third, NAFCOM's supporting database was developed Figure 4-7 information from previous government-led programs,
using
R02338
so its cost estimates may not account for entrepreneurial approaches to developing new launch capabilities. And
finally, the RBS costing methodology does not account for
vector editable the cost pressures associated with a launch service
provider competing in the commercial market.
edits made as requested
The commercial lines shown in Figure 4.7 represent the lower end of the potential cost spectrum associated
with satisfying Air Force launch requirements. As previously stated, satisfying Air Force mission assurance require-
ments may result in launch costs even higher than those realized in missions executed with NASA oversight. So in
this regard, the entire range of expendable launch vehicle costs can be considered to be the range of cost uncertainty.
Given the existing uncertainties in the costing associated with expendable launch vehicles, the business case
for RBS development is not as clear as portrayed in Figure 4.6 when RBS costs are compared to today's EELV
operations. Today, a number of commercial organizations are pursuing a wide variety of innovative launch vehicle
concepts, and emerging commercial market forces may well challenge historical costing methodologies.
4.4 OTHER ISSUES AND COST CONSIDERATIONS
Other factors may also affect the viability of the RBS program both from the positive and negative standpoints.
For example, there would ordinarily be clear benefits to the government for maintaining multiple options to meet
launch needs, and the Air Force has a stated requirement for two independent launch systems for satisfying mission
assurance criteria. Studies have shown cost benefits of from between 10 and 50 percent assuming a competitive
market environment and continuous competition.6 Relying on a single system or launch service provider takes away
the benefits of this competition. The potential advantages from competition, however, need to be tempered by the
very small number of launches that the Air Force model assumes. The fixed prices associated with maintaining
an industrial base for such a limited number of launches would likely more than offset any cost advantages here.
Thus, maintaining two independent launch systems may significantly increase the projected costs associated with
6 R. Nash, "The case for competition in government acquisitions," Daily Caller, June 18, 2012, available at http://dailycaller.
com/2011/02/15/the-case-for-competition-in-government-acquisitions/#ixzz1yBhAuofP; G.G. Daly, H.P. Gates, and J.A. Schuttinga, "The
Effect of Price Competition on Weapon System Acquisition Costs," Paper P-1435, Institute of Defense Analysis, September 1979.
OCR for page 66
66 REUSABLE BOOSTER SYSTEM--REVIEW AND ASSESSMENT
future scenarios using RBS. Conversely, development of a commercial launch capability that can satisfy Air Force
launch requirements may lead to true competition and lower overall costs.
In addition, this analysis essentially accepts the feasibility and success of a reusable booster system in the
time frames suggested by the Air Force projections. However, previous chapters have detailed a number of
important technical areas (as, for example, with the rocketback maneuver) where considerable uncertainty exists
about technology and timing. Additionally, persistently unstable funding may also delay technology development.
Major delays in overcoming technological hurdles would significantly and negatively affect the cost trade-offs
and breakeven points shown in previous charts. Technology maturity levels therefore would add another level of
uncertainty to the balance of the cost equations between RBS and EELVs.