Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 19
20
CHAPTER FOUR
CONTRACT ADMINISTRATION
INTRODUCTION totaling more than 100%, international agencies seem to
prefer a mix of unit-price and lump-sum contracts, and they
The administration of a chip seal project has an immense have also contracted with designbuild, whereby the chip
impact on not only the cost of the project, but also its ultimate seal contractor is responsible for both the design and the
performance. The distribution of risk through the chip seal construction.
contract can create either an incentive to furnish the best pos-
sible quality or a bias to deliver the bare minimum. For exam- The greater reliance on lump-sum contracts by inter-
ple, the heavy use of method specifications that describe in national respondents is significant when one considers that
detail the chip seal construction process essentially absolves all of those nations have developed their own chip seal design
contractors of long-term performance liability as long as they methodologies that are based on a much more detailed set
can prove that they followed the agency's method specifica- of engineering measurements than those used in either the
tions to the letter. Therefore, it is important for owners to for- McLeod or the Kearby design methods. Perhaps their more
mulate the most appropriate contracts for their chip seal proj- scientific approaches to chip seal design allow those coun-
ects. This chapter offers direction on best practices for the tries to feel more comfortable in transferring the construction
administration of successful chip seal programs, from project material quantities risk to their respective construction indus-
development to post-completion. The types of contracts used, tries. Under volumetric unit-price contracts, the contractor
project planning and programming, and contract management has an economic incentive to install as much asphalt and
procedures will be discussed. aggregate as possible and thus might construct the seal in a
manner not beneficial to the life of the chip seal (Gransberg
et al. 1998). Changing the measurement of the chip seal pay
CONTRACT TYPES
quantities to a surface area reverses this incentive. The sig-
Transportation infrastructure contracts have traditionally been nificance of having an engineering-based design method that
awarded using a low-bid process that is often required by leg- does allow for significant adjustments in the field is that
islation at the state and local level. The survey identified two quantity overruns may likely be reduced because the profit
primary types of low-bid contracts: unit price and lump sum. motive for the contractor disappears.
Lump-sum contracts are warranted in construction projects
where the scope of work can be easily quantified. On the other
CONTRACT MANAGEMENT
hand, unit-price contracts are used in those situations where
the aforementioned conditions do not exist (Clough and Sears Chip seal contract management practices in essence define
1994). The owner assumes the risk of quantity overruns by the constraints within which chip seals are designed and con-
agreeing to pay for the actual units applied, rather than pay- structed. There are a number of contract management issues
ing a premium for transferring the risk of quantity overruns that must be addressed to ensure that the ultimate perfor-
to the contractor by means of a lump-sum price. Given that mance of the chip seal is purely a function of the quality of
chip seal projects usually are limited to a defined area of pave- the design and construction and not adversely influenced by
ment, quantity surveys should be fairly straightforward and external administrative constraints. The clarity of the con-
not highly variable. Therefore, lump-sum contracts, including tract documents is essential, because the agency can enforce
the total cost of the project plus mobilization and traffic con- only what is in the contract.
trol, could be used without the agency's incurring a substan-
tial cost increase. The survey results revealed that Arkansas
and Nevada are using lump-sum contracts for their chip seal Construction Season
projects. Arkansas also reported that it was getting excellent
chip seal results. The literature review showed that chip seals applied early in
the summer appeared to perform better than those applied
Contracting procedures vary significantly between North at the end of the summer (McHattie 2001). It is not known
American and international respondents. As can be seen in what the temperature following chip seal placement will be,
Figure 18, North America favors the use of unit-price con- so the only way to address that concern is to limit the con-
tracts. As evident by the proportion of international responses struction season. This is because these early season chip seals
OCR for page 20
21
100% agement into their chip seal design process that relates to
94% 86%
100% the season in which the chip seal will be placed. Figure 19 is
71% taken from Road Note 39 and illustrates this approach to
80%
selecting the proper timing within the chip seal season for
60%
construction.
40% 22%
6%
20%
Survey respondents were asked to specify their allowable
0% chip seal construction season. Analysis showed that the chip
United States Canada AU, NZ, UK, SA seal season is actually not nearly as variable for chip seal proj-
Unit Price-Low Bid Lump Sum-Low Bid Design-Build
ects as for other highway construction projects such as hot
mix paving. Most agencies, regardless of location, contract
FIGURE 18 Types of chip seal contracts. for a chip seal program of approximately 4 months in north-
ern areas to roughly 5 months farther south. The season is
constrained by daily temperature and weather requirements
have more time to cure before being subjected to cold temper- aimed at making sure that the chip seal is applied in the
atures. Thus, it seems that a best practice is to award chip warmest, driest weather possible for the geography. This
seal contracts accordingly to allow for early summer con- topic leads into a discussion of the timing in advertising and
struction, which maximizes curing time before the first cold awarding the chip seal contract, which is commonly called
spell. The British have incorporated an element of risk man- bid letting.
FIGURE 19 Road Note 39 construction season chart (Source: Design Guide for Road Surface Dressing, Road Note 39 1996).