Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 10
10 A Guidebook for the Evaluation of Project Delivery Methods
United States have limited the procurement of constructors to the lowest responsible, responsive
bidder. The combination of these two procurement practices has helped solidify the proliferation
of DBB in the public sector. This method was the traditional transportation project delivery
method until the introduction of DB and design-build-operate-maintain (DBOM) in the Inter-
modal Surface Transportation Efficiency Act of 1991.1 Another step was taken in 1996, when the
Federal Acquisition Reform Act explicitly authorized the use of DB for federal projects. After that,
the Transportation Equity Act for the 21st Century (TEA-21), Public Law 105-178, allowed state
departments of transportation (DOTs) to award DB contracts if the enabling state-level legisla-
tion was in force. Subsequent to the successful use of DB in several projects, many states passed
new legislation and codes to allow alternative project delivery methods, i.e., DB and CMR. Adding
the responsibility of operation and maintenance to DB projects created another delivery method,
DBOM. The differences among delivery methods, the unique characteristics of each project, and
the vast variety of parameters affecting the selection of a project delivery method, have made selec-
tion of a project delivery method complicated for many owners. The purpose of this guidebook
is to facilitate the decision-making process by clarifying the differences among the project deliv-
ery methods and proposing a structured decision-making approach that incorporates all the per-
tinent parameters.
Definitions of the Delivery Methods
Since the early 1980s, owners of construction projects have been putting greater pressure on
the architecture/engineering/construction (A/E/C) industry to improve quality, reduce cost,
and, more importantly, compress the period from project conception to project completion for
all kinds of public and private facilities. As a result, both owners and the industry have experi-
mented with various forms of project delivery with varying degrees of success. The adoption of
alternative project delivery methods has added to the challenge of selecting the method most
appropriate to the owner's needs and desires as well as the project's technical requirements. This
report provides a set of standard project delivery definitions to help communicate the technical
requirements for bringing a new project from the owner's conception to operation and finally
to decommissioning.
Project delivery method is a term used to refer to all the contractual relations, roles, and respon-
sibilities of the entities involved in a project. TxDOT defines "project delivery method" as follows:
"A project delivery method equates to a procurement approach and defines the relationships,
roles and responsibilities of project team members and sequences of activities required to com-
plete a project. A contracting approach is a specific procedure used under the large umbrella of a
procurement method to provide techniques for bidding, managing and specifying a project"
(Walewski, Gibson, and Jasper 2001). The Associated General Contractors of America (AGC)
(2004) defines "project delivery method" as "the comprehensive process of assigning the contrac-
tual responsibilities for designing and constructing a project. A delivery method identifies the pri-
mary parties taking contractual responsibility for the performance of the work." Thus, different
project delivery methods are distinguished by the way the contracts among the owner, the designer,
and the builder are formed and the technical relationships among parties within those contracts.
The Construction Industry Institute maintains that there are really only three fundamental
project delivery methods: DBB, DB, and CMR (Construction Industry Institute 1997). While
1
In 1992, the FTA announced the initiation of a Turnkey Demonstration Program (Federal Register Vol. 57, No. 157,
8/13/92) and later selected five projects for DB implementation. These projects were (1) the Los Angeles Union
Station Intermodal Terminal, (2) Baltimore Light Rail Transit, (3) San Juan Tren Urbano, (4) Bay Area Rapid
Transit in San Francisco, and (5) Hudson-Bergen Light Rail Transit.
OCR for page 10
Background and Definitions 11
there are a multitude of names for project delivery methods throughout the industry, the Con-
struction Industry Institute is essentially correct. Therefore, this report will focus its information
on those three methods.
The AGC also distinguishes between the delivery method and the management method. The
management method "is the mechanics by which construction is administered and supervised"
(AGC 2004). This function is either retained by the owner agency or is outsourced. An example
of outsourcing the management process is to hire an agency CM to represent the owner's inter-
ests during design and construction. Theoretically, any management method may be used with
any delivery method. For example, an owner may hire an agency CM to manage a DBB, DB, or
even a CMR project.
Graphics displaying the contractual relationships among the major stakeholders and their
lines of communication are presented in Figures 2.1 through 2.3 to assist the reader in putting
the contents of this report into proper context. Note that the lines of communication shown in
the figures represent the ability to exchange information through formal and informal requests
for information among the various entities in the project.
Design-Bid-Build (DBB)
DBB is the traditional project delivery method. In this method, an owner retains a designer to
furnish complete design services and then advertises and awards a separate construction con-
tract that is based on the designer's completed construction documents. The owner is responsi-
ble for the details of design and warrants the quality of the construction design documents to the
construction contractor.
Figure 2.1 shows that the owner is situated squarely between the designer and the builder in the
DBB project delivery method. In DBB, the owner "owns" the details of design during construc-
tion and, as a result, is financially liable for the cost of any design errors or omissions encountered
in construction; this is called the "Spearin Doctrine" (Mitchell 1999). The construction phase of
DBB projects is generally awarded on a low-bid basis. There is no incentive for the builder to min-
imize the cost of change orders in this delivery method. In fact, there can be quite the opposite
effect. A builder who has won a project by submitting the lowest possible bid may need to look to
post-award changes as a means of enhancing profit on the project. One author states that the
defining characteristics of DBB are as follows (Bearup, Kenig, and O'Donnell 2007):
· There are separate contracts for design and construction.
· Contractor selection is based entirely on cost.
· Design documents are 100% complete.
Owner
Designer Builder
Contracts
Communication
(Adapted from American Institute of Architects 1996.)
Figure 2.1. Design-bid-build.
OCR for page 10
12 A Guidebook for the Evaluation of Project Delivery Methods
Despite the general definition of DBB given above, DBB projects can also be awarded on a
negotiated basis and a best-value basis (Scott et al. 2006); however, DBB transit projects awarded
in either of these two ways usually require FTA approval and frequently violate local laws. For
projects awarded on a negotiated basis or a best-value basis, the probability that the project will
be awarded to a builder who has submitted a mistakenly low bid is reduced. Additionally, in both
cases, the builder will be motivated to complete the project in a such a way that it be invited back
to do the next negotiated contract or that will reflect well in the next best-value selection. Regard-
less of the award method, DBB involves less builder input to the design than DB or CMR. Thus,
the owner must rely on the designer or agency CM (and not the builder) for a constructability
review, if there is any at all. Nonetheless, in this method the owner has full control over the details
of design, which may be a requirement for some complex projects.
DBB is also characterized by the greatest amount of familiarity in both the design and construc-
tion areas. All qualified designers can compete for the design without restriction. Additionally, all
constructors who can furnish the requisite bonding and meet any agency prequalification crite-
ria are also able to compete without constraint. Design subconsultants and construction trade
subcontractors are also able to compete with minimal restrictions. Finally, as DBB is generally
viewed as the traditional project delivery method in the United States, it is well understood and
accepted by owners and members of the design and construction industries.
CMR or Construction Manager/General Contractor (CM/GC)
CMR projects are characterized by a contract between an owner and a construction manager
who will be at risk for the final cost and time of construction. In this agreement, the owner
authorizes the construction manager to handle the construction phase and give inputs during
the design development. The idea of CMR is to furnish professional management of all phases
of a project life to an owner whose organization may not have those capabilities (North Carolina
State Construction Office 2005). Typically, CMR contracts contain a provision in which the
CMR stipulates a guaranteed maximum price (GMP) above which the owner is not liable for
payment. Often, these contracts include incentive clauses in which the CMR and owner can share
any cost savings realized below the GMP. Some states, like Oklahoma, take the GMP and con-
vert it to a firm-fixed price contract and administer the construction as if it were a traditional
DBB project thereafter (AIA 2005). CMR contracts can contain provisions for the CMR to han-
dle some aspects of design, but generally, the owner retains the traditional responsibility by keep-
ing a separate design contract and furnishing the CMR with a full set of plans and specifications
upon which all construction subcontracts are based (see Figure 2.2). The CMR will usually be
Owner
CM
At-Risk
Designer Trade Subs
Contracts
Communications
(Adapted from American Institute of Architects 1996.)
Figure 2.2. Construction
manager at risk.
OCR for page 10
Background and Definitions 13
paid for furnishing preconstruction services such as cost engineering, constructability review,
and development of subcontractor bid packages. According to AGC (2004), the defining char-
acteristics of the CMR are the following:
· The designer and the CMR hold separate contracts with the owner.
· The CMR is chosen on the basis of criteria other than just the lowest construction cost, such
as qualifications and past performance.
According to Bearup, Kenig, and O'Donnell (2007), additional defining characteristics are the
following:
· The CMR contracts directly with trades and takes on "performance risk" (cost and schedule
commitments);
· The schedule allows for overlapping design and construction;
· The owner procures preconstruction services from the CMR; and
· The owner expects the CMR to provide GMP and to commit to a delivery schedule.
A final defining characteristic, noted in AIA's "Construction Manager at-Risk State Statute
Compendium," is that "transparency is enhanced, because all costs and fees are in the open,
which diminishes adversarial relationships between components working on the project, while
at the same time eliminating bid shopping" (AIA 2005, p. 1).
Constructability and speed of implementation are the major reasons that an owner would
select the CMR method (3D/International, Inc. 2005). Additionally, CMR greatly facilitates
phased construction when that is a requirement for a given project. Unlike DBB, CMR brings
the builder into the design process at a stage in which definitive input can have a positive impact
on the project. "The CM[R] becomes a collaborative member of the project team. Preconstruc-
tion services include budgeting, cost estimating, scheduling, constructability reviews and value
engineering studies." (3D/International, Inc. 2005, p. 4). In CMR, the CM essentially becomes
the general contractor at the time the GMP is established. While some experts attempt to distin-
guish between CMR and CM/GC, due to perceived levels of risk, many agencies use these terms
more or less interchangeably.2 The CMR can and is expected to provide realistic project cost esti-
mates early in the project lifecycle. It is anticipated that after a certain amount of the design is
complete and the project is sufficiently defined, the owner will enter into a contract with the
CMR for providing construction services. Many states reserve the right to go out for bid if they
think that the CMR's price is not competitive (Minchin, Thakkar, and Ellis 2007).3 The timing
of GMP negotiations varies among different agencies. In many cases, at least 60% of the design
is completed before a GMP is established. In some cases, the design is 80 to 90% complete before
a GMP can be effectively negotiated with the CMR. The timing of GMP negotiations depends
on project complexity, agency rules, and external conditions such as inflation and the expected
level of competition among subcontractors. In general, the CMR may feel that committing to a
GMP while all the details of the design are not defined may involve incurring undue risk. Also,
some agency rules may hamper early GMP negotiations. For example, if an agency insists on
requiring a fully open competition for hiring of subcontractors, then negotiating an early GMP
may be more difficult because some subcontractors may be reluctant to give their prices without
2
According to AGC (2004), there has been some confusion about the terms CM at-risk and CM/GC because of
the assumption that the phrase "at-risk" connotes cost guarantee. Even if there are no cost guarantees, the CM
is still at risk because the CMR holds the trade contracts (warranting the performance of the work). Because of
this, some users choose to avoid the debate over the term "at-risk" and instead use the term CM/GC (p. 8).
3
There are two types of CM arrangements, namely agency CM and CM at-risk. Our emphasis in this work is CM
at-risk. Agency CM is not a project delivery method because the CM is not contractually responsible for deliv-
ering the project. The role of agency CM is purely advisory, and thus, the agency CM is usually not at risk for the
cost and schedule of building the project.
OCR for page 10
14 A Guidebook for the Evaluation of Project Delivery Methods
a 100%-complete design. This in turn makes the CMR hesitant to provide a reasonable GMP for
fear that money will be lost if the subcontract bids come in too high.
As the design selection process in CMR virtually mirrors the design process in DBB, imple-
menting CMR does not inherently restrict competition among designers and design subconsul-
tants (AIA 2005). Owners, at their own discretion, occasionally require the designer in a CMR
project to have previous CMR experience, which may result in fewer qualified proposers. As the
constructor is selected on the basis of qualifications and past performance and must also have
the capability to perform preconstruction services, CMR project delivery can constrain compe-
tition to those constructors that have previous CMR experience. Most public CMR laws require
competitively bidding out the construction trade subcontract work packages. The central idea
of CMR is to get the advantage of price competition in the subcontract work packages combined
with the qualifications-based selection of the GC as CMR.
Design-Build (DB)
Design-build is a project delivery method in which the owner procures design and construc-
tion services in the same contract from a single legal entity referred to as the design-builder. A
variety of methods exist for selecting the design-build constructor. Common methods are the
one-step and the two-step processes. The one-step process provides for competitive evaluation
of technical proposals, with the contract award decision based on best value to the owner agency.
The determination of best value is based on a combination of technical merit and price. The two-
step process separates the technical proposal from the price. This method typically uses request
for qualifications (RFQ)/request for proposal (RFP) procedures rather than DBB invitation-for-
bid procedures. There are a number of variations on the DB process, but all involve three major
components. First, the owner develops an RFQ/RFP that describes essential project requirements
in performance terms. Second, proposals are evaluated. Finally, with evaluation complete, the
owner must engage in some process that leads to contract award for both design and construc-
tion services. The DB entity is liable for all design and construction costs and must usually pro-
vide a firm, fixed price in its proposal (El Wardani, Messner, and Horman 2006; Ibbs, Kwak, and
Odabasi 2003; and Graham 2001).
Figure 2.3 shows that from the owner's standpoint, DB simplifies considerably the project's
chain of responsibility. As in CMR, the builder has early constructability input to the design
process. As the owner no longer owns the details of design, the owner's relationship with the
Owner
Design-
Builder
Designer Builder
Contracts
Communication
(Adapted from American Institute of Architects 1996.)
Figure 2.3. Design-build.