Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 108
APPENDIX E
State of Practice
This appendix discusses the methodology and findings of Tasks 1 and 2 of the research effort.
The purpose of Task 1 was to complete a comprehensive literature review relative to ROW cost
estimating while Task 2 involved examining and documenting successful ROW cost estimation
and cost management practices.
The literature review completed by the research team for NCHRP Project 8-49 served as the
foundation for additional searches of published information concerning ROW estimation. It was
necessary to update the original literature review because there has been additional work around
the country directed at estimation accuracy since the NCHRP Project 8-49 literature review was
conducted. The present literature review specifically targets ROW issues. Therefore, the main
objective of Task 1 was to identify documented practices in the area of cost estimation and cost
estimate management specifically relevant to the ROW component of project development. This
review primarily focused on current literature and established the basis for the later stages of
the research.
The main objective of Task 2 was to gain an overview of SHA ROW practice. Additionally, the
practices of several other agencies engaged in estimating the cost of future ROW purchases were
examined. Consequently, successful SHA and local public agency practices in estimating and
managing ROW costs were examined in detail. The research team assembled data on state-of-
practice cost estimating and cost estimate management techniques, including process steps and
tools in relation to the project development phases presented in Chapter 1.
Literature Review
The objective was to identify documented practices in the area of cost estimation and cost
estimate management specifically relevant to the ROW component of project development.
The literature review included locating and reviewing information found in technical papers,
reports, and documents. The sources were
· General internet search engines;
· The Transportation Research Board's TRIS Online;
· Academic databases, such as LexisNexis and Engineering Village 2;
· The ASCE Civil Engineering database;
· Selected SHA websites; and
· Presentations and papers posted on AASHTO's Subcommittee on Right-of-Way and Utilities
website.
The literature review concentrated on documenting and comparing factors and variables that
affect ROW cost estimating such as project type, property value prior to the project, anticipation
E-1
OCR for page 108
E-2 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
of future land use change, timeline, information available at the time of the estimate, and type
of acquisition. Information related to the ROW cost estimation and cost management processes
and tools in the literature were surveyed. The accumulated information was reviewed, analyzed,
and summarized. Although there is an abundance of literature on appraisal and acquisition
of ROW, the research team discovered only a limited amount of information that specifically
related to ROW cost estimation and cost estimate management.
ROW Cost Estimation and Management
The initial NCHRP Project 8-49 research identified ROW costs to be a critical highway proj-
ect cost escalation driver. This was further confirmed by the literature review. ROW cost estima-
tion is a complex undertaking dependent on a magnitude of parameters that are difficult to
quantify, even in the case of an identifiable date only a few years in the future. ROW cost esti-
mates must capture all costs that affect the expense of acquiring the needed property. This is
exceedingly difficult due to the uncertainties involved in many aspects of ROW acquisition. It is
typically necessary to capture deterministic values for each parcel in the following categories:
· Land;
· Property improvements;
· Damages to property in partial takings;
· Utility relocation; and
· Relocation assistance.
The literature particularly stresses the difficulty in estimating ROW cost due to uncertainty in
real estate appreciation and the issue of damages resulting from a partial take. Land values con-
stantly fluctuate and future values are difficult to assess, especially in the case of estimates com-
pleted during the earliest stages of project development. Damages are affected by the size and
shape of the remainder area, location of the remaining access points, reductions in highest and
best use, and length of remaining frontage (Buffington et al., 1995).
In addition, takings by eminent domain or condemnation must be considered when develop-
ing an estimate--that process increases the cost of an acquisition because of legal fees and the
court's sympathy toward a land owner. Eminent domain proceedings add cost uncertainty because
real estate value is determined by judges or juries instead of by definitive market information.
Almost 80 percent of all acquisitions are completed without condemnation (CTC Associates and
WisDOT, 2006) leaving about 20 percent of parcels, on average, that proceed to eminent domain.
However, the percentage of properties proceeding to eminent domain increases when owner's
legal fees are paid by the SHA (FHWA, 2006).
The US Supreme Court case of Kelo versus City of New London, which was decided on June
23, 2005 (Kelo, 2005), affected eminent domain expense throughout the nation (Cambridge Sys-
tematics, 2006). The Kelo case involved the use of eminent domain by the city of New London,
Connecticut, for a community redevelopment project that benefited a private entity. The Court
ruled 5 to 4 that the city's action was permissible under the Takings Clause of the Fifth Amend-
ment. Following wide criticism of the ruling, during the period immediately following the rul-
ing and through July 31, 2006, 29 states enacted changes to their eminent domain laws in one
or more of three ways: (1) restricting the use of eminent domain to certain situations; (2) requir-
ing additional procedures when using eminent domain; and/or (3) defining or redefining certain
terms associated with eminent domain (U.S. Government Accountability Office, 2006). Federal
legislation was also passed in 2006 to address the issue of using Federal funds in eminent domain.
Section 726 of The Transportation, Treasury, Housing and Urban Development, The Judiciary, and
Independent Agencies Appropriations Act of 2006 established that federal funds can only be uti-
lized for public use where "public use" excludes economic redevelopment (Towcimak, 2006).
OCR for page 108
Appendix E E-3
Public use is further clarified with the wording that is should "not be construed to include eco-
nomic development that primarily benefits private entities" (Transportation, 2006). While the
language of the 2006 Appropriations Act was applicable only to projects funded by the act there
is similar language in the 2008 Act (PL. 110-161).
New compensation requirements benefiting property owners have also been passed by some
states since the Kelo decision (Feldman, 2007). These state acts address
· Acquisition costs, including appraisal fees, attorney fees, and expert witness fees;
· Relocation costs, including actual costs of rebuilding structures and compensating business
for loss of business; and
· "Supercompensation" payments, meaning paying a certain percentage over fair market value.
The accuracy of an estimate is also affected by time constraints placed on completing the
estimate, the quality of information available, and project and parcel complexity. Accuracy suf-
fers under estimate preparation time constraints because the estimator has a limited amount of
time to research the project and appraisal data. Similarly, the quality of available information
can have a negative effect on the estimate because the estimate can only be as accurate as the
information upon which it is based. In an attempt to improve ROW cost estimates, several tools
and models for ROW cost estimation have been developed. Recently a cost estimation model
was developed by Kockelman et al. (2004) in cooperation with TxDOT. Based on data from
TxDOT and a commercial property database (CoStar), three models were developed. The
accuracy of these models in predicting parcel acquisition cost was acceptable in the case of
agricultural and vacant parcels, but the model lacked accuracy in the area of commercial and
residential takings. Although the models were not accurate predictors in these areas, the
authors argue that the tool may be used in budgeting for gross total ROW cost in a TxDOT
District (Kockelman 2004).
Early ROW estimates are often only gross approximations arrived at by using a percentage
of the estimated construction cost (CTC Associates and WisDOT, 2006) or some other order-
of-magnitude estimating technique. Project definition is frequently nebulous during the plan-
ning phase of project development; therefore, ROW boundaries at this point are not well defined.
Furthermore, there may be multiple project alternatives being considered during the planning
stage of project development. Alignment changes are likely, and these may significantly affect
the ROW cost estimate.
It was reported that early public involvement in the form of public meetings is beneficial
because it allows the SHA to gauge the level of support for a project. This can serve as an indica-
tor of the rate of condemnations and even the amount of contingency to include in the estimate
(CTC Associates and WisDOT, 2006). A larger ROW cost contingency might be necessary if pub-
lic support is absent because this may be an indicator as to the number of condemnation parcels
that can be expected.
Selected SHA websites, including those of California, Florida, Georgia, Minnesota, Ohio,
Wisconsin, and Virginia, were searched for procedures and manuals on cost estimation of
ROW and other aspects of ROW procurement. Much of the material found on the SHA web-
sites related to appraisal and acquisition of property, including procedures and forms used
throughout the process. Caltrans devotes a chapter of its Right of Way Manual (Right, 2007)
to ROW cost estimating. This information can be found on line at www.dot.ca.gov/hq/
row/rowman/manual/ch4.pdf (Estimating, 2007). The manual specifically discusses aspects
of the estimate and general estimate information. The Ohio DOT has a specific procedure for
estimating cost of ROW (2300 Cost Estimation . . . 2007). This procedure is tied to the Ohio
DOT project development process.
OCR for page 108
E-4 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
ROW Appraisal and Acquisition
It should be emphasized that much of the literature focuses on the appraisal and acquisi-
tion of the parcels rather than directly discussing cost estimation and cost estimate manage-
ment. Kockelman discusses how the dollar amount for appraised property values is established
through three methods: (1) the Sales Comparison Approach; (2) the Income Approach; and
(3) the Cost Approach (Kockelman et al., 2004). These approaches vary in methodology and
application. The Sales Comparison Approach in which comparable sales in the area establish
the base dollar value of the property is, by far, the most common approach. The Income
Approach is typically used in commercial or investment properties. It attempts to estimate the
income that will be realized from the property. The Cost Approach is used when comparable
sales cannot be found in the area and calculates the cost of replacement minus any deprecia-
tion of the existing structure.
The Uniform Act of 1970 (Uniform, 1997) governs the treatment of property owners for all
federally funded projects by providing a set of procedures and standards for ROW acquisition.
The major implementation of this act is that all property owners be justly compensated for their
property and receive relocation assistance.
Condemnations are a concern when acquiring property because they can increase costs and
delay the project. Condemnation rates (or the percentage of properties that move to condemna-
tion proceedings) vary from state to state. The FHWA notes that the percentage of parcels pro-
ceeding to condemnation can be reduced by (1) the use of mediation methods between the prop-
erty owners and public agency; (2) the use of well-trained ROW agents handling acquisitions
who are authorized to negotiate settlements; and (3) the use of quick settlements in lieu of allow-
ing the property owner a long period of time to consider the offer (FHWA Office of Real Estate
Services, 2006).
Hakimi and Kockelman (2006) discuss best acquisition processes while considering the
uniqueness of each state in terms of political, social, environmental, and other factors. They
recommend that the public should be contacted early in the process and that states should
update laws and statutes to outline compensable items so as to streamline the acquisition
process. Additionally, special acquisition techniques, such as land exchange, land consolida-
tion, and advanced acquisition, should be used. Such techniques may not be available in all
states; however, such techniques should be considered to the extent allowed under state law.
A few such techniques are outlined in the "European Right of Way and Utilities Best Practices"
report (European, 2002).
In summary, the method of ROW appraisal and acquisition can affect the accuracy and con-
sistency of cost estimation and cost estimate management. Appraisal and acquisition methods
must be understood by those who prepare ROW cost estimates. The appraisal and acquisition
methods should be integrated into the overall project development process. As noted in the
literature review of cost escalation factors completed in the NCHRP Project 8-49 research, in-
accuracies and/or delays in ROW acquisitions can affect project cost escalation profoundly.
Literature Review Summary
The literature review provided a basis for further research. ROW appraisals and acquisitions
constitute much of the ROW literature. The ROW cost estimation literature that was discovered
was limited to several statistical estimating models, discussion of the effect of the Kelo case, and
several piecewise descriptions of the line items of an estimate. It provided selected information
on the effects of condemnations, land appreciation, and damages.
OCR for page 108
Appendix E E-5
Research Methodology
In addition to the literature review, a series of onsite and telephone interviews were conducted
with agencies across the United States. The goal of these interviews was to collect data on cur-
rent successful ROW cost estimation and cost estimate management practices. Seven SHAs and
two local public agencies were interviewed.
Interview Protocol
An interview protocol was developed to guide data collection during interviews. The objec-
tive of the interview protocol was to capture successful practices, including ROW cost estima-
tion process steps and tools. It was modeled after the interview protocol used for NCHRP Proj-
ect 8-49. Questions were developed based on findings of the literature review. In particular,
the literature review findings identified problem areas that needed to be addressed through the
interviews.
The interview protocol covered six areas and consisted of 15 questions. The areas of interest
to this research were similar to those in the original NCHRP Project 8-49, but were more spe-
cific to ROW issues. The interview questions examined six areas within ROW cost estimation
and cost estimating management:
1. Determining ROW Requirements;
2. ROW Cost Estimate Preparation;
3. ROW Cost Estimate Reviews;
4. ROW Cost Estimate Communication;
5. ROW Cost Estimate Management; and
6. State Laws and Other Factors that Affect the ROW Process.
The six areas of interest governed the organization of the interview protocol. Section 1 of the
protocol explored the process steps and tools used by the SHAs to determine ROW require-
ments. Based on these steps and tools, Section 2 examined how ROW estimators produced esti-
mates for the defined ROW requirements. More specifically, it addressed policies and procedures
guiding estimate preparation, the elements of each estimate, how environmental issues were
handled in the estimate, whether risk and uncertainty were considered, and if contingency was
applied to the estimate. Estimate review processes and practices were the focus of Section 3 of
the protocol. Section 4 addressed the issue of estimate communication and included training of
estimators and communication of estimating procedures. Section 4 also covered the issue of con-
tacting property owners. Section 5 of the protocol focused on how differences were reconciled
between estimates, the procedures for handling changes in ROW requirements, and triggers for
an update to ROW cost estimates. The effect of state laws and other factors such as environmen-
tal, political, and social issues on the ROW process and estimates were addressed in Section 6.
The effects of acquisition techniques such as advanced acquisition, incentive offers, and other
non-standard techniques on estimating ROW costs were also explored in Section 6.
The protocol was prefaced by several introductory pages that confirmed the interview time
and date, described the background of the research, and provided instructions and interview
expectations. The background material covered previous NCHRP Project 8-49 findings relative
to ROW, including a discussion of the typical project development phases relevant to ROW and
the basis for the ROW research. The instruction and interview expectation sections outlined such
aspects of the interview as the phased approach to be employed relative to each of the questions
during the interview and other details. Included in the interview package were the project devel-
opment phase flowcharts for planning, programming, preliminary design, and final design
that had been developed during the earlier NCHRP Project 8-49 work. These flowcharts were
OCR for page 108
E-6 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
included to bridge the terminology differences that exist among agencies and address some of
the factors limiting this research, which were discussed in Chapter 1.
Interview Participants
The seven SHAs interviewed were California, Florida, Georgia, Minnesota, Washington
State, Wisconsin, and Virginia. These SHAs were selected based on input provided in Phase I
of NCHRP Project 8-49. Each appeared to have systematic and relatively successful ROW cost
estimation practices from which the research could benefit. As noted in the methodology,
interviews were completed with participants from both the central office and with ROW
administrators in districts/regions around the state. In addition to interviewing SHAs, the City
of Phoenix Street Transportation Department and the O'Hare Modernization Program Office
of the City of Chicago were interviewed to provide further perspectives on ROW cost estima-
tion and cost estimate management. A list of interview participants by position from each
agency is provided in Table E.1.
Interview Process
Because of the complexity of the ROW cost estimation process and the information being col-
lected from SHAs, onsite interviews were the main activity used for data collection. The option
of a survey was ruled out because surveys would not provide adequate information describing
the ROW cost estimation process. Most issues could not be answered with yes/no or multiple-
choice answers. It was necessary to acquire in-depth information about the cost estimation
process that included some elaboration and explanation on the part of the interview participants.
Onsite interviews provided the opportunity to clearly communicate specifics about the process
and provide the detail necessary for developing the ROW cost estimation and cost estimate man-
agement flowcharts.
Interviews were conducted with SHAs and other organizations having experience with ROW
acquisition. The interview process focused on the four phases of project development to provide
a frame of reference for linking the application of successful ROW practices to the project devel-
opment timeline. This enabled effective data collection and helped to identify differences as
project development progresses. Contacts were acquired through Phase I of the NCHRP Proj-
ect 8-49 Project, and the FHWA Office of Real Estate Services also provided suggestions. Eigh-
teen formal SHA interviews (Anderson et al., 2007b) were conducted during the earlier phase
of the NCHRP Project 8-49. Experience from the previous research and recommendations pro-
vided the research team with valuable contacts possessing considerable experience and knowl-
edge of successful practices. Some SHAs, especially large states, are highly decentralized and rely
on the districts/regions within the state to manage projects and perform estimates. Therefore,
when interviewing SHAs, the research team attempted to capture perspectives from both cen-
tral office ROW administrators and other administrators in districts/regions around the state.
This provided diverse perspectives on ROW cost estimation and related issues.
The first step in the interview process was to contact the agencies. Upon initial contact with
the potential interview participants, the interview protocol was transmitted by email to the par-
ticipants several days prior to the scheduled interview. This enabled the participants to review
the protocol and prepare for the interview. Interviews were set up in 2- to 3-hour blocks to allow
ample time to cover the entire process from the first planning estimate to the activities required
during final design.
In most cases, the interview was conducted by two individuals from the research team. One
member would typically act as facilitator while the other took detailed notes. Both team mem-
OCR for page 108
Appendix E E-7
Table E.1. Agency interview participants.
Highway Agency Interview Participants
Senior ROW Agent Headquarters Office
Senior ROW Agent Headquarters Office
Senior ROW Agent North Region
Senior ROW Agent North Region
Senior ROW Agent District 3
California ROW Manager South Region
Senior ROW Agent South Region
Associate ROW Agent South Region
ROW Agent South Region
ROW Estimator South Region
ROW Estimator South Region
Appraisal & Review Manager
Georgia
Manager, ROW Cost Estimates
Manager, Appraisal & Appraisal Review
Director, Office of ROW
Deputy State Manager, Appraisal & Cost Estimating
Florida
State Cost Estimating Administrator
District One Cost Estimates Administrator (Bartow/Lakeland)
District Seven Cost Estimates Administrator (Tampa)
ROW Program Manager Central Office
Assistant Director, R/E & Policy Development Central Office
ROW Engineer District 1
ROW Engineer District 2
ROW Engineer District 3
Minnesota ROW Engineer District 4
ROW Engineer District 5
ROW Engineer District 6
ROW Engineer District 7
ROW Engineer District 8
ROW Engineer Metro
Assistant Director for Appraisal and Appraisal Review Program
Washington State Appraisal Specialist, Olympia Region
Appraiser, Olympia Region
Real Estate Supervisor SE Region
Real Estate Supervisor SE Region
Real Estate Supervisor NW Region
Wisconsin
Real Estate Supervisor District 3
Real Estate Supervisor District 5
Division Realty Office FHWA
Virginia Assistant Director ROW Manager
Projects Administrator
City of Chicago Relocation Manager
Director of Public Affairs
Traffic engineering Supervisor
City of Phoenix Acting Assistant Real Estate Administrator
bers took an active part in the interview. The first 15 minutes of the interview typically consisted
of introductions, a summary of the research background and framework, the objective of the
research, and statement of the research team's expectations of the interview. Additionally, the
status of the project and findings of previous interviews were summarized to provide the partic-
ipants with the current status and direction of the research project. Following the introductory
portion of the interview, the participants were probed for information regarding the SHA's proj-
ect development process and any special terminology. This served to give the research team a
basis for further questions and to relate participant answers to project development phases (plan-
ning, programming, preliminary design, and final design). Then, the facilitator would guide the
interview toward the first ROW estimate completed during planning. From this point on, a dis-
cussion proceeded in which interview participants would tell the "story" behind the SHA's ROW
OCR for page 108
E-8 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
cost estimation process. As the interview drew to a close, issues not yet covered were addressed
using the interview protocol as a checklist. The members of the research team would typically
use the time following the interview to make additional notes on general impressions of the inter-
view. All details were recorded in the interview protocol under the related questions.
In lieu of proceeding straight through the interview questions one by one, most interviews
began with general discussions, which led to specific topics within the context of ROW cost esti-
mation and cost estimate management. This practice was adopted during the first interview with
the Minnesota DOT. That interview served as a "test" dialogue for the newly developed proto-
col. Consequently, the protocol questions served more as a checklist to ensure that all issues were
covered. Shortly following the interview, an interview report was prepared which consisted of
filling out the protocol based on the interview notes. This allowed the team to capture and under-
stand the process for ROW cost estimation and cost estimate management used by the SHAs
throughout all phases of project development. In addition to the on-site interviews, conference
calls via telephone were used to follow up on any issues unclear after the initial interview.
Documents Collected
SHA ROW estimating tools were documented during interviews, and any documents describ-
ing the tools or examples of the tools that the agency used were requested at the time of the inter-
views or in follow-up emails and telephone calls. The documents gathered ranged from cost
estimate maps used to determine ROW requirements to cost estimate spreadsheets used in com-
pleting estimates. Screenshots of ROW tracking and estimate systems were also requested and
provided by the SHAs. The SHAs were always asked for copies or web addresses of manuals, poli-
cies, and procedures that supported their ROW cost estimation and cost estimate management
processes.
State-of-Practice Characteristics
Critical issues relating to ROW estimating were identified during the interviews as those most
difficult to estimate or issues that may have a significant effect (good or bad) on creating an accu-
rate estimate. Based on the responses of the interview participants, the most notable critical issues
include (not presented in an order of importance or priority rank)
· Condemnations
· Damages
· Inflation and other market conditions
· Risk analysis and assigned contingency
· Scope definition
· Estimating tools
· Estimator experience and knowledge
Condemnations
Estimating the costs of condemnations is very difficult because of two major factors. First,
there is the issue of determining the number of condemnations, or what percentage of parcels
will move to condemnation proceedings. The FHWA Office of Real Estate Services' report on
state condemnation practices (2006) indicated that approximately 80 percent of acquisitions are
completed without condemnation while FHWA online data reported a 12.5 percent condemna-
tion rate for 2004 and a 12 percent condemnation rate for 2005 (FHWA, 2007). This variable is
study specific and may vary drastically between projects, between regions/districts, or even
OCR for page 108
Appendix E E-9
within regions/districts. As discussed previously in the literature review, the condemnation rate
is heavily dependent on state laws governing the process and whether the public agency is respon-
sible for paying acquisition costs of the property owner such as appraisals, expert witnesses, and
other legal fees (FHWA Office of Real Estate Services, 2006).
The second issue is the actual cost of the condemnation proceedings. Condemnation expenses
include engineering, appraiser, and economists' fees plus attorney and court costs, and the final
condemnation award amount. The fee portion, together with legal costs, may add significantly
to the cost of a condemnation proceeding. Additionally, states have specific laws concerning con-
demnations. In one state it is the financial responsibility of the acquiring agency to reimburse
the property owner for an independent appraisal if such is requested by an owner. This stipula-
tion is a result of the Supreme Court Kelo decision. Condemnations may cost a project more
than just money: the proceedings may cost the project valuable time. Proceedings can delay a
project schedule. Time delays then affect estimated construction cost. The cost and rate of con-
demnations is heavily dependent on state laws and social factors that exist in a particular local.
Damages
Damages due to partial takings of a property were indicated by agencies to be one of the most
difficult aspects of ROW estimating. The definition of the term under 23 CFR Ch. I (4102
Edition) § 710.105 Definitions is
Damages means the loss in value attributable to remainder property due to sever-
ance or consequential damages, as limited by State law, that arise when only part of
an owner's property is acquired.
Damages are primarily an issue in acquiring a portion of a business. Assigning a cost to
damages can be very subjective and, many times, the accuracy of the estimated cost is depend-
ent on the experience of the estimator.
Real Estate Inflation and Other Market Conditions
Assessing the potential effect of inflation/appreciation and other related real estate market
conditions is a challenge. This is an issue in preparing cost estimates during every project devel-
opment phase. Property values increase at rates different than the inflation rates for construc-
tion materials and labor. Properties in highly urban areas or areas where there is substantial
growth potential may be subject to substantial increases in the market value of land. The results
of the interviews in this project were consistent with the interviews and data collection in Phase I
of NCHRP Project 8-49 concerning inflation and other market conditions.
Risk Analysis and Assigned Contingency
The majority of agencies interviewed made no attempt to conduct a formal detailed risk analy-
sis of items that could affect ROW cost, although most agencies did assign contingency amounts
in some manner. A detailed risk analysis can be defined as a systematic method of identifying
and evaluating risks using a formalized agency procedure. The majority of agencies reported that
they did not specifically address risk analysis in a formalized and documented procedure. Only
two SHAs reported performing detailed risk analyses where specific project risks are identified
and then addressed by some application of contingency. Risks affecting ROW derive from the
schedule, property appreciation, condemnations, damages, and other issues that exhibit uncer-
tainty or may be unknown. Moreover, the use of contingencies was an issue throughout the
SHAs interviewed. Four SHAs reported the regular practice of applying a contingency to their
OCR for page 108
E-10 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
ROW estimates: the two aforementioned states using detailed risk analysis and two others who
explicitly assign a contingency. Other SHAs may apply contingency values subjectively based on
the estimator's opinion or judgment about the cost estimate.
Scope Definition and Estimating Tools
Determining a project's ROW requirements early in the development process is problematic,
particularly during the planning phase (e.g., 10 to 20 years out from the estimated construction
letting year). Phase I of NCHRP Project 8-49 found that actual cost of project ROW is frequently
greater than the estimated cost projected during the early stages of project development. Two
primary factors can explain this: (1) inadequate scope definition and (2) the absence of effective
tools and methods to complete ROW cost estimates. ROW estimates made during the planning
phase of project development are often based solely on a percentage of estimated construction
costs. Agencies using this method maintain that the cost benefit is not substantial enough to
invest staff effort in more detailed ROW estimates at this early stage because (1) limited project
scope information is available, (2) there are multiple alignments to consider, and (3) there will
be inevitable changes to the project as scope is refined as the project moves through develop-
ment. This is not the case, however, with the Cities of Chicago and Phoenix, which finance their
projects with bond money and therefore must have accurate cost estimates before going to the
bond market. Both cities work hard to define project scope in detail early in project development
and to develop accurate early ROW cost estimates.
Estimator Experience and Knowledge
Estimator experience was consistently noted as heavily affecting the quality and accuracy of
ROW cost estimates. In achieving estimate accuracy, the estimator's knowledge of the project
area and market plays a role in many subtle ways. SHAs are facing issues related to personnel
turnover, especially related to employees with 15 to 20 or even 30 years of experience in ROW
cost estimating. These people are quickly reaching retirement and when they depart, invaluable
experience and knowledge will be lost.
Overview of Current Practice
A ROW cost estimate is produced during each of the first three phases of project develop-
ment: planning, programming, and preliminary design. Before preparing the estimates, ROW
requirements must be provided by planners or the project design team to establish the basis
of the estimate. Following preliminary design, appraisals and acquisition typically commence.
Typically, no further cost estimates are generated at final design, but ROW cost management
should continue as purchases are executed. ROW cost management occurs during final design
and is completed by comparing actual costs reflected in the appraisals and acquisitions to the
estimated costs. If actual costs exceed the estimated amount, the project manager is notified
and action is taken to either request additional funds or to make design changes that might
reduce ROW cost. Additional ROW needs are sometimes identified during construction.
When this occurs, the staff members responsible for ROW cost management must work
closely with the agencies construction and design sections to minimize the effect of these new
ROW requirements.
The following subsections discuss the current and general state of practice relative to each of
the project development phases. Current practices are discussed in a general manner that out-
lines the overall state of practice in the SHAs interviewed. Later in this appendix, specific suc-
cessful practices will be covered and critical review of these practices is presented.
OCR for page 108
Appendix E E-11
Determining ROW Requirements
The basis of a ROW cost estimate is the ROW requirements and this is dependent on the level
of project scope definition. Even in the case of a planning-level ROW cost estimate where the
estimate is based on a percentage of estimating construction cost, the ROW estimate is depend-
ent on the planner's ability to develop a reasonable scope definition to confirm the percentage
applied. Typically, scope definition is clarified as the project development process proceeds from
the initial planning phase to final design and construction.
The need for a project is typically defined in the initial project development phase of planning
where scope definition is often nothing more than a statement of purpose and need. The scope
at this point is expressed in very general or broad terms and usually consists of only an approx-
imate number of lanes or a width or several potential alignments, with little definitive support-
ing information available. A ROW estimator typically is not involved at this stage, and it was
found that ROW estimates are often completed within the agency's Planning Division and are
not the responsibility of the ROW Division. As previously stated, a percent of the estimated con-
struction cost is often used at this point in the process.
At the programming phase of project development, the scope of the project has been further
defined and usually an alignment relating to ROW needs has been determined. In the case of
most SHAs, the ROW division or group will receive a request from the project manager for a
ROW cost estimate. This request is often accompanied by an aerial map or other visual repre-
sentation of the project site with approximate ROW boundaries indicated. This aerial map
defines the ROW requirements for the project. The total area to be acquired may also be indi-
cated. In some cases, SHAs reported that rough parcels would be indicated along with parcel
areas, but this is not common practice at programming.
ROW requirements during preliminary design are reflected in an updated aerial map or a pre-
liminary drawing provided by the design engineers. The map typically shows the refined ROW
boundaries, defines each parcel, shows parcel boundaries, and provides the areas required for
each parcel.
Final ROW plans exist at the final design phase in which all ROW requirements are explicitly
defined as parcels. No further estimates are completed at this point as ROW appraisals begin,
followed by acquisition of parcels. It is likely that some changes may occur during final design
that will affect the ROW requirements; while such changes are typically minor in extent, they can
affect ROW cost significantly. In that case, new ROW plans may be released and reconciliation
of the cost changes occurs, if necessary.
General ROW Cost Estimating Practices During Planning
During planning, ROW estimates in many SHAs are usually based on percentages of construc-
tion costs. Historical ROW costs from general databases or ROW cost from comparable projects
may also be used to produce this early estimate. Construction costs for planning estimates, as
outlined in NCHRP Report 574, are frequently based on lane-mile cost factors and prepared by
planners. If ROW is required, the estimate for this project cost component often does not involve
the ROW division. Planners also prepare the ROW estimate. In general, planning estimates are
used for long-term budgeting. The ROW amount defined in the planning estimate appears to
have minimal bearing on later estimates.
General ROW Cost Estimating Practices During Programming
When preparing the programming estimates, a field visit to the project location is usually com-
pleted by the estimator. The ROW estimator assigned to complete this early estimate generally
OCR for page 108
E-12 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
will either walk or drive the project and note pertinent details such as improvements to be
removed, potential damages due to partial takings, and the general topography of the project
area. Improvements to be removed include any structure, pavement, outdoor sign, or any other
enhancement to the property that is necessary to remove before construction begins. A determi-
nation must be made by the estimator related to the current use of the property because the land
values may be drastically different for each use. The estimator must determine whether the use
of the property is residential, commercial, industrial, or agricultural. The ROW estimator will
prepare the estimate based on the ROW requirements per the aerial map and any data obtained
during the project site visit.
SHAs typically have a cost estimate sheet or checklist to ensure that all elements affecting ROW
costs are considered. This is the case for the estimates completed during programming, which
usually sets the baseline budget (the estimate by which all other estimates are compared for cost
management purposes). A cost estimate sheet will have line items for all elements to be included
in the estimate. Typically, the major estimate elements are (1) land, (2) improvements, (3) relo-
cation costs, (4) damages, and (5) condemnations.
Land values are established by comparable sales in the general project area using resources
such as the tax assessor's records, area realtors, or commercial realtor databases. At this point in
project development, the estimate is normally completed on a gross area basis. Therefore, the
estimator is looking to establish a value to apply to the total ROW area on a price per acre or
price per square-foot basis, depending on property use.
Improvements to the raw land and the condition of the existing site improvements must be
included in the cost estimate. In addition to justly compensating land owners for their proper-
ties, improvements (e.g., buildings, outdoor signs, and parking lots) must be included in the
compensation.
Relocation costs for all displaced individuals and their belongings are included in the estimate.
Most SHAs appear to have reasonable data for estimating relocation costs and apply a set dollar
amount, based on recent historical costs and depending on the type of displacement (business,
residential owners, or residential tenants).
Damages are hard to estimate in almost every case. Estimating such costs requires judgment
on the part of the estimator. A value must be assigned based on the size, shape, and use of the
parcel remainder. The estimator's experience and knowledge of the area are very important in
establishing this amount.
Condemnations are based on historical data and/or previous experience of the estimator in the
project area. The condemnation rate (or the percentage of parcels that will proceed to condem-
nation) must be estimated in addition to the actual costs of those parcels that may proceed to con-
demnation. The condemnation rate differs drastically from state to state because of state laws
adjudicating property rights and state laws governing condemnation proceedings. Condemna-
tion rates are estimated based on recent project experience in the area, but estimating the con-
demnation rates is still very subjective given that a human factor is always involved. The human
factor can be defined as the uncertainty and unpredictability related to dealing with property own-
ers when an agency is attempting to acquire their property. The reaction of individuals to an
agency acquiring property is difficult to predict. If the condemnation rate is estimated accurately,
the cost of condemnations will usually be accurate because they are primarily based on state laws.
General ROW Cost Estimating Practices During Preliminary Design
At the preliminary design phase of project development, the ROW cost estimate is further
refined. In most cases, this is a completely new estimate developed by the ROW division person-
OCR for page 108
Appendix E E-13
nel, but it may be an update of a previously developed estimate. This varies by SHA. The estima-
tor usually makes a project site visit to explore any issues not apparent from aerial photos or pre-
liminary plans defining the ROW requirements. The project manager or project engineer will
often accompany the ROW cost estimator to provide input on probable design scenarios that
will affect the ROW requirements and cost, and the potential trade-offs between ROW and
design may be discussed.
Again, a cost estimate sheet is used in producing the estimate to ensure that all aspects of ROW
cost are included in the estimate. The same line items included in the programming estimate
sheet are examined for this estimate but now are examined in more detail (e.g., parcel informa-
tion should be available by this point in project development). The preliminary design estimate
is completed using parcel-by-parcel data where a cost is estimated for each individual parcel. This
is the last cost estimate completed before the project is programmed in the State Transportation
Improvement Program (STIP).
Other than the estimates described here, update estimates may occur when major changes
occur in project design. These changes, though, must be communicated to the ROW Division
by the project manager or project engineer. Communication becomes important in this case.
Many SHAs attempt to update estimates annually, but some SHAs noted that the size of their
ROW offices or groups of individuals is too small for a comprehensive annual update.
General ROW Practices During Final Design
Final ROW plans are released during the final design phase--appraisals begin, followed by
acquisition. No further cost estimates are prepared. ROW acquisition can begin in earlier phases
through protective buying, hardship acquisition, and other early acquisition actions, but most
SHAs responded that these were seldom used because of bureaucratic issues such as state laws
restricting the length of time ROW can be held after purchasing and prior to construction on the
property.
In general, the ROW agents in charge of appraisals and acquisition will be aware of cost
overruns, but requesting more funds seems to be the current practice instead of attempting to
manage costs to a previously set budget.
Estimate Review and Approval Practices
Review of a completed estimate during any of the project development phases is typically lim-
ited to a visual scan by the estimator's supervisor. In specific cases where the cost of ROW is
extremely high in value, a division head may be required to sign off on the estimate. The SHAs
contacted had no formal and documented review process covering ROW cost estimates. ROW
supervisors typically have many years of experience with ROW estimates and perform high-level
reviews of the cost estimate by using "rules of thumb" and heuristics that they have developed
through their years of estimating experience. This is completed by examining the major elements
of the estimate that have a large effect on ROW cost. The supervisor then determines whether
these elements of the estimate appear consistent with past cost experience and subsequently
approves or disapproves.
State Laws and Other Factors
State laws and environmental, political, and social factors affect the ROW cost estimation
process and affect ROW cost. The effects of these laws and factors vary by state. The Kelo versus
City of New London case which went to the U.S. Supreme Court seems only to have affected
OCR for page 108
E-14 Procedures Guide for Right-of-Way Cost Estimation and Cost Management
SHAs to a limited extent given that most highway agency practices were in conformance with
the requirements prior to the case result. However, changes have been made to the eminent
domain laws in several states. Interviews confirmed that some state legislatures have passed laws
requiring the SHAs to reimburse property owners for private appraisals, attorney fees, and/or
other acquisition costs up to a certain value. Furthermore, some states have tightened ROW con-
demnation requirements in the areas of notification and time to respond to SHA actions. All
states have a defined process for condemnation proceedings and, depending on the state, con-
demnation actions can delay project construction starts.