3
A Strategy for Managing the Infrastructure

The Strategy

Although highly structured, formalized strategic planning activities, with accompanying volumes of data and staff analyses, are no longer in vogue in the private sector, successful enterprises now do implement explicit, well-coordinated plans for action involving all functional departments, with a common set of goals and coordinating mechanisms. The major finding of this study is that the Navy lacks an overall strategy for achieving the resource shifts necessary to support its recapitalization needs.1 This chapter draws extensively from experiences in both the public and private sector and offers a strategy for managing the entire infrastructure.

1The committee's finding that the Navy lacks an overall strategy is similar to a conclusion reached by the GAO in its investigation of the Department of Defense infrastructure. See the following reports: U.S. General Accounting Office. 1997. High-Risk Series: Defense Infrastructure, Letter Report, GAO/HR-97-7, Washington, D.C., February 1,p. 10, available online at < http://www.access.gpo.gov/cgi-bin/getdoc.cg?dbname=gao&docid=f:hr97007.txt>; and U.S. General Accounting Office. 1997. Defense Budget: Observations on Infrastructure Activities, GAO/NSIAD-97-127BR, Washington, D.C., April 4, p. 32, available online at <http://www.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=gao&docid=f:ns97127b.txt>. Furthermore, in the first of these reports the GAO noted the following: “However, breaking down cultural resistance to change, overcoming service parochialism, and setting forth a clear framework for a reduced infrastructure are key to avoiding waste and inefficiency. To do this the Secretary of Defense and the service Secretaries need to give greater structure to their efforts by developing an overall strategic plan.”

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 50

What Is to Be Achieved?

The objective is to provide essential fleet support at reduced cost to make resources available to recapitalize, modernize, and increase the performance of the fleet, and thereby strengthen the Navy's core capability (fielding and using fighting forces) for the next century. The current budget for the infrastructure is $26.7 billion, from which cost savings of $3.5 billion to $5.0 billion are required.

How Is It to Be Achieved?

The objective can be achieved only by changing the Navy's business structure and modes of providing operational support—specifically, by adopting modern enterprise process technology and practices; competitive sourcing of as many of the support functions as possible with acceptable risk; learning by doing, so that adjustments can be made to these unfamiliar activities along the way; and building in safeguards against loss of support for the core capabilities during the transformation.

The following elements are essential to a successful strategy for achieving the shifts in resources needed for recapitalization:

• Knowing the cost structure of all the infrastructure activities, so that the Navy can understand where the leverage is, and therefore where to expend its efforts;

• Setting goals (money and time), assigning consistent responsibilities and authorities, and making plans that can be followed;

• Setting up a management information system to track support-system performance and costs;

• Rationalizing command and organizational responsibilities, authorities, and accountability to accord with the overall objective of the strategy;

• Preparing revised internal rules and procedures, and proposing legislative changes;

• Involving those affected inside the Navy, in other Services, and in civilian communities; and

• Obtaining agreements and legislation as needed in the Department of the Navy, DOD, the Office of Management and Budget (OMB), and Congress.

With What Is It to Be Achieved?

The resource and leadership requirements to accomplish the strategy are discussed explicitly in this chapter. These requirements involve the following:

• Commitment on the part of the top levels of Navy command and administration to reach the objective, as discussed in Chapter 4; and

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 51

• Adoption of key policy, technology, and business management enablers for systematic use throughout the Navy, as enumerated below.

Findings

Efforts to date to reduce the cost of the infrastructure (achieved through regionalization, consolidation of functions, personnel and facility downsizing, competitive sourcing, Smart Base initiatives, and so on) have achieved only a small fraction of the resource shifts required to meet the Navy's modernization goals. The committee estimates that these efforts, when fully implemented Navy-wide, could reduce infrastructure costs by about $0.5 billion per year. However, the funds required to modernize the Navy are in the range of $3.5 billion to $5.0 billion per year. These current efforts are, therefore, inadequate to meet the modernization goals. A major evaluation and process change in the way the Navy conducts all elements of its infrastructure operations will be necessary to achieve the added cost reductions required to modernize the fleet. However:

1. The Navy currently does not have a proven methodology for conducting this evaluation or for implementing and managing change in its infrastructure operations.

2. The Navy also does not have a methodology for determining, on a continuous basis, current industry “best practices” for fleet support functions.

3. Networked information systems can be a major enabler for cost reduction by enhancing access to and accountability for services. Compatible software applications and systems and shared information elements that facilitate interoperability for management control must be available, in addition to connectivity, before the benefits can be realized.

The committee also believes that the scope of this evaluation and process change, sometimes referred to as “reengineering the organizations,” needs to be broad enough to materially affect all of the major claimants for the infrastructure dollars in question and should go deep into the hierarchy so that responsible managers will have the opportunity to change both the quality of service provided and the cost of delivery. All this must be accomplished within a decisionmaking framework where the interests of all users of infrastructure products and services are represented.

The committee notes that no single staff element in OPNAV or the Secretariat has sufficient oversight responsibility and authority to manage all of the infrastructure resources highlighted in Figure 1.2. Thus, responsibilities and authorities to implement change must be made clear and issued by the CNO.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 52

Recommendation

The senior leadership of the Navy should immediately initiate a process to improve the business operations of the entire Navy infrastructure with the goal of reducing costs by the $3.5 billion to $5.0 billion per year required to fund modernization of the fleet. To effect needed changes, a proven management methodology should be used that includes the following essential elements:

Establishment of a practical vision of the future, with quantifiable goals, shared by all of the senior stakeholders in the Navy;

Development of strategic proposals to move in the new direction and to deal with obstacles;

Development of tactical plans for implementation, including task forces, milestones, and time tables;

Clear assignment of responsibilities, authorities, and accountability;

Follow-up progress reviews at regular intervals;

Development of key output metrics for success, tracking of accomplishments against them, and requirements for results;

Incentives and rewards for positive performance and punishment for noncooperation;

Celebration of victories; and

Continuous improvement, because change is continuous and cannot be accomplished instantly.

This same methodology should be employed at successively lower levels of command to align their goals, incentives, and metrics with the Navy's larger strategic goals until the entire process of change has been institutionalized across the Navy.

Navy-Wide Enablers

Although the list of business practices that can be used to improve productivity and reduce costs is extensive, the committee recommends that the Navy focus on three key enablers for application throughout the infrastructure and that it make the commitment to implement them fully without exception and without compromise. The three enablers, discussed below in the context of improving Navy infrastructure productivity, are as follows:

• Performance measures, cost management and allocation of resources,

• Information technology for infrastructure management, and

• Competition.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 53

Performance Measures, Cost Management, and Allocation of Resources
Level of Service

Accurate vision statements are important to establishing strategic plans and measuring progress toward achieving the vision. The committee noted that included in the 21st Century Shore Support Infrastructure: Navy Infrastructure Vision and Strategic Plan is the statement: “Our motto should be: Equal to or better service at equal to or less cost.”2

This theme was evident throughout the committee's briefings and site visits and has clearly permeated the entire organization. Although this philosophy is typical Navy “can do” and is understandable, it is inconsistent with the goal of reducing the infrastructure to the minimum necessary to satisfy the users' requirements. It establishes a particular mind-set throughout the organization that potentially precludes critical analysis of where the goods or services provided exceed user requirements or where the cost of providing the last n percent of quality or quantity is not cost-effective (e.g., as when providing the last 5 percent of the quality or quantity consumes 20 percent of the cost). This kind of critical analysis is a fundamental management tool in determining the “knee of the curve” for providing goods and services and the return on the investment, and it is a necessary component of determining opportunities for reducing the infrastructure without eliminating real required goods and services. If the infrastructure is to be reduced to the level that is necessary, it must be understood and accepted by both the users and the leadership that is acceptable for the infrastructure to provide only the minimum quality and quality of goods and services to satisfy the user's requirements.

Finding

The current Navy infrastructure vision and strategic plan discussed above may reduce the likelihood of obtaining critical analysis of the value of goods and services provided (e.g., essential services at minimum cost) and thereby impede cost-effective reductions in the infrastructure.

Major Recommendation

The Navy should change its statement of infrastructure vision to“Essential service at minimum cost.”

2Hancock, VADM W.J., USN, Deputy Chief of Naval Operations (Logistics, N4). 1997. 21st Century Shore Support Infrastructure: Navy Infrastructure Vision and Strategic Plan, Washington, D.C., June 24.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 54

Output Measures

The reason for attempting to reduce and streamline the infrastructure is to reduce costs and free up funds to recapitalize the Navy. To date, streamlining has been done mainly by arbitrarily reducing funds for the infrastructure and charging the infrastructure with developing new and innovative means of providing the same or better service at lower cost. There is, however, no way of knowing if the reductions in funds in different areas are too great or not great enough—i.e., will the reduction in funds result in a loss in capability and readiness, or is there potential for even greater reduction? Without a means of measuring the output of the infrastructure, these questions cannot be answered and the Navy is left with trial and error, which potentially can lead to serious degradation in the necessary support provided to the operating forces.

Traditionally the Navy has, for the most part, used inputs in determining the performance and requirements of the infrastructure, particularly base operating support. For example, the requirement for funding for real property maintenance is often expressed as a percentage of the current plant value (i.e., real property maintenance “should be funded” at 2 percent of the current plant value). The problem with this approach is that it neither identifies the consequences of funding at higher or lower levels nor relates funding to the capabilities of the facilities being maintained to perform the functions required by the user. A second problem is stating a requirement in terms—usually in financial terms (e.g., backlog of maintenance and repair)—that do not describe the consequences or loss in capability if the requirement is not satisfied.

To determine the minimum resource requirements for the infrastructure and relate resource allocations to the ability of the infrastructure to support the needs and readiness of the operating forces, it is necessary to develop measures of performance that capture output. To be most effective, the user(s) must contribute to the process of developing the requirements for output; some such measures for regional bases are discussed in Chapter 2 (in the section titled “Regionalization”).

In developing output measures, several steps are required. The process should be iterative and continuous, allowing decision makers, from the program manager to the CNO, to evaluate what is required to support the user and what level of performance should be expected by the user. A recommended process, suggested in Appendix C, assumes that the Navy's regionalization plan is implemented.

Funding Vehicles, Paying for Internal Services, and the Navy Working Capital Fund

Within the Navy and the Marine Corps, many activities provide services to other parts of the organization. When providing these internal services, there is

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 55

always a concern as to how to allocate resources across the many demands, how to control costs, and how to guarantee that customers' needs are best satisfied. A good internal management process should provide cost visibility, performance measurement, cost containment, and customer control.

There are basically two ways to pay for services provided internally by an organization: customers pay for services as they are provided, or central management gives a budget to the service provider and directs that organization to deliver its services to the internal customers.

Portions of the Navy and the Marine Corps have been using some form of a customer reimbursable system since 1878. As discussed in the Center for Naval Analyses (CNA) report on the Defense Business Operations Fund (DBOF),3 DBOF was created in 1991 to consolidate all of DOD's reimbursable systems under one set of rules. In 1997, the Office of the Secretary of Defense (OSD) returned oversight of the reimbursable systems to the Services and relabeled them as the Working Capital Fund. Across all of DOD, approximately $75 billion in services are paid for by customers, and the Navy and Marine Corps account for about $20 billion of this business.

Direct payment to service providers is an alternative to customer reimbursements to service providers for services. Mission funding does not provide the same incentives to service providers to reduce costs and improve performance, but it does guarantee some specific amount of revenue to the service providers and thereby allows for a more stable, guaranteed workload.

The Department of the Navy has used both customer reimbursement and mission funding as a means to pay for various infrastructure services for more than 100 years, and is not likely to totally eliminate either process in favor of the other for many more years, if ever.

The committee is aware of (1) many of the advantages and disadvantages of the different means of payment for internal services, and (2) some of the current difficulties that customers have with Navy Working Capital Fund (NWCF) services and/or their costs. This study and this committee, however, were neither designed nor tasked to specifically address NWCF or mission funding issues. The committee's primary purpose in discussing the NWCF activities is to make sure that they are included in future Navy efforts to develop and improve measures of output along with mission funding activities. The NWCF activities are providers of a major function of all infrastructure services, and the exclusion of some or all of them from consideration in developing better output measures for the infrastructure would be a major failing.

Moreover, the committee observes that the NWCF activities are currently under the management cognizance of the financial managers and comptrollers,

3Trunkey, R. Derek, and Jino Choi. 1996. The Defense Business Operations Fund (DBOF) Problems and Possible Solutions, Research Memorandum 95–196, Center for Naval Analyses, Alexandria, Va., March.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 56

and that there is no equivalent of a chief operating officer for this more than $20 billion annual Department of the Navy business. Although the financial managers focus well on the cost inputs for providing NWCF services, these customer-funded services are as lacking in quality output measures as are the mission-funded activities.

Finding

The Navy does not have sufficient output measures to properly determine the value of and minimum essential needs for infrastructure goods and services, and to justify the allocation of resources to provide such infrastructure goods and services.

Major Recommendation

The Navy should establish a management information system to track support-system performance and costs. This system should be based on an integrated set of cost and performance metrics that are developed using fleet user inputs as well as those of service providers.

Recommendations

The CNO should put a process in place across the Navy, in each major claimancy and in each region, to develop and maintain output measures for each major function or activity that is provided by the infrastructure. A recommended process for accomplishing this is outlined in Appendix C.

The CNO should ensure that users have a prominent role in developing the requirements for the goods and services to be provided and the funding required to provide them. Users should focus on essential, cost-efficient support rather than better support and on acceptable risk rather than risk avoidance.

N4 should initiate a fresh look at current Navy metrics, such as the requirement for real property maintenance (RPM) and the backlog of maintenance and repair, by reviewing best business practices.

There should be two sets of metrics, one top-level and the other management-level. The top-level metrics should reflect the overall goals of the infrastructure and should measure system cost and effectiveness at the major claimant and Navy-wide level. The management-level metrics should be more clearly related to day-to-day resource decisions at the region or activity level. The metrics should be constructed so that management-level process metrics can be aligned with top-level strategic metrics.

The CNO should direct that N8 set up a system that tracks the top-level infrastructure metrics and helps to assess cost-effectiveness in meeting fleet needs. The elements of such a system would include (1) using a cost model such

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 57

as the COBRA model4 (used to establish a cost baseline for comparison of comparable mission and base functions across DOD for the base realignment and closure process in 1991, 1993, and 1995) to establish a cost and performance baseline for infrastructure activities; (2) ensuring that the full cost to the Navy of military manpower is included as a cost variable; (3) linking essential fleet requirements to infrastructure costs; and (4) taking full account of the feedback effects of changes in the support system as consequence of changes in the operating fleet.

The CNO should request that the Secretary of the Navy (SECNAV) task the Assistant Secretary of the Navy/Financial Management and Comptroller (ASN/FM) to appoint an NWCF chief operating officer, responsible for (1) providing greater visibility regarding the cost of individual NWCF activities, including related overhead costs, and (2) overseeing the development of output measures for NWCF activities, to include giving users of services (major claimants) the opportunity to participate in the development of such metrics.

Finding

The Navy does not have a mechanism or process for determining, on a continuing basis, current industry best practices and performance for comparable functions.

Recommendation

The Navy should invest in a resource person for each regional commander's and major claimant's staff who is familiar with, and has access to, industry and trade associations and consultants who can provide up-to-date information on current industry best practices for each of the infrastructure functions provided by the region. This information should be used in setting cost and performance goals. A network of such persons with expertise in best practices should be developed for sharing the practices and lessons learned in applying them within the Navy.

4R&K Engineering Planning Systems. 1997–1998. Cost of Base Realignment Actions (COBRA), Roanoke, Va. Available online at <http://www.rkeng.com/projects/cobra.html>; U.S. General Accounting Office. 1997. Military Bases: Lessons Learned from Prior Base Closure Rounds, GAO/NSIAD-97–151, Washington, D.C., July; U.S. General Accounting Office. 1995. Military Bases: Analysis of DOD's 1995 Process and Recommendations for Closure and Realignment, GAO/NSIAD-95–133, Washington, D.C., April; U.S. General Accounting Office. 1993. Military Bases: Analysis of DOD's Recommendations and Selection Process for Closures and Realignments, GAO/NSIAD-93–173, Washington, D.C., April.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 58

Information Technology for Infrastructure Management

At the start of the information age, the DOD led the way in developing both computers and networks. It dominated the marketplace, funding the research and setting the priorities. In 1955, the Navy was considered to have the best computer systems in the world. But a sea-state change has occurred, and today's information technology (IT) industry is leading the charge. DOD currently represents less than 5 percent of IT business. The objectives are to improve connectivity, speed of information flow and information sharing, streamlined operations, and new business models. Success derives from getting the right information to the right people in the right time frame. Connectivity, content, cost, control, sharing, and collaboration are the essential elements to success.

A Navy-wide Information Plan

The committee acknowledges the difficulty and enormous costs associated with creating an enterprise-wide information plan for an institution as complex as the Navy. However, the payoff is potentially huge because information technology can have an impact on the infrastructure and on shore readiness in two ways. The first is to increase capabilities and provide services in ways that were not possible before. The second is to reduce the costs of providing the fleet with current shore-based outputs by using new means to provide the services. In either case, information systems rarely result in increased capabilities or reduced costs simply by automating tasks being performed by personnel. Rather, information systems are a lever for increasing capabilities or reducing costs by enhancing access to and accountability for data and services.

The industrial age revolutionized the Navy by giving individuals control over thousands rather than tens of horsepower. This magnification of human labor revolutionized society as well. A modern revolution in information technology offers the Navy another opportunity to make startling improvements. It provides individuals with unparalleled control over goods, services, and activities that cross the barriers of time and distance. Exploiting this newfound power is key to a cost-effective shore establishment. Information technology in the 21st century is the lubricant that will allow the Navy business to flow with less friction and waste. It holds the potential for integrating ship and shore in ways that were never before possible.

Given at the end of this section are the committee's recommendations for evolving a Navy-wide information plan with the following attributes:

Navy-wide information space (infospace): defining, creating, and maintaining it;

Service access: the key to consolidation of

infospace-based Navy shore services; and

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 59

Decision support: leveraging the power of managers for cost-effective decision making.

Navy-wide Information Space and Its Components

The concept of a Navy-wide information space (infospace) is that of an adaptive system defined at any time by a set of performance standards for timely and effective information delivery throughout the Department of the Navy. The infospace includes basic components such as an information network infrastructure and information workstation capabilities that can be adapted to IT technology advances; associated training; and technology refresh cycles. However, it is emphasized that the infospace is a system characterized by a set of connectivity and service goals rather than a set of hardware and software goals. The particular technology solutions can vary, but the goals can and should remain relatively constant. Establishment of connectivity and service goals creates a benchmark against which progress can be measured without constraining the combination of solutions applied to the problem. Although this discussion is aimed primarily at the Navy, the infospace will eventually have to embrace all of DOD. Many of the prescriptions in the following sections can be applied DOD-wide.

The purpose of the infospace is to provide an infrastructure for delivery of information and services from any provider to anyone in need of a service. This approach must use Internet technology, rather than attempt to provide new point-to-point connections for each client-server combination. The concept of major information services requiring specific connectivity and specific workstations is no longer economically feasible. There must be a standard vehicle for delivery of and access to information and services. It should include not only a network with sufficient connectivity and bandwidth but also a standard information workstation that all service providers can depend on and develop around (i.e., a standard for developers and providers of software applications).

The desired infospace is, therefore, a trusted capability that all developers can depend on (e.g., as it is possible to depend on the existing telephone system). In an ideal system, the issues of how to get connected to users, where those users are, and what capabilities they have will disappear. Such a trusted service delivery system is critical to the Navy's consolidation and regionalization cost-cutting efforts. If all service providers know that they can reliably deliver their service to any user anywhere in the Navy, the design and development task is greatly simplified. In addition, issues of geography and distance can be subordinated to those of cost and effective service. If commanders and managers can depend on the infospace to access and obtain service in a reliable and timely manner, the management need for “controlling our own” is diminished. This lowers many of the cultural barriers to consolidation and regionalization. The key is that on both the provider and the user sides, the infospace must be trusted in terms of security, access, timeliness, and usability.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 60

There are four basic components to a Navy-wide infospace, each requiring standards:

1. Network infrastructure,

2. Standard information workstation,

3. Training, and

4. Refresh and replacement cycle.

Each of these components works with the others to create the dependable delivery of information services across the Navy. Note that these components are a set of standards around which a variety of capabilities can be developed. The important thing is to select the standards and begin building immediately. These will serve to focus the now varied and disjointed efforts. The goal is not to stop the many organizations within the Navy from developing the capabilities that they need to get their jobs done. The goal is to provide a unified vision so that the efforts of all can provide a cost-effective solution for all. The challenges faced in the development of an infospace vision cannot be used as an excuse to further slow the deployment of Internet and computing technology throughout the Navy.

Network Infrastructure. The key to the infospace is the establishment of Navy-wide secure and unsecure (broadly accessible) internets, the communications backbone that ties the structure together. Again, the infospace network, however, is a set of goals and standards for connectivity, security, and service, not a set of technology requirements. There must be a continual process of evaluation of the performance of the infospace relative to goals, and evaluation of the goals themselves. These goals provide the focus for technology acquisition. Programs that promise networked voice and video services while the Navy cannot yet guarantee universal Web access are counterproductive. The key goal areas are connectivity, timely service standards (bandwidth), electronic mail (e-mail), access to the World Wide Web, and security.

Connectivity. The key goal is that every standard information workstation in the Navy will be electronically connected to every other information workstation and to every information service. Note that technological connectivity is different from authorized connectivity. Whether an information workstation can access a given service should never be a question of stringing wires or of acquiring hardware. It should be only a negotiation of authorization. The question should never be, Is it possible to get timely access? but rather, Should access be authorized? The infospace technology should never be a barrier; it should always be a facilitator. Barriers, when needed, should be created intentionally. For example, barriers to data communication should exist only for purposes of good management and security.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 61

A Navy-wide connectivity scorecard should be created as a key management tool. The scorecard will continuously monitor the percentage of information workstations in the Navy that meet the connectivity goals. This information will provide a clear focus for the management and development of the infospace.

Timely Service Standards (Bandwidth). A prime reason for lack of trust in information technology services is poor response time. A service that is too slow will not be used. Users will find workarounds that will avoid the infospace service. These workarounds will drive up costs in ways that are undesirable and hard to manage. Infospace service providers should not be allowed to deliver untimely services. Ineffective, globally provided services will encourage local managers to build up their own individual capabilities and thus will defeat the desired cost savings many times over.

Minimal bandwidth standards for each information workstation should be defined. This means not only technical communications capacity to the end station but also total network throughput. A minimal standard might be that “a 10K Web page can be delivered from any server in the Navy to any information workstation in the Navy in an average of 10 seconds or less.”

Delivery of a service in 10 seconds is not actually acceptable for interactive work, but it does guarantee some access to everything in the Navy. Another helpful standard might be that “a 10K Web page can be delivered from any server to its primary users in an average of 2 seconds and a maximum of 10 seconds.”

A variety of standards can be set that define terms of actual services to be delivered, not technology to be purchased. The key is timely service, whether ATM, 10BaseT, switched Ethernet, or plain telephone lines are used.

There should be a regular system for monitoring whether or not each separate goal (standard for timely service) is being achieved. In the case of WWW pages, COTS proxy servers can provide all of the necessary statistics to easily monitor key performance. Periodic testing and audits of performance can be carried out. Because these goals are always stated in terms of performance perceived by end users, any users who feel that they are not being served can run their own test with a wrist watch. The scorecard for compliance is easily understood and easily verified. Compliance with timeliness goals cannot be overemphasized. Poor service is useless service, and users will find other more expensive ways to do their job.

Electronic Mail. Electronic mail (e-mail) is the premier collaborative tool in the Internet age. All information workers in the Navy should have an e-mail address that can follow them in a robust fashion as they move through their careers. It should be possible to rapidly update such addresses with minimal effort in response to job changes. It should also be easy to locate and separate the e-mail address of an individual job function (e.g., N4) from that of its current

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 62

occupant (e.g., the N4). Such knowledge, of course, is subject to authorization. Such “white pages” services can be delivered via the WWW and thus exploit the same authorization structure.

A key to rapidly organizing teams to work on problems when they are not co-located is the construction of a team mailing list. Every officer with administrative responsibility should know (either personally or through trained staff) how to create such a mailing list in less than a day. This capability provides for rapid organization of personnel without the restrictions of time and distance.

Access to the World Wide Web. The World Wide Web (WWW) is the primary vehicle for universal access to infospace services. Web servers are easy to set up and easy to maintain. Training for creating and managing Web sites should be widespread among Navy personnel. Information made available on the WWW should replace most hard-copy manuals and general information materials. In specifying the information workstation, a well-defined set of plug-insor help applications should be included. Among this set would be office productivity tools and a standard page-publishing tool such as Adobe's portable document format (PDF)/Acrobat. These standard applications help provide for almost instantaneous delivery of manuals, procedures, and training materials. If every information workstation has infospace connectivity and standard WWW browsers and help tools, then electronic publication of materials can become a reality. Instead of archiving, shipping, storing, and updating tons of paper publications, they all can be distributed and accessed on an as-needed basis. This can result in a huge savings and provide more timely and accurate information.

It is important to recognize that the Hypertext Mark-up Language/Hypertext Transfer Protocol (HTML/HTTP) standards together form the backbone of the WWW. With these, a vast amount of information and service can be shared from Navy databases. HTML alone can provide many of the access and information needs required to support consolidated or regionalized shore services. In addition, standard Java plug-ins can allow consolidated providers to download specialized interfaces to their services.

Security. The military's need for secure communications is obvious and pervasive throughout the infospace. Systems must be in place to monitor compliance with security standards to create a trusted environment.

One aspect of the security architecture that receives less attention than communications and computer security is authorization for services. A uniform authorization architecture is needed. When individuals create a new service to be delivered across the infospace, it must be relatively straightforward for them to define which job functions are authorized to have access to and make requests for that service. They must be able to easily accept requests for service and validate those requests against the authorizations defined for the service. It is not acceptable for every new service to develop its own mechanism for deter-

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 63

mining who is trying to access the service and whether or not they have permission. This is part of the infrastructure that must be generalized to permit free but appropriate access across the infospace. Needed are standard mechanisms for granting permission as well as standards for validating digital signatures. Not all of these needs are currently satisfied by COTS products.

Standard Information Workstation. Every information worker in the Navy should have access to a standard information workstation, which is key to a successful Navy-wide infospace—a network connection between service provider and user is not by itself sufficient. If the service provider cannot depend on baseline capabilities at the user end, delivery of the service will not be successful or will be much more complicated than necessary. Information workstations may or may not be the same as warfighting computers. The key is that there be a standard set of capabilities that service providers can test their software against and then depend on. Users need to know that if they have a standard information workstation, they will have access to any of the services offered over the Navy-wide infospace system. Standardizing the information workstation capabilities also simplifies the training process for users.

The information workstation should not be a vendor standard; it should be a standard set of testable capabilities. Where there is a vendor-specific standard, the opportunity for competition is reduced and the value of the standard information workstation declines in the long run. In terms of hardware, vendor-independent standards are quite straightforward. Vendor-independent software standards are much more difficult. In many cases, vendor-specific software standards are unavoidable. Where possible, two alternatives should be allowed. This complicates the standard somewhat but preserves the critical competitive environment. However, any alternative must be a viable competitor in the open marketplace rather than one supported by its privileged position as a Navy standard.

The standard information workstation should include:

• A standard operating system and “windowing” interface system;

• Standard office tools such as word processing, spreadsheet, and presentation software;

• WWW browser plus standard help applications; and

• A downloadable software translator standard such as Java.

A standard operating system and “windowing” interface system can simplify training and ensure users' confidence in their ability to access the infospace services. With standardized office tools, the training is again simplified. In addition, the ability of personnel to collaborate across the Navy-wide system is greatly enhanced. If everyone has access to the same word processor or spreadsheet, then sharing documents or budgets via e-mail can become a reliable and trusted form of communication. If these tools are not interoperable, then trying to share information becomes a frustrating experience.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 64

The WWW browser standard is the tool for universal access to consolidated infospace services and defines a unified window on the world. A downloadable software standard allows providers to specialize the access to their services. It is very important that this standard be carefully constrained and monitored. A selected standard must have provable security properties to prevent viruses and other threats, and it must be reliable. Minor variations in the downloadable software standard can cause frustrating user interface failures.

Training. The purpose of creating the infospace is to facilitate access to information and services. Technology alone will not accomplish this. It is essential that training programs be put in place to ensure that everyone knows how to access infospace services. Generational issues will arise. Some personnel over age 50 will never use a computer as part of their everyday activity. Trained staff must support such people. Most admirals do not type their own letters, and some do not lay hands on a computer, provided that all support staff are appropriately trained. For all newly trained personnel, both enlisted and officers, basic access and navigation skills should be required training. It is of little value for a regionalized service to provide infospace access when few of its customers have the training necessary to exploit such access. Again, a dependable and predictable trained base of users is essential to the delivery of infospace-based services.

Refresh and Replacement Cycle. The cardinal rule of computing technology is that it will change. Any model for computing that is based on “buy once, use forever” is foolish—the Navy infospace must be an adaptive system. End user computing technology should be amortized over 4 years, with slightly longer periods for network services. There must be a plan for continual upgrade and replacement. The power and capabilities of computers are doubling every 18 months. This means that a 4-year-old machine is five times slower than a new machine at the same price. A problem with Navy-wide infrastructure standards is that they cannot change willy-nilly. Everyone must depend on the standard. The nature of computing, however, demands responsiveness to continual change.

If a 4-year rolling plan is adopted for upgrades, the standards can also be placed on such a plan. For a given year, one can stipulate that 4 years from now, every information workstation in the Navy will have capability X. Setting a new standard defines the upgrade. When service providers want to utilize the new capability, they can request that particular users upgrade sooner or plan a deployment that is in line with the upgrade plans.

The technology refresh plan should also provide for the discarding or upgrading of non-compliant and unused applications. When yearly standards are set, service developers are put on notice that within 1 year, 25 percent of the information workstations or Internet capability will no longer support their service and that within 4 years none of the information workstations will. Such a

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 65

planning cycle gives clear direction to the upgrade process that everyone can work within.

The technology refresh plan also provides for upgrades to training. As the technology requirements within the infospace are changed, the corresponding training can be changed. With the new capabilities will come a new generation of personnel prepared to exploit those capabilities.

Service Access

The key to consolidation of infospace-based Navy shore services is to provide access to those services that is as good as or better than before. A Navy-wide infospace can facilitate such savings. A centralized automobile fleet that provides reservations over the Internet is more accessible than several with a few vehicles scattered at multiple sites. The goal is to provide access to services via the infospace rather than physically locating the services near the customers. This effectively moves the service from “down the street” to “on the desk.” Such electronically available shore services will be more tightly integrated and accessible to shipboard personnel than any number of physical “storefronts.”

Each time a service is consolidated to a centralized location from a number of independent entities, a new infospace application should be created to provide access to the consolidated service. This provides service users with more effective and timely access than before, while at the same time reducing the costs of supporting the service. In order to meet such a goal, new strategies for developing information technology applications must be adopted. The old-fashioned COBOL-oriented multiyear development methods are completely unworkable in this domain. The very large“do everything but the dishes” software contracts will not serve this need. Software must be created and changed rapidly to provide exactly the service information required. Changes brought on by vast amounts of cheap computing power, universal networking, and standardized workstations can make such developments possible. The development time for new applications for small organizations must be cut from years to months (3 to 5). Otherwise, the costs of supporting large software installations will remove any cost savings that may result from the consolidation. Old-style software methods frequently transferred costs from service providers to IT providers without any real cost savings. This cannot be repeated.

Service Expectations. A key to effective network-based rather than location based services is a set of uniform expectations about such services. One of the major costs in IT deployment is the training of users. The Navy cannot afford to create a major training program for every new service application. To eliminate the training burden, all services within the infospace should support the following features in a standard way.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 66

• Provide uniform mechanisms for finding desired services.

• Supply sufficient information for intelligent selection of services by users where more than one alternative is available.

• Implement uniform mechanisms for requesting services and in particular for requesting authorization to receive service.

• Provide clear, uniform tools whereby users can estimate the costs of a requested service. This will promote effective shopping for services. Users cannot be expected to make cost-effective use of resources if the cost implications of requesting a service are not clear.

• Provide users with accurate information about the status of their request.

• Provide users with accurate metrics of overall performance (i.e., average time to delivery, average number of faults, and so on). Simply making such performance information known to users will improve cost-effective delivery of service.

When human-based services are replaced with networked information-based access to services, trust must be established. Current Navy personnel have clear expectations of the control that geographic proximity and command structure can provide. Effective officers and other managers have learned how to get results from such services. When access to such services is through an infospace, new expectations must be established. Providing a uniform set of such expectations, which apply to all services obtained over a Navy-wide infospace, will sharply lower the barriers to replacing personal access with electronic access.

Metrics for Infospace Service Success. Information technology has a mixed record in the area of cost reduction. With each such project, metrics for success should be clearly established up front. A key metric in this area is staffing impact. Every information technology application should be able to clearly state,“If this IT application is put into place, then the total Navy staffing will be reduced by X number of people within Y years.”

Having established such a claim, the IT project should be held to it. In particular, the hidden staffing requirements must be made known, including IT support people and user area staff required to use the application. Replacing user staff with IT support staff will generally increase costs rather than reduce them. It must be clearly shown that the IT staff is significantly smaller than the staff that the application is replacing. It must also be shown that the IT project is not pushing work out of the centralized area into the user areas. This is frequently done when centralized impact is easy to see while user area work is considered to “blend into the overhead.” Using IT to move work does not save money. IT saves money only when it eliminates work entirely.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 67

Decision Support

The payoff from these information technology investments will be major improvements in the ways functions are performed and decisions are made within the activities composing the infrastructure. When IT is used to leverage the power of decision makers to make cost-effective choices, then costs can be reduced. For example, alternative ways to deploy helicopter assets in response to humanitarian requests could be examined, with both costs and time-line parameters displayed; or information service that quickly displays all of the choices with their costs could enable in-transit personnel to select cheaper quarters.

Information technology can rapidly generate and present alternatives in a way that is not possible otherwise. Information systems can also clarify the consequences of decisions. A simple example is the ship berthing and movement tool created by California Polytechnic State University and used in the San Diego region. This tool allows harbor personnel to rapidly work through various ship movement plans to determine which might meet the goals with less cost in time and money. It is cheaper to move ships on a screen than under real power. The Navy needs more of these kinds of decision support tools that clarify cost consequences of decisions.

The strategy for new applications of software and databases will require professional attention. Historically, the information systems organization in major companies was responsible for applications running on mainframe computers, with users operating dumb terminals. The widespread availability of personal computers did little to enhance the utility of the functional stovepipes of information that have evolved within the departments, such as sales, finance, and customer service, and provided little improvement in productivity overall.

In the 1990s, client-server-based systems evolved as the model for distributed computing. However, interdepartmental data analysis and management required enterprise resource planning (ERP) tools involving specialized analysts to tailor the interfaces for each client's request. Today, as the World Wide Web, browsers, and other tools mature, the architecture for enterprise-wide data access and analysis can evolve smoothly from a hardware, software, and configuration management perspective. Thus, the committee believes that both the client server and Web-based architectures have their own advantages; the Navy will require professional assistance in managing its implementation program.

Major Recommendation

The Navy should define and implement the concept of a Department of the Navy-wide information space (infospace) using a set of standards—some of which are now being partially implemented by the Information Technology for the 21st Century (IT-21) initiative—to serve both shore and afloat activities. The infospace should be defined by performance standards for timely and effec-

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 68

tive delivery of information and services throughout the Department of the Navy, including the fleet and its support. It should include a network infrastructure and a standard information workstation for every responsible information worker in the Navy, not just those in the operating forces. The infospace should be used as the primary vehicle for delivery and integration of information about the entire Navy infrastructure to include the following functions: acquisition, central logistics, central personnel, communications, force management, installations, medical functions, quality of life, science and technology, and training. Funding for this effort, including funding for essential technology upgrades and related training, should be identified and protected within the Department of the Navy.

Recommendations

The Chief Information Officer (CIO) should:

Establish performance, service, and communications standards for the infospace that are not adequately addressed in the current draft guidance (Information Technology Standards Guidance).5 These standards must be performance based and not be a set of technology requirements.

Advise the N6 on which Navy-wide site licenses should be negotiated for use on standard information workstations. Such licenses will encourage interoperability, intercommunication, and standardization.

Ensure that there is a Navy information management system both to monitor IT performance and cost and to track metrics for successful delivery of services within the infospace.

Act as a facilitator and arbitrator for cross-stovepipe IT applications.

The CNO should require basic infospace access and navigation training for all new enlisted and officer personnel, and he should address the IT specialist personnel training and retention problems caused by commercial market forces. Possible alternatives are using educational subsidies with extended tours to train and retain IT specialist personnel, and outsourcing IT specialty needs.

All Navy managers should:

Ensure that IT applications derive from business change initiatives;

Use the Navy-wide infospace to create paperless business transactions;

Use decision support tools and performance metrics to elucidate cost and performance consequences of business decisions; and

Encourage use of the Navy-wide infospace for disseminating good IT practices.

5ITSG Integrated Product Team. 1998. Information Technology Standards Guidance, Version 98-1.1, Chief Information Officer, Department of the Navy, Washington, D.C., June 15. Available online at <http://WWW.doncio.navy.mil/itsgpublic>.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 69

Competition6

Recent experience has indicated that substantial savings can result from competition.7,8 From 1978 to 1994, the DOD held more than 2,000 public-private competitions with an average planned savings of 30 percent. These planned savings were seen in all the military branches and for virtually all types of commercial activities. Based on these experiences, in 1995 the Navy planned to outsource about 25,000 positions, including 3,400 military billets, and reflected these savings in its out-year plans. Although the number of competitions held through February 1998 was for only 2,100 positions, the Navy increased the goal of completing A-76 competitions, involving 80,500 positions, including 10,000 military billets, by the year 2002.9,10 In light of past experiences, many have questioned the Navy's ability to realize savings of these magnitudes in the future. Here, evidence is reviewed and ways are proposed to improve the success of the program.

Many excuses are given for failing to realize the projected savings, but they can be grouped into three categories: (1) the number of positions available falls far short of the required target because the function performed is deemed inappropriate for competitive sourcing, (2) the number of positions actually competed is below expectation because local constraints usually govern the process, and (3) the realized savings percentage is lower than forecasted because previous actions already had captured the largest source of efficiencies or the budget already reflected the cost of the most efficient organization (MEO).

A review of data and trends indicates that more savings are not being realized through competitive sourcing because most jobs ashore have not been competed. Specifically, according to the Navy's records, there are 300,000 commercial activity positions (60 percent of which are civilian) and, at most, only 10 percent have been previously competed. In addition, many military personnel remain in commercial activities, but personnel policies limit the number of bil-

6Privatization is often cited as a preferred method of improving performance or reducing cost. However, the committee believes that competition tied to a particular service and marketplace is the key enabler that stimulates innovation and improvement in both government and private activities.

7Marcus, Alan J. 1993. Analysis of the Navy's Commercial Activities Program, CRM-92-226, Center for Naval Analyses, Alexandria, Va., July.

8Tighe, Carla E., Samuel D. Kleinman, James M. Jondrow, and R. Derek Trunkey. 1996. Outsourcing and Competition: Lessons Learned from DOD Commercial Activities Programs, CNA Occasional Paper 23, Center for Naval Analyses, Alexandria, Va., October.

9U.S. General Accounting Office. 1998. Defense Outsourcing: Impact on Naval Sea-Shore Rotations, GAO/NSIAD-98-107, Washington, D.C., April.

10Trunkey, R. Derek, Benjamin P. Scafidi, Francis P. Clarke, Cheryl Kandaras, Andrew M. Seamans, LCDR Carolyn M. Kresek, USN, Robert P. Trost, Angela L. King, Christine H. Baxter, Kerensa E. Riordan, Steven Smith, and Michael Ye. 1998. Moving Forward with A-76 in the Navy, CRM98-9.10, Center for Naval Analyses, Alexandria, Va., April.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 70

lets available for competition. A recent study showed that, in the Navy, only 16,800 of 138,000 military shore billets are available for competitions after accounting for policies such as sea-shore rotation and homebasing.11 While this should be sufficient to complete the current rounds of competitions, such large exemptions limit the Navy's flexibility in targeting activities and consolidating them for larger competitions. Moreover, in past years, 34 percent of Navy competitions, many of them very large, were canceled. By comparison, only 3 percent at the General Services Administration were canceled because senior leadership supported the program and demanded that it be executed. As mentioned above, the Navy plans to announce competitive sourcing for 80,500 positions over a 5-year period and is building its candidate list from claimant inputs. In 1997, the Navy announced the proposed competition of 10,000 positions. The goal for 1998 was to announce 15,000 positions, but the Navy was unable to achieve that. The Navy has so far completed competitions for only 250 positions out of its goal of 80,500. Clearly the cause for these shortfalls is a major concern because government personnel represent a large fraction of infrastructure costs.

Sea-Shore Rotation Policy Constraints

Because the policy of reserving shore billets for military personnel after tours at sea places a major constraint on the number of jobs eligible for competition, the committee examined the issue in some depth. The Navy needs to attract and retain quality sailors. A component of the overall personnel management process is the rotation of the career enlisted force between sea and shore billets. The purpose is to reduce the time deployed and the associated stress of operational jobs and separation from family. Another reason is to enhance skills for later deployments. The Navy fears that more sea time will hurt both recruitment and retention.

The rotation policy is executed by reserving many shore jobs for military personnel. In recent years, the sea-shore rotation objectives have been coming more and more into conflict with Navy objectives to reduce the number of personnel providing support ashore. A recent homebasing policy to rotate personnel into shore billets near their previous sea assignment introduces additional constraints. If cutting military personnel ashore is required to improve efficiency and if that will hurt personnel readiness, the Navy has to consider alternative ways to soften the impact and make a Navy career attractive. This section

11Trunkey, R. Derek, Benjamin P. Scafidi, Francis P. Clark, Cheryl Kandaras, Andrew M. Seamans, LCDR Carolyn M. Kresek, USN, Robert P. Trost, Angela L. King, Christine H. Baxter, Kerensa E. Riordan, Steven Smith, and Michael Ye. 1998. Moving Forward with A-76 in the Navy, Research Memorandum 98-9.10, Center for Naval Analyses, Alexandria, Va., May.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 71

reviews some of the issues and considers ways to satisfy both personnel and efficiency objectives.

Measuring Rotation

The Navy classifies all its billets with a sea-shore code. Sea duty billets are those in deployable units or at some of the overseas ashore installations. Student billets are classified separately and are not included in the computed sea-shore numbers. The metric used by the Navy to monitor sea-shore rotation is the sea-shore ratio. This indicator is the simple ratio of time in sea duty to time in shore duty. It is computed only for E5 to E9 billets, because these are considered the career pay grades. Overall, the Navy calculates its sea-shore ratio at about 3.8:3. That is, a career sailor is expected to spend 3.8 years at sea for every 3 years ashore. There is considerable variance across ratings. An important attribute of the sea-shore ratio is that the DOD and the Congress generally accept it as a tool to manage the Navy career force.

There are several concerns with using the sea-shore ratio as a management tool:

• The ratio is for billets and not personnel. Although manning practices vary, one should protect only military shore billets that correspond to sea billets that are actually filled by people in pay grades E5 to E9.

• The metric covers all E5 billets. Although some of those billets are filled by E5s in their first term, rotation is designed for careerists. By including only positions traditionally filled by E5 careerists, the process could have a significant effect on the ratings with 6-year initial obligations.

• Student billets ashore are excluded from the shore part of the ratio, although one of the reasons to return personnel to shore is to develop skills that will increase productivity at sea.

The committee examined sea-shore ratios for personnel instead of billets, using the Navy's classification of sea and shore billets. Figure 3.1 displays these ratios over time, with the following observations. The jump in 1989 reflects a change in the definition. The top curve represents the ratio for personnel using the Navy's practice of including all E5s and above. That curve shows that the ratio for personnel has averaged 3.3:3 over the past few years. That is, when personnel rather than billets are looked at, there appears to be more than a 10 percent drop in the ratio (from 3.8:3 to 3.3:3). The lower curve includes only career personnel. Comparing the curves suggests two distortions caused by including first-term E5s. It makes the sea part of the career appear larger and the long-term decline look more dramatic than it was. Overall, actual Navy sea-shore ratios for careerists are less than 3:3. Individual ratings may still have

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 72

image

Figure 3.1
Sea-shore ratios for personnel, 1982–1997.

considerably higher ratios. The actual sea-shore ratio has been relatively flat since 1991 and generally declined during the drawdown.

Effects of Sea Duty

The principal reason for managing sea-shore rotation is to keep extended sea duty from reducing retention. In surveys, personnel frequently report family separation as a key reason for leaving the Navy. However, analysis of actual retention rates shows only modest impact of sea duty and time underway on retention. An extensive study in the 1970s showed that a 10 percent increase in expected sea duty (e.g., from 50 to 55 percent) would decrease retention by 3 percent (from 25 to 24.1 percent).12 A later study of retention in the 1980s found similar effects for measures of personnel tempo (perstempo).13 This study

12Warner, John, and Matthew Goldberg. 1984. “The Influence of Nonpecuniary Factors on Labor Supply: The Case of Navy Enlisted Personnel,” Review of Economics and Statistics, February, pp. 26–35.

13Cooke, Timothy, Alan Marcus, and Aline Quester. 1992. Personnel Tempo of Operations and Navy Enlisted Retention, Research Memorandum 91–150, Center for Naval Analyses, Alexandria, Va., February.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 73

looked at actual deployment lengths, time between deployments, and time underway when not deployed. Perstempo had the most deleterious effect on the retention of married personnel. But even here, the greatest impact was from very long deployments, those of more than 8 months. The retention declined from 40 percent to 30.5 percent. Other effects were more modest and in line with the earlier study.

The above studies also found that reenlistment bonuses can compensate for additional sea duty. In most cases, reenlistment bonuses that are equivalent to less than 10 percent of regular military compensation (base pay and tax-adjusted allowances) would offset as much as a 25 percent increase in perstempo.14,15 Married personnel would require higher bonuses. Some would still leave, but others originally leaving for different reasons would later reenlist and offset the loss.

Hidden Costs of Rotation

Fairly recent research16-19 has uncovered a hidden cost of reserving shore billets for military personnel. Activities with the highest percentage of military personnel produce the greatest savings when competed, i.e., opened to competitive bidding. Controlling for the size of the competition and the type of activity competed, public-private competitions of military positions produce 50 percent more savings than competitions of civilian positions. This strongly suggests that the Navy pays dearly by retaining a military person unnecessarily in a shore position that could be competed. Although these results may have been unexpected, they are consistent with other general observations:

• Young individuals tend to be less productive than older individuals, at

14Cooke, Timothy, Alan Marcus, and Aline Quester. 1992. Personnel Tempo of Operations and Navy Enlisted Retention, Research Memorandum 91–150, Center for Naval Analyses, Alexandria, Va., February.

15Sharma, Ravi, and Henry Griffis. 1995. Implications of Changes in Time Spent at Sea,Research Memorandum 94–150, Center for Naval Analyses, Alexandria, Va., April.

16Marcus, Alan J. 1993. Analysis of the Navy's Commercial Activities Programs,Memorandum 92–226.10, Center for Naval Analyses, Alexandria, Va., July.

17King, Angela L., Angela M. Rademacher, and R. Derek Trunkey. 1996. An Examination of the DoD Commercial Activities Inventory Data, Information Memorandum 471, Center for Naval Analyses, Alexandria, Va., December.

18Trunkey, R. Derek, Robert P. Trost, and Christopher M. Snyder. 1996. Analysis of DoD's Commercial Activities Programs, Research Memorandum 96-63, Center for Naval Analyses, Alexandria, Va., December.

19Snyder, Christopher M., Robert P. Trost, and R. Derek Trunkey. 1998. Bidding Behavior in DoD's Commercial Activities Competitions, Research Memorandum 97-68, Center for Naval Analyses, Alexandria, Va., January.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 74

least between the late teens and mid-fifties. Contractors often use older workers to do work previously done by younger military personnel.

• Turnover reduces the productivity of workers. Rotation by definition moves people continuously through the activity. With a 3-year rotation, the average worker has only 18 months at the activity. Contractors keep workers longer and lessons learned are more likely to persist over time.

• Organizations that are predominantly military have limited ability to use part-timers and temporary workers. Contractors can, at apparently less cost, use overtime during surge workloads and reduce the number of full-time employees.

• Military personnel are not accounted for in local budgets, because these costs are handled centrally. Although local activities do not purposely overuse or misuse personnel, costs are hidden in a budget sense, and no one can free up funds for other uses by cutting military personnel. As a result, the system is biased toward having excess people.

• The demand for work performed by military personnel is often unconstrained by cost. For example, civilian depot costs are often covered by reimbursements from the fleet, whereas the military intermediate maintenance facility costs are not. When there are choices, the fleet tends to use the latter facilities. Although depots attempt to bring down their costs, the intermediate maintenance facilities have no such pressures.

Reconciling Efficiency and Personnel Objectives

Some shore jobs must remain military. Some of these jobs require personnel with recent operational experience or provide additional skills for later tours. But for many jobs, this is not the case, and in most cases there is a hidden cost.

The Navy faces a dilemma in deciding which shore billets can most easily be competed or staffed by civilians. If it eliminates general billets that are unrelated to sailors' jobs at sea, it has reduced its flexibility in assigning personnel ashore. Training and maintenance billets, for example, require personnel with the appropriate rating and Navy enlisted classification (NEC). Yet the rotation needs of individual ratings may shift over time and the shore billets may not match. The clear point here is that the Navy must consider the efficiency gains, the impact on skills, and the flexibility in making assignments when it considers which functions and billets to target for competitive sourcing and other infrastructure efficiencies.

As a general observation, the committee believes that the process for selecting military billets for competition and other efficiencies is weighted too heavily to standard sea-shore goals. For example, the Deputy Chief of Naval Operations, Manpower and Personnel (N1) currently has veto authority over the inclusion of military shore billets. It is the committee's view that the decision needs to be based on the inputs of all stakeholders. Disagreements could be resolved by the Vice Chief of Naval Operations (VCNO) as the final arbitrator.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 75

There are many ways to reconcile efficiency and personnel concerns. For one, the Navy should try to identify alternative ways to improve sailors' quality of life. For example, many sailors find workloads while in home port to be particularly onerous. Since about half of the time in a sea billet is spent at the home port, those working conditions should be reviewed. Tiger teams on the base could move from ship to ship to reduce long workdays when the ship is in port. Also, time underway when not deployed can be better utilized, so that there are fewer days away from home.

The Navy could consider increasing compensation. As noted above, many sailors would accept an additional year or two, or even another sea tour, for additional pay. The most effective tool is almost certainly sea pay, which could be targeted to those at the end of their sea tours. Not all need to accept this offer for the Navy to cut into the number of required shore billets.

Another option to consider is including the employment of military personnel as part of private contracts. That is, the contractor would agree to use some of the personnel in the performance of the service to the Navy. There are several benefits and limitations to this approach. First, if the Navy outsources to a highquality provider, it will benefit from the training its personnel receive in leading business practices. Second, military personnel will eventually benefit when they leave the Navy because they can cite private-sector experience. To the extent that there are savings, they result from the Navy having fewer people in support activities. If a contractor is using military personnel, the Navy will still pay for them directly or, if the contractor pays part of the military personnel cost, the Navy will pay indirectly through the contract price. Also, this option does not address the drawdown in ashore requirements resulting from other efficiencies, such as regionalization, Smart Base, and direct vendor deliveries.

Another way to keep some of the military shore billets is for the Navy to include military personnel in their MEO and participate in the competitions. When military positions are now competed, they are automatically converted to civilian positions for the in-house bid. To keep some military positions in the in-house bid would require more flexibility in switching funds between Navy military personnel (MPN) and O&M. However, the evidence is that contractors will win most of these competitions, and only a few billets will be saved. Also, this approach along does not help with other labor-saving initiatives.

Another solution would integrate military personnel with government civilian personnel. The Navy has started to do this in maintenance, where the civilian depot work force and the military intermediate maintenance work force are being combined. The merger allows for downsizing through the reduction in excess capacity and scale economies. It also may improve the productivity of both the civilian workers, who bring to the job greater maintenance expertise, and the military workers, who bring to the job the understanding of operational usage and diagnostics. More importantly, this may allow the Navy to cut civilian workers in lieu of its military workers. This approach works because of the

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 76

excess capacity at the depots. However, just as there is a hidden cost in using military personnel instead of private civilians in many areas, it is also likely that there is a hidden cost in using military personnel instead of government civilians in many jobs.

In the long run, the Navy needs to cut personnel at sea. Programs such as Smart Ship can cut into those requirements. Cutting those billets not only reduces shore billets reserved for sailors, but it also cuts into the total number of support personnel needed.

Infrastructure efficiencies can reduce the need for facilities and the associated construction costs. They can also cut inventories. But the biggest costs are in personnel, and it is those costs that must be cut if the Navy is to shift resources from support into modernization.

A-76 Competition Practices

In its visit to the San Diego naval bases, the committee was briefed on successful public-private competitions (e.g., family service centers) and a private-private competition for third-party deliveries of office supplies throughout the area. Drawing on these experiences, and those of others,20 the committee offers its suggestions on ways to improve the numbers and quality of local A-76 competitions.

First, the Navy should remove the local obstacles to effective competition. Today, managers of local activities have little or no reason to downsize or compete unless directed. Currently, installation managers must (1) pay for conducting the analyses leading to the competition, (2) incur the inconvenience or hardship of losing employees and dislocation, and (3) return the savings realized to the U.S. Treasury—all while being measured on the level of service provided.

Second, the Navy should focus on larger competitions, anticipating the results of regionalization, by carrying out process redefinition and holding competitions concurrently. For example, if a larger number of qualified bidders could be solicited, functions might be combined, since experience shows that the percentage of savings per billet increases with the size of the function competed.

Third, those in the chain of command must unequivocally support the competitive process. Because the supporting analyses of solicitations take several years in most cases, formalized organizations charged with planning and implementing major competitions will be required to provide continuity as the leadership rotates.

20Trunkey, R. Derek, Benjamin P. Scafidi, Francis P. Clarke, Cheryl Kandaras, Andrew M. Seamans, LCDR Carolyn M. Kresek, USN, Robert P. Trost, Angela L. King, Christine H. Baxter, Kerensa E. Riordan, Steven Smith, and Michael Ye. 1998. Moving Forward with A-76 in the Navy, CRM98-9.10, Center for Naval Analyses, Alexandria, Va., April.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 77

Findings

In the areas of competition and sea-shore rotation, the committee's key findings are the following:

• The Navy's decentralized tactical process to identify A-76 competition candidates and to execute the program is not producing the large competitions necessary to reach the Navy's goal. Larger, more strategically executed competitions are needed to attain the Navy's competitive sourcing goal.

• Larger competitions have traditionally produced greater initial savings. In the past, competitions for fewer than 10 positions produced estimated initial savings of 22 percent; competitions for activities with more than 200 positions produced savings of 45 percent.

Supporting findings: There are still significant opportunities to reduce costs with competitive sourcing.

—According to the Navy's records, there are 300,000 commercial activity positions (of which 60 percent are civilian) and, at most, only 10 percent have been previously competed. Even if all traditionally noncompeted work (such as depot maintenance and R&D) were excluded, the Navy would still have 55,000 civilian positions and 17,000 military positions available for competition.

—Using the estimated savings from the 1980s competitions and adjusting them for changes in the mix and size of activities and the civilian-military makeup of the work force would suggest slightly lower initial savings: from 31 percent to 27 percent. However, to the extent that there are trends, estimated savings have increased over time. If competitions are arranged by the year in which they were decided, the estimated percentage saved is higher in the later years. Also, the drawdown in forces and manpower seems to have had no effect on the percentage saved. The DOD work force peaked in 1987. The estimated percentage saved continued to increase into the early 1990s, when the earlier program ended. The most recent competitions are producing estimated savings greater than the historical 30 percent average. In the Navy, each of the three Navy competitions completed in 1997 and 1998 had estimated savings of more than 35 percent. The Air Force reports that it is now initially saving an average of 34 percent. Other DOD efficiency initiatives are either increasing or not affecting the savings from competitions. For example, the Navy regionalized and competed three family service centers concurrently in the San Diego region, an approach that produced greater savings than would have resulted from three separate competitions. Also, the Navy has used efficiency reviews in an attempt to reduce costs. Although the internal efficiency review at the telecommunications facility in Stockton, California, produced no savings, a later competition produced an estimated initial savings of 37 percent.

—Many military personnel remain in commercial activities, and personnel policies are a major limit on the number of billets available for competition,

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 78

with only 16,800 of 138,000 military shore billets available for competitions under the implementation of current policies on sea-shore rotation and homebasing. The Navy has limited its own flexibility to target activities and consolidate them into larger competitions.

Conclusions

Past uses of competition, for the most part, are based on the practices of the 1980s, which were far from optimal. Recently, there has been a revolution in strategic sourcing in the commercial world. Moreover, although some shore jobs must remain as military positions, the Navy needs to better reconcile its infrastructure efficiency and seagoing personnel management objectives. This should increase opportunities for competition. It is the committee's conclusion that the Navy could increase savings further through actions such as the following:

Taking a more strategic approach to competitions. The Navy can bundle positions for competition, select sources as long-term partners, and induce continuous improvement to match the practices of innovative commercial firms.

Regionally competing support functions. The Navy now can take advantage of scale and scope economies. Half of the competitions between 1978 and 1994 were for 14 or fewer positions. Competitions of that size are relatively costly to administer, do not attract the most successful firms in the private sector, do not provide opportunities for economies of scale or scope, and produce the least savings. In the past, 37 percent of competitions for 10 or fewer positions produced no savings, whereas only 4 percent of competitions for 100 or more positions produced no savings.

Requiring OPNAV approval to cancel competitions. Many competitions are being canceled by command-level authority.

Continuing to critically review inherently governmental positions. Many of these jobs could be commercial, and the use of this exemption category varies considerably across locations and parts of DOD.

Removing disincentives to competitive sourcing. Until recently, local commands paid for the competitions but did not keep any of the savings. Headquarters should pay the cost of the competition and allow local commands to keep some of the savings to improve facilities and quality-of-life services.

Adjusting military personnel policies to allow for competitive sourcing of more continental United States (CONUS) shore positions. For example, the Navy includes sea billets normally filled by first-termers to justify shore billets for its careerists. In some cases, additional pay may be required to attract personnel to longer operational tours or shorter CONUS tours. Given that planned savings from competing functions performed by military personnel far exceed those from competing functions performed by civilians, targeting additional pay

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 79

to those affected could be a cost-effective approach to increasing the number of military positions available for competition.

Creating competition support offices as corporate repositories of lessons learned and providers of expertise. Regional and local commands will be less frustrated if they know how others have solved problems similar to their own.

Committing strong leadership to overcome resistance throughout the Navy and DOD. Large-scale use of competition requires a commitment from those at the top.

Making provisions for sea-shore rotation slots in any competitive sourcing. That is, Navy personnel could work in contractor-managed billets for their shore rotations. To increase retention, contractors could be prohibited from hiring military personnel until they had completed another sea rotation.

Major Recommendation

The Navy should use competitive sourcing as a preferred approach to selecting the best providers of all support. In this regard, the Navy should establish a cross-functional team under the Assistant Secretary of the Navy/Installation and Environment (ASN/I&E) and the Assistant Secretary of the Navy/Research, Development, and Acquisition (ASN/RDA) to be responsible for overseeing the execution of competitive sourcing in business operation areas approved by Navy leadership.

In addition, the Navy should address all existing constraints in sea-shore rotation. The CNO should broaden the objective to managing seagoing personnel as a part of total naval personnel management and should direct relevant elements of the Office of Naval Operations (OPNAV) and second-echelon commands to search for innovative ways to satisfy the morale and retention needs that allow greater flexibility in reducing the cost of the infrastructure.

Recommendations—Competition

The SECNAV-OPNAV-fleet team should determine the best approach for each business operation area with respect to stopping provision of services in-house and instead establishing private-private competitions, public-private competitions, government-owned contractor-operated facilities, or public-private partnerships.

The Navy should no longer depend on a bottom-up tactical approach. The senior cross-functional team should recommend to the CNO and SECNAV particular areas in which to stop in-house provision and instead consolidate into large, more strategic competitions.

The CNO should develop a schedule for the actions recommended above that reflects the urgency of reducing costs in business operations.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 80

Recommendations—Managing Seagoing Personnel

The CNO should expand the Navy's current objective beyond sea-shore rotation to finding the best ways to attract and retain sailors.

The CNO should task an appropriate independent analysis and research firm to better define the relationships among sea tour lengths vis-à-vis shore tour lengths, sea pay, time with family, work satisfaction, and other appropriate factors, to determine the impact on moral and retention of seagoing personnel.

The CNO should establish an ongoing dialogue between the CNO staff (including all stakeholders in reducing the cost of the infrastructure) and the fleet commanders to better define the specific attributes of maintaining morale and retention of seagoing personnel in the Navy.

The CNO should direct relevant elements of the OPNAV and second-echelon commands to (1) search for new and innovative ways of satisfying the morale and retention requirement that would allow greater flexibility in reducing the cost of the infrastructure, and (2) carefully review the requirement or policy for the shore duty billets to be closely associated with the skill(s) required at sea. In addition, the committee recommends the following: (1) balance the potential gain or loss of skills with the loss in flexibility in accommodating new opportunities for privatization of functions; (2) strive to obtain better integration of shore duty billet policies with larger Navy programs and competitive sourcing initiatives; (3) continue and expand the merging of intermediate-and depot-level maintenance programs with military personnel integrated with civilians in shipyards and NADEPs; and (4) look for ways to make use of military personnel in other contractor facilities and in competitive sourcing contracts.

The CNO should change the veto authority of the N1 over billets nominated for competitive sourcing to one of greater management consensus by all of the stakeholders, with the VCNO as the final arbitrator.

Implementing the Strategy

Changes of the kind and magnitude visualized under the strategy outlined in this chapter do not come easily to a large, tradition-based organization. In part, the changes will be induced by the new Navy systems that are acquired, in which new technologies and new system designs will make their own demands on the support system. However, the Navy cannot wait to implement infrastructure change with new acquisition programs. An intensified campaign to make the most of the opportunities presented, especially when it entails extensive organizational and budgetary shifts, will be challenging in the extreme and should be initiated now. The changes involved will entail risks to achieve the benefits sought, and managing—not minimizing—risks will be essential to success.

The benefits to be achieved are obvious. The portion of the Navy's personnel, material, and other resources available to apply to the Navy's core systems

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×

Page 81

and missions will be increased. The Navy's use of highly trained personnel can be better applied to those systems and missions. In improving shore support, the quality of life of Navy personnel and their families will be improved, leading to higher rates of retention and better-trained crews. Overall fleet readiness and combat capability will be improved within given, constrained budget levels. Also, tendencies toward isolation of the Navy from the civilian economy and population that may have attended the shift to an all-volunteer, career force and reduction of its supporting infrastructure through the BRAC process will be lessened or reversed.

The risks are those attending disruption and establishment of new organizational connections and procedures. Traditional organizational responsibilities and authorities will be shifted to other who will have to learn how to use them in new circumstances. Unfamiliar funding patterns will require different justification that may be more difficult to support with budgeting authorities, such as OMB and the Congress, to which the new patterns will be unfamiliar. The order of sequentially dependent changes may be lost in the processes of overcoming institutional resistance, throwing the effectiveness of such changes in doubt without remedying the negative effects of the disruptions or gaining all of the positive benefits that were sought. Mistakes will be made. Some may be costly, using resources sorely needed for substantive investments; other may be irretrievable in a less forgiving oversight environment, causing ripples that could further disrupt the process of change.

In the last analysis, all such risks entail potential added expenditures of time and resources in effecting the sought-after changes, with the chance of using the fleet's financial resources ineffectively and, in consequence, hurting its readiness and combat capability. The benefits, to the extent that they are achieved, will greatly enhance resources available for the Navy's core missions and capabilities, and its readiness along with them.

It is the balance between the risks and rewards that must be weighed by Department of the Navy decision markers in taking each step of the strategy to rationalize the fleet system and its support component. Perhaps the only certainty in the equation is that failure to take at least some of the risks will lead inevitably to further decline in the fleet's efficient and effective use of any available resources, and consequently in its size, capability, and readiness. There thus seems to be no alternative to going forward, managing the risks as they are anticipated and felt.

Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 49
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 50
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 51
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 52
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 53
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 54
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 55
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 56
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 57
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 58
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 59
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 60
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 61
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 62
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 63
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 64
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 65
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 66
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 67
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 68
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 69
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 70
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 71
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 72
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 73
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 74
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 75
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 76
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 77
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 78
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 79
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 80
Suggested Citation:"3 A Strategy for Managing the Infrastructure." National Research Council. 1998. Recapitalizing the Navy: A Strategy for Managing the Infrastructure. Washington, DC: The National Academies Press. doi: 10.17226/6391.
×
Page 81
Next: 4 The Need for Top Leadership to Drive Change Across the Entire Navy System »
Recapitalizing the Navy: A Strategy for Managing the Infrastructure Get This Book
×
Buy Paperback | $64.00
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF
  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!