| Copyright © 2009. National Academy of Sciences. All rights reserved. Terms of Use and Privacy Statement |
Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 91
7.
Interpretation of Case Histories
The original data for the 87 projects discussed herein were obtained
through an extensive procedure (see Appendix C) involving extraction of
detailed information from documents submitted by owners and personal in-
terviews with staff representing the owner, contractor, and engineers
for each project. The procedure was extremely complicated, involving
accurate recording of both qualitative and quantitative data. For exam-
ple, qualitative data included statements regarding problems related to
ground conditions encountered during construction, comments on the ef-
fectiveness of the site investigation program, and opinions concerning
disputes. The quantitative data covered a wide range of items, such as
project costs and schedule, tunnel specifications, geologic criteria,
types and number of exploration techniques, and construction methods and
progress. Subsequently, some basic calculations using these quantita-
tive data were made, for example to derive the face area, volume in cu-
bic yards of excavation, borehole spacing, advance rate per shift, etc.
Occasionally there was some overlap; sometimes the actual excavated vol-
ume in cubic yards had also been obtained from documents supplied by the
owner.
The original data from documents and interviews were recorded on a
15-page data form, with the interviewers often adding several pages of
explanatory information. These data were then combined with the basic
calculations. Thus, there was a large and complex body of qualitative
and quantitative information to be examined.
CaARTED AND PLOTTED DATA
Surmary Matrixes
An array of geotechnical problems that occurred during construction of
the 84 mined tunnels and 3 deep shafts can be seen at a glance in the
summary matrix presented separately as Plate 1. The matrix shows the 87
study projects plotted against the abbreviated "problems encountered"
list from the project abstracts. This list allowed for consideration of
31 separate items grouped into 7 categories: unstable ground, ground-
water inflow, hazardous environmental factors, mechanical problems (rock
and TBMs), soft-ground methods, compressed air, and other.
91
OCR for page 92
Through the use of symbols, the matrix indicates which conditions
developed into problems and which of the problems were serious enough to
cause claims. The matrix makes it clear that most projects encounter
not just one, but several construction problems. What may not be ap-
parent is that many conditions interact or affect each other, so that
some judgment was required in deciding on the primary culprits in an
abbreviated list of problem descriptions.
A second matrix was prepared to chart selected, original numerical
data for each of the 87 projects in combination with basic calculated
data for each. A total of 57 different items were displayed in the
summary matrix, as shown in Table 7.1.
TABLE 7.1 Contents of Data Matrix
Original Data
Name of project
Purpose of tunnel
Number of bidders
Start and finish dates
Cost, engineer's estimate
Cost, bid
Cost, total to build
Cost, exploration
Number of tubes
Length of tunnel
Shape of tunnel
Tunnel volume
Type of ground
Geology (simplified)
Overburden, max and min
Water head, max and min
Water inflow, max and min
Boreholes, number
Boreholes, lin ft
Borehole depth, max and min
Boreholes, distance from centerline
Compressive strength tests, number
Compressive strength, max and min
Construction equipment/method
Primary support
Advance per day, max and average
Days worked
Shifts worked
Crew size
Problems, construction
Liquidated damages in specifications
Claims made, $
Claims settled, $
Calculated Data
Months to build
Factor to escalate costs
Cost, bid as % of estimate
Cost, total as % of estimate
Face area
Tunnel volume
Cost, $/c u yd
Cost, $/lin ft
Exploration, % of tunnel cost
Exploration, $/cu yd
Boreholes, average depth
Boreholes, lin ft/route ft
Boreholes per 1,000 route ft
Boreholes, spacing
Boreholes, $/lin ft
Overall advance per day
Advance per 8-fur shift
Labor, total man hours
Labor, man hours/day
Excavation, man hour s/cu yd
Excavation, cu yd/hr
Claims made, $/cu yd
Claims settled, $/cu yd
Claims, $ settled as % made
The information summarized in the data matrix served for initial re-
view of comprehensive results, following which the content of the matrix
was expanded by additional basic calculations. This revised data summary
92
OCR for page 93
formed the basis for plotting graphically and for arithmetic tabulation.
Among the tabulations were such items as total claims made and settled,
cost in dollars per cubic yard for different methods of excavation,
boreholes in linear feet for tunnels in mountainous areas, etc.
A modified version of the data summary matrix is presented sepa-
rately as Plate 2. It -displays 20 of the 57 items of original and
calculated information contained in the complete summary.
Plots Generated
Our ing several subcommittee meetings, the complete data summary was re-
viewed in conjunction with the problem summary in order to select items
that appeared to be most promising for study. To accommodate the variety
of data selected for examination, the ability to sort and plot graphi-
cally at various scales was essential. A specialized computer program
was written by personnel of Tudor Engineering Company to select and plot
TBM, drill-and-blast, soft-ground and compressed-air tunnels built for
rapid transit, railroads or water conveyance, or underground subway
stations or hydroelectirc powerhouses. Table 7.2 lists the plots gen-
erated to sort the data according to various combinations of parame-
ters. Another computer program without plotting capability, prepared at
Virginia Polytechnic Institute to manage the abstract form of the case
histories, was also used to search and review the data on a general
basis.
TABLE 7.2 Data Plots Generated for Correlation
Plot X Axis Y Axis Method
1 Boreholes, LF/RF Cost, 1982 $/c u yd All
2 Exploration, as % cost Total cost, as % All
eng. est.
3 Exploration, $/cu yd Cost, 1982 $/c u yd All
4 Boreholes, number Cost, 1982 $/cu yd All
5 Avg. Advance, LF/day Cost, 1982 $/c u yd All
6 Claims made, $ Total cost, $ All
7 Boreholes, LF/RF Total cost, as % All
eng. est.
8 Water inflow, max gpm Total cost, as ~ All
eng. est.
9 Bidders, number Total cost, as ~ All
eng. est.
10 Boreholes/1, 000 RE Cost, 1982 $/c u yd All
11 Face area Cos t, 19 8 2 $/cu yd All
12 Water inflow, max gpm Cost, 1982 $/c u yd All
13 Avg. Advance, LF/day Cos t, 19 8 2 $/cu yd All
14 Boreholes, LF/RF Exploration, as % cost All
15 Length, LF Cost, 1982 $/cu yd All
16 Advance rate, LF/day Cost, 1982 $/c u yd TBM, D&B
17 Advance rate, LF/day Cost, 1982 $/cu yd D&B
18 Advance rate, LF/day Cost, 1982 $/c u yd TBM
19 Advance rate, LF/day Cost, 1982 $/cu yd Soft ground
93
OCR for page 94
TABLE 7.2 Data Plots (continued)
Plot X Axis Y Axis Method
20 Boreholes, number Cost, as ~ eng. est. TBM
21 Length, LF Cost, as % eng. est. TBM
22 beg. Advance, LF/day Cost, as ~ eng. est. TBM
23 Exploration, as ~ cost Cost, 1982 $/cu yd TBM
24 Boreholes/l,000 RF Total cost, as ~ TBM
eng. est.
25 Boreholes, number Total cost, as % D&B
eng. est.
26 Length, LF Cost, as ~ eng . est. . D&B
27 Avg. Advance, LF/day Cost, as ~ eng . est. D&B
28 Exploration, as % cost Cost, 1982 $/cu yd D&B
29 Boreholes/l,OOO RF Cost, as % eng. est. D&B
30 Boreholes, number Total cost, as ~ All
eng. est.
31 Length, LF Cost, as % eng . est All
3 2 Avg . Advance, LF/day Cos t, as 9s eng . es t . All
33 Exploration, as % cost Cost, 1982 $/c u yd All
34 Length, LF Cost, as % eng. est. All
35 Boreholes/1, 000 RF Total cost, as ~ All
36
Exploration, as ~ cost
37 Boreholes, LF/RF
38 Boreholes/1, 000 RF
39
Boreholes, number
40 Exploration, as ~ cost
41 Boreholes, LF/RF
42 Boreholes/1,000 RF
43 Boreholes, number
44 Length, LF -
45 Boreholes, LF/RF
46 Total cost
47 Boreholes, LF/RF
48 Overburden, max
49 Avg. Advance/8 hr
50 Avg. Advance/8 hr
51 Avg. Advance/8 hr
52 Excavation, cu yd/hr
53 Excavation, cu yd/hr
54 Excavation, cu yd/hr
55 Avg. Advance/8 hr
56 Avg. Advance/8 hr
57 Avg. Advance/8 hr
58 Excavation, cu yd/hr
S9 Excavation, cu yd/hr
60 Excavation, cu yd/hr
eng. est.
Claims paid, as % All
total cost
Claims paid, as % All
total cost
Claims pa id, as ~ All
total cost
Claims paid, as % All
total cost
Claims made, as 96 cost
Claims made, as 96 cost
Claims made, as 9s cost
Claims made, as % cost
Cost, 1982 $/c u yd
Cos t, 19 8 2 $/cu yd
Cost, as % eng . est .
Avg. Advance/8 hr
Avg . Advance/8 h r
Leng th
Cost, 1982 $/c u yd
Face ar ea
Length
Cost, 1982 $/cu yd
Face area
Leng th
Cost, 1982 $/cu yd
Face area
Le ng th
Face area
Cost, 1982 $/c u yd
94
All
All
All
All
TBM
TBit (water )
All
All
All
D&B
D&B
D&B
D&B
D&B
D&B
TBM
TBM
TBM
TBM
TBM
TBM
OCR for page 95
TABLE 7 2 Data Plots (continued)
—
Plot X Axis Y Axis Method
61 Boreholes, LF/RF Bid, as 9s eng . est. All
62 Boreholes LF/RF Bid, as % total cost All
63 Boreholes, LF/RF Claims made, as 9~ All
eng. est.
64 Boreholes, LF/RF Claims made, as % bid All
65 Boreholes, LF/RF Total cost, as % bid All
66 Exploration, as 9e Bid, as 9e total cost All
eng. est.
67 Exploration, as % Total cost, as % All
eng. est. eng. est.
68 Exploration, as % Claims made, as % All
eng. est. eng. est.
69 Exploration, as ~ Claims made, as % bid All
eng. est.
70 Exploration, as ~ Total cost, as ~ All
total cost eng. est.
71 Boreholes, LF/RF Total project cost, as All
~ eng. est.
72 Boreholes, LF/RF Total project cost, as All
~ hid
"Cost" refers to mined tunnel (or shaft) construction only, excluding
claims and modifications awarded. "Total cost" is synonymous with "as
completed cost," which includes any claims and modifications awarded.
"Project cost" refers to the total contract, of which the mined tunnel
is a part.
Review of the plots led to a determination that many of the combina-
tions of parameters reflected a lack of significant or meaningful corre-
lation. Moreover, in cases where the parameters had been further sorted
for plotting according to construction method, sampling limitations pro-
duced results that were deemed generally inadequate for correlation pur-
poses. The ability to distinguish among the types of projects proved
interesting for discussion of-the plots but provided no conclusive re-
sults.
Variation in sample size was a continuing concern because of its po-
tential for limiting or negating the utility of the plots. As noted
above, the sorting technique was a factor that ultimately yielded inade-
quate samples for more than 30 percent of the plots. However, the plots
generated to examine all projects were also subject to some reduction in
sample size arising from availability of data for parameters. The ef-
fects were most apparent for parameters based on water inflow and on
excavation and advance rates combined with work force units (number of
length of shifts and crew size). Results for other parameters, such as
exploration costs, were monitored for possible sampling influence. From
the standpoint of availability of samples, the parameters considered
most reliable for correlation purposes included data relating to tunnel
length, face area, overburden, cubic yards of excavation, number of bid-
ders, boreholes, engineer's estimate, bid estimate, total cost, and
claims made and awarded.
95
OCR for page 96
The subcommittee critically reviewed the results derived from the
mass of qualitative and quantitative information gathered from the 87
case histories, and selected the more distinct of the pertinent results
for presentation. The discussion that follows is confined to matters
that bear on the nature of the relationship between geology and con-
struction and the significance of the geotechnical site investigation.
INTERPRETATION OF RESULTS
Data derived from the 84 mined tunnels included in the 87 study projects
shown in Plate 1 is tabulated in Table 7.3. Overall, unstable ground is
the most prevalent problem encountered during construction, with
blocky/slabby and running ground cited most often as specific conditions
(38 percent and 27 percent, respectively) for all the projects. Ground-
water inflow is cited as a problem in 33 percent of the projects.
TABLE 7.3 Problems and Claims* Reported for Mined Tunnels
Problems Claims
{% of tunnels) {% of tunnels)
Blocky/slabby rock, overbreak, cave-ins 38 16
Running ground 27 9
Flowing ground 5 4
Squeezing ground 19 8
Spalling, rock bursts 6 4
Groundwater inf low 33 6
Noxious fluids 6 4
Methane gas 7 2
Existing utilities 1 0
Soft bottom in rock 2 2
Soft zones in rock 4 2
Hard, abrasive rock (TBMs) 5 2
Face instability, rock ~ 5 1
Roof stabbing 4 1
Pressure binding (equipment) 4 4
Mucking 5 2
Surface subsidence 9 2
Face instability, soil 11 5
Obstructions (boulders, piles, 12 11
high rock in invert, cemented sand)
Steering problems 4 0
Air slaking 1 0
*AS noted earlier, in this report the word "claim" is a shorthand
expression that encompasses all requests for extras as a result of an
unexpected subsurface situation.
The percentage of incidence as a problem indicated for Groundwater
does not account for its role as a contr ibutor to the incidence or
96
OCR for page 97
severity of other conditions {e.g., flowing ground, face instability),
which would raise its rating significantly. As explained in Appendix C,
there may have been instances where unclear original sources of informa-
tion led the subcommittee to label occurrences of "flowing" ground
(which is wet) as "running" ground {which is dry). This is one of the
reasons that the problem tabulations do not give as much weight to
groundwater as it deserves. The subcommittee believes that water plays
a large and varied role in tunnel construction difficulties; yet it may
not always appear in the simplified listing of problems encountered in a
project because it is a secondary contributor to the primary problem.
For example, face instability would in many cases not have been a prob-
lem without the presence of water to reduce friction along joint surfaces
or create seepage pressure, although the water might exist in quantities
too small to deserve mention under groundwater inflow. In the same way,
if only half of the recorded occurrences of running ground were really
flowing ground, then that would raise by 12 the number of projects for
which groundwater was a contributing cause of significant problems.
Of all the problems, the highest incidence of claims (16 percent)
was recorded for the grouping with the highest incidence of occurrence,
i.e., blocky/slabby rock, overbreak, cave-ins. Of the other five con-
ditions reported most frequently, three exhibit a similar relationship
to claims. However, groundwater ranks several positions higher in
problem incidence than in claim incidence; the ranking for obstructions'
is the reverse. Even so, the overall relationship-is unchanged: The
six conditions causing the most problems cause the most claims. Gener-
ally thereafter, it is difficult to determine a pattern by ranking.~'
However, the significance of a problem is related not only to fre-
quency of occurrence but also to magnitude of impact. The tabulations
in Table 7.3 can be translated to obtain a measure of impact by relating
the incidence of claims to the occurence of problems. This method
reveals that the relationship between occurrence and impact can be
inversely proportional, as shown by the ratings presented in Table 7.4.
For comparison purposes, Table 7.4 lists the problem conditions accord-
ing to their frequency of occurrence, from highest to lowest. The impact
rating is on an ascending scale, with a maximum value of 10. (For quick
comparison between problem occurrence and significance, the impact rating
can be multiplied by 10--i.e., a rating of 9.2 indicates a 92 percent
incidence of claims per occurrence.)
Table 7.4 reflects considerable impact--a rating higher than 6.5--
for six specific conditions, all of which occur infrequently: soft
bottom in rock, pressure binding, obstructions, flowing ground, spelling
and rock bursts, and noxious fluids. At this point the impact rating
decreases suddenly, revealing six conditions closely grouped in the
range from 5.0 to 4.0. In this grouping, the impact rating is moder-
ately high and the frequency is generally low, but a trend begins toward
more direct proportion (i.e.-, for blocky/slabby rock and squeezing
ground). For the remaining problems, the impact rating then drops to
3.3 (running ground), clusters again with five conditions (including
groundwater inflow) between 2.8 and 1.8., and then falls to 0.
97
OCR for page 98
TABLE 7.4 Impact Rating for Problem Conditions
Conditions (% Problems or occur rence)
Blocky/slabby rock, overbreak, cave-ins (38)
Groundwater inflow (33)
Running ground (27)
Squeezing ground (19
Obstructions (12)
{boulders, piles, high rock, cemented sand)
Face instability, soil {11)
Surface subsidence (9)
Methane gas (7)
Noxious fluids (6)
Spalling, rock bursts (6)
Hard, abrasive rock, TBMs (5)
Face instability, rock (5)
Flowing ground (5)
Mucking (5)
Pressure binding, equipment (4)
Roof stabbing (4)
Soft zones in rock (4)
Steering problems (4)
Soft bottom in rock (2)
Air slaking (1)
Existing utilities (1)
Impact Rating
4.2
1.8
3.3
4.2
9.2
4.5
2.2
2.8
6.6
6.6
4.0
2.0
8.0
4.0
10.0
2.5
S.0
o
10.0
o
o
In certain instances (e.g., pressure binding), the severity of a
problem can be linked with the sensitivity of the eons traction method to
a particular condition. In others (e.g., overbreak, obstructions), it
Is less clear whether difficulty is more a function of the existing con-
dition or the technique. It is likely that frequency of occurrence may
sometimes be a moderating influence because it results in enhanced expe-
rience and ability to cope that offsets the problem to some degree. In
part, this may explain why the incidence of claims and/or impact rating
for some problem conditions (e.q., runnnino around) is lower in relation
. . . · . . . . . . . .
to prevalence than might otherwise be expected.
Unfortunately, several important aspects of the relationship between
geotechnical conditions and eons traction problems cannot be readily dis-
cerned or computed. They are the length of delays and degree of ineffi-
ciencies that are introduced as a consequence, and their associated
costs. The cost impact is not limited to construction dollars alone,
but extends to project reliability and longevity.
Although certain aspects remain ill defined, the plots and tabula-
tions of numerical data yielded several interesting trends and quantita-
tive values that help delineate the extent of the interaction of geology
with construction and the effect of the geotechnical site investigation.
The findings relate to the level of exploration, cost estimates, project
costs, and claims.
Before discussion of the findings, the manner of reporting the data
merits a brief explanation. For the tabulated data, results are gen-
erally presented as the arithmetic mean--referred to hereinafter as the
"average," in the commonly understood sense of the word. For much of
98
OCR for page 99
the plotted data, results are cited in terms of the "median. n Here, the
value expressed by the median is considered more accurate than the every-
day form of averaging, because the median accounts for the effects of
significant skew in the samples. The techniques for deriving the values
differ and, therefore, the terms "average" and ~median" are not used in-
terchangeably in this report.
Level of Exploration
In present practice, overall, the average number of boreholes drilled per
1,000 route ft of alignment is 2.4--i.e., a spacing that approaches 415
ft. It should be noted that these figures are based on 84 projects, of
which 20 percent are in mountainous areas where tunnel depth can often
exceed 1,000 ft and hole-to-hole spacing can reach thousands of feet.
When data for these tunnels are excluded in order to reflect more common
practice, then the average number of boreholes per 1,000 route ft nears
3.9, for a spacing that is about 260 ft.
Although these tabulations provide a measure of exploration, they do
not allow sufficiently for the effect of tunnel depth. Therefore, a
more meaningful gauge can be obtained by determining the linear ft of
borehole drilled per route ft of alignment. When the level of explora-
tion is expressed in this manner, then the median lin ft of borehole per
route ft is .34 in overall practice and .42 in common practice. (In
this instance, the averages for lin ft per route ft are similar, .30 and
.43, respectively.)
Exploration costs were extremely difficult to compile because sep-
arate records of the amounts spent were often not available or were
incomplete. In addition, the task of apportioning costs for investiga-
tion programs overlapping several projects was complex. AS a result,
the figures for exploration costs are considered less reliable than
others reported herein.
Of the 84 study projects, exploration costs for 36 were obtained.
Information was sufficient for 30 projects (except as noted) to permit
the extrapolations shown in Table 7.5 Although some inconsistencies in
matching samples were encountered, the preponderance of the data was ob-
tained from projects for which figures were consistently available for
each item tabulated. Therefore, the small variation in matching samples
did not affect the results significantly.
TABLE 7.5 Exploration Costs Compared to Construction Costs
Exploration Costs ($ millions)
Construction Expressed as % Construction
($ millions) Total Overall Range Median
,
Engineer's Estimate 829.87*
Basic Construction** 661.29
As Completed 694.00
9.80* 1.18 .01-24.4 .44
11.53 1.74 .02-17.5 .75
11.53 1.66 .01-17.5 .70
*Figures are based on data for 28 projects.
**Costs excluding claims awarded.
99
OCR for page 100
Figure 7.1 illustrates more clearly the degree and nature of the
scatter indicated by the range cited for exploration costs as a percent
of construction costs. It is evident that funds expended for site inves-
tigation programs do not rise with increasing project costs. Rather, a
significant number of the more costly projects {i.e., those in the upper
half of the scale) exhibit a decrease in exploration funds to a point
well below the median. It is in the mid range that the number of proj-
ects above the median generally equals the number below. However, only
about 30 percent of these projects approach the median within a reason-
ably small range of scatter.
Overall, these results indicate that present practice is to devote a
relatively small portion of project costs to a site investigation pro-
gram. In some instances, low expenditures may be warranted because a
sufficient body of information may be available from explorations con-
ducted for overlapping projects, or nearby projects, or from other
sources such as aerial surveys and regional geologic reports. However,
these circumstances cannot be assumed to explain entirely the general
low level of expenditures or the scatter in the data. Even though the
cost of construction is not always in direct proportion to the geotech-
nical complexity or extent of a project, the relationship between these
factors is obvious. On that basis, it is apparent that level of explo-
ration costs does not correlate satisfactorily with construction costs.
Estimates of Cost: Engineer and Contractor
The engineer's estimate is a measurement of costs that is used by the
owner for a variety of purposes throughout the conceptual to completion
phases of a project. Essentially it serves as a benchmark for the devel-
opment and evaluation of the components of the planning, design, bid-
ding, and construction processes. As such, the engineer's estimate is
depended on to predict the actual project costs with reasonable accuracy.
Figures 7.2, 7.3, and 7.4 compare the as-completed costs for mined
tunnels with the engineer Is estimate. The comparison examines the cost
relationship in terms of several parameters representing the level of
exploration. The individual results combine to form a more comprehen-
sive basis for correlation.
A review of Figures 7.2 through 7.4 reveals that as-completed costs
differ significantly (+50 percent) from the engineer's estimate when
the level of effort or funds devoted to geotechnical site investigations
are low. However, this degree of variability is a reasonable occurrence
only during the earlier stages of the initial conceptual work--i.e.,
when the exploration program is still in progress. This circumstance
suggests that general exploration practice is providing inadequate in-
formation for reliably estimating as-completed costs. The suitability
of the site investigation also must be considered for its sensitivity to
the effort level, an important concern because of its potential influ-
ence on reliability.
The deviation between as-completed and estimated costs decreases as
exploration increases. Figure 7.2 indicates that the engineer's estimate
becomes a more reliable tool for predicting actual costs when sufficient
exploration has in fact been accomplished--i.e., boreholes at greater
100
OCR for page 101
(by-) ue!PaW I
N
Or,
N
00
!
,
. I
1-
(L-) Ue!PaW I \
`1 >
I ~
1
,1 1 1 1 _ 1 .1 _ 1 1 , 1 ._ ~ 1 1
to. ~ o
~1 And
m. o
lSOD NOIlOnUlSNOD JO % SO 1SOO NOIlV~OldX~
101
o LO
~ o
to
l
.
(n ~
LL C:
n in
o
CC ~
~ o
Z Z
of
111
l
LU ~
F_ -
lll ~
J tO
~ O
8 o
~ z
PA
~
OCR for page 102
1
· 1
cs)
oo
u)
~ . -
~ x
LD
x
-
..
~c
~c
zo
co
.—
:'
4 -
~n
~ 4-
q)
4—
q, ·
- o
~n ~
o
.
x a' Ln 0 c~ 0 _ _ ~
. . . . . . . .
oo 0 u~ a~ ~ {D (D
CD 00 ~ O CO ~ U.
~ ~ ~ - - ~
- oo - ~ ~ oo ~ ~
— co ~ ~ ~ ~ r~
C~ ~7 ~ d d r— oo
o o o
· o
1
IL
.
o
o
~i
- ~ ~J
~o
.
.
.
1. ~
.
.
o l ....
1 ·
.
-
P
- o
iD
~ c
~ ~o
.m
~ -
.
u] ~ z
~ - z
- cs
tn
LL
~ uJ
z ~ · - z
i~
z ~
· o 1 o
N l.L
O
LL
0, 0
UJ
00 ~
O <:
z
J
z
_
CD ~
o tn
J
o
I
~L
~ O
O
O
1 ·o
l I I I I I 1. 1 I I 1 1 1 1 1 1 1 1 o
O O O O O O O O o O ~
00 (D ~ C~ o oo ~ ~ ~ P;
_ ~ _ ~ ~ ~
V
31~WllS3 S,8 33N 1 9N3 J0 % SU lSOO G3131dWOO-SU
102
OCR for page 103
o
. -
x -
~D
~ -
-
u,
.—
'': o
x -
o
. ~
- ~
~ o
. - ~
~ tn
~ 4-
cn z
u)
c~
4 -
-
co
o
c]
4 -
o
o
.
1 1. 1 1 1 1 1 1
~n
LU
u)
~:
Ul
u]
z
z
,l
l
l
1
1
1
l
l
l
1
1
l
.
.
.
.
· !. o
~ 1 - 1 1 1 - 1 1 1 1 1 1
o
LL
cn
CO LL
z
I
U)
J
C~
X
-
C9 ~
o
C~
z
O
.
z
o
tn
m
LL
o
C~ ~
.
~n
o
_ ~
_ ~ Z
0 O
.2 _
~ O~
Ln _ ~ X
llJ
— 0
O L~
C)
LL
O O O O
rn
0 ~
oo
31UWllS3 S,833NI9N3 30 % SU lSOD 03131d~00-SU
103
o o
d. N
OCR for page 104
1
1
X . - . 1
~ con,- 0 1
~ ~ -
1
In LL
~ - ~
ret
' x
o o ~
LL
.. in
c
- ~ ~
(D O LL
. - "c ~
cn c
~ o ~
~ z z
a, UJ
A) ~
in c)
~ c, 1
c' ~
~ o 1
l
1
1
o
1
o 1
1 1 1 1 1 1 1. 1. 1
.
o
1 1 · 1 1 1 1 1 1
o ~
31~1WllS3 S,833NION3 JO % SO lSOO 03131d~00-S~
104
lo.
lo.
in
U)
UJ
UJ
z
o CD
~ Z
U]
LL
o
<(
N ~
~0
Z
O O
. _
N ~
o
X
lL
O O
~ N
O
O ~
~:
V
OCR for page 105
than 0.6 linear ft per route ft. At this point, a substantial reduction
is reflected in the frequency and degree of scatter above the estimate.
A similar trend is exhibited in Figures 7.3 and 7.4' when funds expended
exceed one percent. Decreasing scatter below the estimate is less marked
in degree, but it is a tendency worth noting.
The contractor's bid was examined in terms of two of the three param-
eters used in evaluating the engineer's estimate. Appropriately, the
major difference in approach was to review the relationship of the con-
tractor's bid to both the engineer's estimate and as-completed costs.
These results are presented in Figures 7.5, 7.6, and 7.7.
In Figure 7.5 it is apparent that the discrepancy (+SO percent)
between the bid and engineer's estimate decreases as the exploration
level nears and continues beyond 0.6 linear ft of borehole per route ft
of tunnel alignment. Then, the bid begins to approach, and is generally
less than, the engineer's estimate. Interestingly, it can be observed
that Figure 7.5 reflects results distinctly similar to Figure 7 . 2 with
respect to incidence, degree, and pattern of scatter.
At least a partial explanation for this similarity is provided by a
review of Figures 7.6 and 7.7, which compare the bid estimate and as-
completed costs. Here, the incidence of scatter is consistent with that
exhibited previously for low levels of exploration, but the degree of
scatter is less pronounced (230 percent rather than +SO percent).
Moreover, at more suitable levels of exploration (greater than 0.6 for
boreholes or one percent of the engineer's estimate), the convergence of
the contractor's bid with as-completed costs is excellent, in terms both
of degree and consistent pattern. The benefits resulting from the geo-
technical site investigation are obvious.
The difference in effects noted for the engineer's estimate and the
contractor's bid merits attention to consider some of the possible
causes. First, it might be expected that the contractor would be more
experienced in evaluating requirements for tunnel construction suited to
various purposes and ground conditions. Moreover, it is the contrac-
tor's business to be accurate in determining the cost of individual
elements so that an advantageous cash flow can be maintained. The
margin between profit and loss is rarely sufficient to accommodate major
inaccuracies without severe consequences. In comparison, the engineer's
estimate is intended to predict total costs for the entire project (of
which the mined tunnel is only a part) with a reasonable degree of accu-
racy, which permits a more flexible approach. However, this built-in
tolerance can be diminished or even eliminated if the estimating process
is constrained. Among the elements that particularly influence the
results are inflation before and during construction, constructibility,
and detailed subsur- face information. If policy, procedures, or cir-
cumstances limit the determination or incorporation of any such basic
components, then the accuracy of the engineer's estimate can be reduced
accordingly and often to a profound degree. As inaccuracies escalate,
it is increasingly difficult to avoid distortion of the estimate for the
entire project.
Certainly the bases for accuracy differ somewhat between contractor
and owner, as well as the strictness of the criteria. In the final anal-
ysis, only the owner can determine if the criteria have been satisfied
when the engineer's estimate is simply higher than as-completed costs.
105
OCR for page 106
l
a,
co
~ .—
~ x
'I:
x
r~
N ..
C
~C
._
~ ~n
~ _
U) ~
C) ~
4-
._
_ O
~ .
o
.
X ~ O C~ — ~ N 1— 10
O ~ 0O tD — ~ O C~
(D CO CS) O 00 C~ CD 00
— N _ C~)
— 0o — LD 0~ CO C~ UD
— ~ ~ ~ ~ ~ r~
C~ ~ ~ ~ ~2 I~ 0 -
O O
1 1 1 1 1
O O
OO CD
o
_ N
UJ
~S
cn
UJ
~:
LL
Z
z
111
.
.
l
· · O
.
·.
.
.
o
~0
_ C~
~ .
~ .m
O
C~
~o
._
N
O
C~ lL
— O
O O
_ CS:
~:
Ul
0D
O ~
UJ
z
J
z
o U'
o
I
UJ
~ O
O m
1 o .
1. .0. _
1 . 1 1 1 . 1 · 1 1 1 · 1 1 1 1 o ~
0 0 0 0 0 0 0
d ~ O CO CO ~ C~
_ - —
31UWllS3 S,833NION3 JO % S~ GlS S,HOlOVUlNOD
106
OCR for page 107
.'oa~om~ ·~ ]=
0 ~ so ~ 1
~ a) a) al a) cot 1
so 1
A",, 1 — ~
CD <( Lo CJ) OD ~ Ln · ~ Z
X ~ ~ rat so ~ — ~
(~ o o o c] do. z
~ .. ~ -
- ~ ~ ~
..
~ O O ~ Z
~ ·=
_ o 1 -
o 1 ~
1 o O
1 _ cc
1
1 ~ _
1 ~ . .
AID ~
~ z
· ~ · z
1. _ ho'
· ~ LLJ
~ · — E °. O
t ~ o m
4~10 0 0 {~~ —U O
.~- · ~ 5
O ~ o - 0 g O ~ ~0 0 0
C)
lSOO G3131dWOO-S~ JO % SO 'ClB S,HOlOVUlNOO
107
OCR for page 108
· l
·- c] o.
in co ~
co ~ - ~ o
~ -
o
.-
x~_ 1
c ~
_ ~ 1 - o.
~ In 1 ~ L1J
' o 1 ~
4) - ~
In ~ _
1 —~ UJ
. cat in
to ~ ~
~ ~ 1 ..
o 1 - Liz
1 on
.
t
t
1 ~
1 .m
, ~
~ o $
1 .. .-
t
LL
o
cn
U. ~
. ~
in
o
C'
z
o. °-
CC
o
J
X
.
O
O
· In. 1 1 1 1 1 1 1 1 1 10 ~
O O O O O O O O O O
CO (D ~ Cat 0 00 CD ~ Cat
_ ~ ~ — ~ z)
lSOD 03131dWOO-SU JO % SU 'Cl ~ S,HOlDVUlNOD
108
OCR for page 109
Claims
Requests for extra payments for unexpected subsurface situations--i.e.,
claims--appear to be a significant part of tunnel cost. Of the 84 mined
tunnels studied, 49 reported claims related to geologic and/or subsur-
face conditions. (Three of these claims were for comparatively small
amounts, i.e., less than $25,000.) Projects without claims totaled 29,
and there were 6 for which no information was available on whether claims
-had occurred or not. Overall, then, it appears that about 60 percent*
of tunnel projects entail claims, and that claims are substantial for
about 55 percent of tunnel projects. Stated differently, of the proj-
ects experiencing claims, nearly 95 percent of the claims are for large
amounts.
Of the 49 tunnels with claims, there were 32 for which sufficient
data were reported (Table 7.6) to permit evaluation. Combining the fig-
ures in Table 7.6 yields the following sums (in constant 1982 dollars):
total claims of $253.7 million, claims paid of $161.8 million, basic con-
struction costs of $1,364.8 million, and as-completed costs of $1,526.6
million.
Examination of the data for the 32 tunnels reveals that 11 of the
claims (8 major and 3 minor) were settled for essentially 100 percent of
the amounts requested, one major claim was settled for 115 percent, and
3 major claims were settled for zero payment. The remaining 17 claims
were settled for sums varying from 10 to 70 percent of the amount re-
quested, for an average of 39 percent. There is no apparent relationship
between the amount of the claim--made or paid--and the original size of
the project.
Overall, the indication is that payments were settled at about 64
percent of the original total claimed. These payments amounted to nearly
12 percent of the basic construction costs. (If this average were com-
puted from the claimant's viewpoint~-i.e., increase the as-completed
total by $91.9 million [the difference between claims made and paid] to
reflect construction costs considered justifiable--the settled payment
would approach 10 percent.)
In view of these results, the possible influence of the exploration
program is an unquestionably relevant concern. Therefore, claims were
reviewed in terms of several parameters that served for correlation in
the preceding sections. To obtain an appropriate comparison, the data
base was expanded by removing the limitations imposed for Table 7.6.
Claims made were examined in terms of both the engineer's estimate and
contractor's bid, and then compared with the exploration level for bore-
holes.
*It is possible that this figure may be low as an extrapolation to
industry-wide occurrence. At least two owners who volunteered completed
projects are known to have each withheld one newly completed project with
claims currently in litigation. If very many of the participating owners
faced similar dilemmas, then the sample may be biased toward the "no
claims" end of the study spectrum. Also, some projects with litigation
completed may have been withheld to avoid possible embarrassment to any
interested parties. The subcommittee hopes that the potential for dis-
tortion is minimal and limited to unresolved claims.
109
OCR for page 110
TABLE 7. 6 Compar ison of Claims with Construction Costs
Totals* Repor ted for Claims
Tot_ls* for Constr action
Claims Made Claims Paid Bas ic** As-Completed
-
0.008 0.008 4.69 4.7
0.008 0.008 12.59 12.6
0.010 0.010 4.79 4.8
0.060 0.020 10.18 10.2
0.250 0.150 11.65 11.8
0.350 0.350 16. 15 16. 5
0.600 0.600 14.4 15.0
0.680 0.170 16.43 16.6
0.700 0.700 21.4 22.1
0.747+ 0.747+ 32.3 33.05
0.787 0.387 25.013 25.4
0.800 0 5.9 5.9
1.000 0.200 15.2 15.4
1.290 0.370 28.83 29.2
1.400 0 19.4 19.4
1. 600+ 1.600 29.0 30.6
1. 800+ 1.800 99.9 101.7
2.000 0 275.5 275.5
2.100 2.100 51.2 53.3
2.100 1.200 - 71.5 72.7
2.600 1.500 32.3 33.8
5.400 2.000 18.5 20.5
6.900 1.300 29.7 31.0
7.500 0.750 19.55 20.3
8.100 2.980 73.22 76.2
11.800 3.400 42.6 46.0
19.200 11.100 104.5 115.6
25.100 7.950 140.55 148.5
25.100+ 25.100 44.2 69.3
28.200 20.200 34.8 55.0
37. Coo 7.500 - 29.8 37. 3
58.500 67.600 29.1 96.7
*Constant 1982 dollars, in millions.
**Costs excluding claims paid.
Results of the compar ison, presented in Figure 7.8, indicate a well
defined relationship between claims and the exploration effort. At low
levels of exploration, approximately 50 percent of the requests were for
amounts greater than 10 percent of the engineer's and contractor's esti-
mates. Overall, claims averaged 29 percent of the engineer's estimate
and close to 28 percent of the contractor's bid. As soon as exploration
exceeds 0.6 linear ft of borehole ner route ft of alignment, a marked
. , _ _ _ , , _ _
~ _ , _ ,
_
.
. . .
, ~ ,
_
~ . _. .
decrease occurs in tne number ana size or the claims. Ants trend down-
ward continues sharply as the borehole level exploration increases. A
similar comparison of claims and funds expended for exploration produced
matching results. Thus, it is clear that the s ite investigation program
can moderate the occurrence of claims and their severity.
110
OCR for page 111
80
70
us
~ m 60
In En
UJ ~
In O
LL <(
z ~
z 50
z O
c~
LL
O O
O ~ 40
UJ
LL
3 30
LL
~:
in
LL
z
I
20
10
o
FIGURE 7.8
- t
o
.
1
·
o
o o
. ~
.
o
~ ~ o
.
.
o
.
o
-9, . ~
~o o ~ o ~o
0.^ ~ 0 1 1 1
· Bid Data Only Avai fable
~ Selected Case Studies 2, 3, 6, 7, 8, 9
Project Data Not Shown:
X Axis O Y Axis ~ Y Axis
0.01
_ 9.75
~ 0.41
188.1
197.8
72.6
139.7
235.0
126.9
o
0 0.5 1.0 1.5
BOREHOLES,
2.0 2.5 3.0
IN LINEAR FT PER ROUTE FT OF TUNNEL ALIGNMENT
111
3.5 4.0
OCR for page 112
Project Costs
The ultimate cost of projects can be estimated accurately and controlled
or moderated without sacrificing fair compensation. These goals are at-
tainable when the site investigation program is conducted at a sufficient
level to permit thorough evaluation of the subsurface by all parties to
the construction process and according to their specific needs. However,
the exploration program can only contr ibute successfully to these goals
if the level of effort is increased as a matter of general practice.
This belief is based In part on the following f indings , which relate to
the relationship between exploration and project problems and costs.
· Of all the projects studied, only 11 reported no s ignif icant prob-
lems and none reported minor problems alone. For more than 85 percent
of construction projects, the typical level of site investigation is too
low to characterize subsurface conditions adequately in order to plan
for or avoid impact on constructibility. This circumstance leads to
inaccurate budgets and schedules, inappropriate construction procedures,
unnecessarily (often) high increases in as-completed costs, claims and
litigation, and difficulties with operations and maintenance.
· The engineer's estimate varies 250 percent from both bid costs
and as-completed costs at the levels of exploration commonly practiced.
These deviations are a source of uncertainty for the owner, contractor,
and the public, and promote costly adversary relationships. When typical
exploration practice is increased, bids and as-completed costs tend to
equal or even fall below the engineer's estimate.
· Claims related to unanticipated subsurface conditions occur for
about 60 percent of construction projects. In some instances, a claim
may be part of the fair cost of a project. Overall, however, claims and
disputes result in inefficiencies that are expensive for the owner and
contractor. Improving site characterization by increasing exploration
reduces the incidence of claims and attendant effects; when unnecessary
claims are avoided, construction is more economical.
· A significant portion of project costs stems from claims settle-
ments rather than from investigation of the site for design and con-
struction purposes. The typical one percent (about) of project costs
expended for exploration Is obviously too low when compared with the
average 12 percent of project costs devoted to settled payments for
claims. If this figure were extrapolated from 65 to 100 percent of the
projects reporting claims, then the average minimum settlement is
slightly greater than 7 percent of project costs. However, these aver-
ages represent only the amounts publicly paid in settlement of a claim.
For the adversaries, there are additional costs for staff and legal ser-
vices that usually are not disclosed. These "hidden" costs can be tre-
mendously high, and in some instances may reach a total that represents
a signif icant portion of the pro ject cost
The geotechnical s ite investigation cannot predict every problem
that may be encountered, and attempts to do so generally result in pro-
grams that are disproportionately expensive for the value received. For
every underground project, cost-benefit is a key element. Increasing
the level of effort and funds for exploration is demonstrably beneficial
and cost-effective.
112
Representative terms from entire chapter:
tbm tbm tbm