CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS—GOVERNMENT PERSPECTIVE

Robert M. Griffin, Jr.

Naval Facilities Engineering Command

The greatest difficulty originally experienced by Naval Facilities Engineering Command (NAVFACENGCOM) personnel was in trying to use familiar firm fixed-price contracting methods for an undefinable requirement. We quickly discovered that only new and varied types of contracts could enable us to deal with the increasing demands of the navy's Environmental Program. The Navy's strategy, therefore, is to establish and maintain a portfolio of contract vehicles that in concert will successfully execute the Navy's environmental requirements.

CLEAN Contracts. The Comprehensive Environmental Response, Compensation and Liability Act of 1980 requires that response action contractors be selected using Brook Act procedures. Accordingly, NAVFACENGCOM procures environmental work which requires a licensed professional (i.e., studies and designs) utilizing “Brooks Act” procedures. This process uses technical merit as the basis for selection. To manage this type of work NAVFACENGCOM developed a series of Cost Plus Award Fee, Architect-Engineer contracts known as CLEAN (Comprehensive, Long-Term Environmental Action, Navy) contracts.

The primary focus of the CLEAN contracts is the study and design phases of the installation restoration program and post remediation inspection services. The CLEAN contracts are administered on a regional basis. Their term is a base year with nine option years. The values of these contracts range from $100 million to $260 million per contract. We currently have eight CLEAN contracts for a total of $1.2 billion. NAVFACENGCOM is presently negotiating two new CLEAN contracts at our Southwestern Division (San Diego, CA) and at our Northern Division (Philadelphia, PA).

Fixed-Price Contracts. With experience we have been able to separate from the cost reimbursement arena various project types which can be accomplished on a fixed-price basis. Some examples are air and water studies, compliance evaluations, underground storage tank removals, asbestos abatement, and uncomplicated remediation projects.

RAC Contracts. Since the CLEAN contracts are awarded utilizing “Brooks Act” procedure, remedial action cannot be accomplished except in rare cases where immediate

Suggested Citation:"CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS -- GOVERNMENT PERSPECTIVE." National Research Council. 1994. Environmental Remediation Contracting: Summary of a Symposium. Washington, DC: The National Academies Press. doi: 10.17226/9266.
×

removal is necessary to prevent continued, unacceptable risk to population and environment. Work which does not require a licensed professional (i.e., remedial action and long-term maintenance) is procured utilizing price competition. Since technical considerations may be more important in environmental remediation than lowest price, we utilize Source Selection procedures. This involves evaluation of factors such as technical capability, management capability, quality and depth of human resources, and experience with a variety of types of environmental remediation in addition to cost. Award is made to the contractor whose proposal represents the best overall value to the government.

The Source Selection process was used to award eight contaminant-specific Cost Plus Fixed Fee (CPFF) Remedial Action Contracts (RAC) which are nationwide in application but are centrally managed in Port Hueneme, CA. The aggregate value of all eight contracts is $150 million and the maximum term is five years. A primary focus of the RAC contracts is complicated remedial action efforts and technology demonstration projects. Our decision to centrally manage the first eight RAC contracts was driven by the small number of remedial actions anticipated at that time. As earlier studies are completed and the Navy moves heavily into remedial action, we believe that RAC contracts will be awarded on a regional basis and will probably be structured to include several compatible types of contaminants. Use of the fixed fee may not enable us to adequately incentivize excellent work since the contractor would receive the same fee for any acceptable performance. Therefore, whenever resources are available the award fee is preferred for any large, continuing effort.

Environmental Job Order Contracting (JOC). The newest type of contract vehicle being tested is a combination Fixed Unit Price Indefinite Quantity contract. Wage rates to be paid are based on the local Davis-Bacon wage determination. Unit prices are bid for materials and equipment usage. A multiplier is bid which includes indirect costs and profit. When a delivery order is being negotiated, a reasonable number of hours and units will be determined. The multiplier will then be applied to the total negotiated price of the delivery order. The primary focus of this type of contract is small environmental compliance projects.

Special Requirements. The availability of all of these contract types is the first defense against environmental contracting problems. However, the use of cost reimbursement contracts may result in additional contracting pitfalls. For example, in most cases neither the contractor nor the government personnel are acclimated to the requirements of cost reimbursement accounting as contrasted with fixed price accounting. The applicability of indirect costs was not a problem when the contractor merely quoted a final price, which he determined annually covered all of his costs and permitted a reasonable profit. Award of a cost reimbursement contract may require the contractor's accounting system to attain a new level of sophistication. Government personnel must use caution when developing the basic requirement since the government must pay for all reasonable effort. Technical oversight which includes decisions on what type of effort is required becomes crucial. Financial personnel can contribute to an understanding of cost accounting methods which is necessary to perform the invoice review to certify only allowable, allocable, reasonable and applicable costs for payment.

Suggested Citation:"CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS -- GOVERNMENT PERSPECTIVE." National Research Council. 1994. Environmental Remediation Contracting: Summary of a Symposium. Washington, DC: The National Academies Press. doi: 10.17226/9266.
×

Oversight Requirements. The administration of a cost type contract is extremely resource intensive. NAVFACENGCOM greatly benefited from having a structure already in place for the administration of construction contracts. While the need for Navy construction has decreased, the need for environmental remediation has increased, especially with respect to base closings. This change permitted NAVFAC resources to be transferred to meet the new requirement. A regional structure which includes contracting, technical, and financial components is essential in the administration of very large cost reimbursement contracts. Attempts to manage large cost reimbursement contracts without such resources bear a high risk of failure. Specialized training in the administration of Cost Reimbursement contracts is critical. Accordingly, NAVFACENGCOM developed a five-day Environmental Cost Reimbursement course and a three-day Environmental Contracting Officer's Technical Representative course to supplement previous contracts training.

Standardized Procedures. Committees composed of NAVFACENGCOM regional representatives developed generic Invoice Review Procedures, Award Fee Plans, RAC Acquisition Plans, Source Selection Plans, and Request for Proposal documents. These jointly developed procedures provide a more standardized response to the environmental industry and distribute lessons learned throughout the NAVFACENGCOM community.

Conclusion. Each new development was a response to a pitfall discovered during solicitation and administration of environmental remediation contracts within NAVFACENGCOM. Keys to continuing success in contracting for a clean environment will include:

Continuous development of innovative contract vehicles;

Maintenance of a large portfolio of contract options;

Continuous training in new contracting methods; and

Establishment of partnerships, both internal among different professions and external with clients, regulator, and the hazardous waste management industry.

Suggested Citation:"CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS -- GOVERNMENT PERSPECTIVE." National Research Council. 1994. Environmental Remediation Contracting: Summary of a Symposium. Washington, DC: The National Academies Press. doi: 10.17226/9266.
×
Page 17
Suggested Citation:"CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS -- GOVERNMENT PERSPECTIVE." National Research Council. 1994. Environmental Remediation Contracting: Summary of a Symposium. Washington, DC: The National Academies Press. doi: 10.17226/9266.
×
Page 18
Suggested Citation:"CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS -- GOVERNMENT PERSPECTIVE." National Research Council. 1994. Environmental Remediation Contracting: Summary of a Symposium. Washington, DC: The National Academies Press. doi: 10.17226/9266.
×
Page 19
Next: CONTRACTING FOR ENVIRONMENTAL STUDIES: PITFALLS AND CAUTIONS -- CONSULTANT'S PERSPECTIVE »
Environmental Remediation Contracting: Summary of a Symposium Get This Book
×
 Environmental Remediation Contracting: Summary of a Symposium
MyNAP members save 10% online.
Login or Register to save!

READ FREE ONLINE

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!