Improving the Accuracy of Early Cost Estimates for Federal Construction Projects (1990)

Chapter: Appendix C The Construction Budget Preparation Process at IBM Corporation

« Previous: Appendix B The Construction Budget Preparation Process at the Naval Facilities Engineering Command
Suggested Citation:"Appendix C The Construction Budget Preparation Process at IBM Corporation ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
×
Page 31
Suggested Citation:"Appendix C The Construction Budget Preparation Process at IBM Corporation ." National Research Council. 1990. Improving the Accuracy of Early Cost Estimates for Federal Construction Projects. Washington, DC: The National Academies Press. doi: 10.17226/1693.
×
Page 32

Below is the uncorrected machine-read text of this chapter, intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text of each book. Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.

APPENDIX C 31 Appendix C The Construction Budget Preparation Process at IBM Corporation Prepared by Edward Marsch* Based on business needs, operating units within the corporation working with the Real Estate and Construction Division (RECD) prepare a Statement of Requirements (S/R) to establish the need to house people and/or equipment in new facilities. The S/R includes absolute requirements for these facilities and also, in some cases,” wish lists” of additional elements which the Operating units would like to incorporate, if feasible. The Statement of Requirements is quantitative and covers approximate size, intended population, location, and inter-relationships. It also lists the need for such special spaces as cafeterias, auditoriums, computer spaces, classrooms, etc. Once the requirements have been determined, the Consulting Services Group, comprising architects and engineers, takes the S/R and develops a Design Criteria (D/C) or building program which is qualitative in nature. Depending on the type of proposed building, certain Corporate Facilities Practices (CFPs) are observed. These documents define the minimum standards which must be maintained in the design of the facility. Next, the D/C is translated by Consulting Services into a set of Estimating Assumptions (E/A) for all trades. The assumptions form the basis from which the Statement of Requirements could be built, to IBM's standards. At this time the building is purely hypothetical in nature, as all this preparatory work takes place before retaining an Architect. IBM has developed a standardized computerized format for these Assumptions which allows the group to work logically through the proposed project. It includes the elements and systems most commonly found in typical IBM facilities. RECD has developed a standard Construction Library. This document is a detailed listing of all construction elements found on IBM projects. The library is coded specifically for IBM's use and it bridges the Masterformat/CSI trade numbering standard format to IBM's Construction numbering format. It is designed to be adapted for use on each IBM project, and ties in with the Standard Estimating Assumptions. RECD's estimating department prepares a budget estimate from the S/R, D/C, and E/A. As nearly as possible many of the elements of the proposed building are incorporated into the estimate, and the pricing reflects RECD's experience of constructing buildings in many parts of the country. In the civil, structural, and architectural trades, Unit Pricing is usually performed. For the mechanical and electrical trades, the estimator generally breaks down his estimate into labor, material, and equipment costs. To the construction cost, the estimator adds line items including architects' fees, IBM costs, and any other special considerations to reach between the budget and a recently completed project. This provides a sanity check to his estimate. The budget estimate, the bridge and a preliminary schedule are then presented to IBM's senior management for funding approval. *Edward Marsch is the Director of Planning/Analysis of IBM's Real Estate and Construction Staff.

APPENDIX C 32 Assuming approval of the project, an architect is retained to begin design. RECD provides him with copies of the S/R, D/C, CFPs, and Construction Library. He is also given a construction budget within which he must design the facility. IBM specifically avoids giving him copies of the Estimating Assumptions and the Budget Estimate since these could well limit his creativity in reaching a successful design solution. The architect prepares a design solution for IBM's review, together with his own budget estimate which is presented in the Construction library format to enable IBM to compare the costs against the original budget. After the scheme has been approved, the A-E prepares preliminary drawings which are submitted to RECD for review and comment. IBM examines the plans and specifications and verifies that the estimate is reasonable for the scope described. At this early stage the estimator ensures that the project remains within budget while the Consulting Services Group monitors overall design. As a team, the two groups manage the development of the project. If, at any time, the cost for the proposed project exceeds the budget, RECD initiates a series of meetings with the A-E and the design team, to review the design with the intention of reducing the overall cost without sacrificing the quality of the job. Such “Value Engineering” could affect any part of the job, from substituting a structural system (steel vs. concrete frame), a mechanical system (ducted return vs. plenum), or an electrical system (conduit and wire vs. BX cable). As the project becomes better defined, each level of detail is checked from preliminary and intermediate stages through final drawings. Each stage is accompanied by estimates reflecting the increased level of detail and are matched against the original estimate. The Construction Library, as mentioned above, is used throughout the planning and budget stages of the project and into the bidding cycle. Contractors are required to submit their proposals when bidding the work, using the IBM/CSI format in order to provide estimate comparison. Payment requisitions are submitted using the same format, and IBM's accountants use the same document to capitalize the project. The Library is a major resource in the creation of an Historical Data Base from which much valuable information can be obtained for use in the preparation of budgets for future projects. Throughout the course of the project, IBM uses the budget estimate as a basis for comparison between the original concept and the finished product. During the buy out phase of the project and in the negotiation of change order work the IBM/CSI format provides ready access to cost data, which eliminates much of the guesswork otherwise encountered, primarily because the format allows the cost of the work to be broken down into fairly concise construction elements. As can be seen from the above narrative, IBM places great importance in developing detailed, realistic budgets, and then manages the project to it.

Next: Appendix D Current Procedures for Preparing Early Estimates »
Improving the Accuracy of Early Cost Estimates for Federal Construction Projects Get This Book
×
Buy Paperback | $40.00
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF
  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  6. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  7. ×

    View our suggested citation for this chapter.

    « Back Next »
  8. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!