Question-and-Answer Session

How should DOE deal with flawed projects brought to the agency by congressional supporters?

Dr. Merrow: It would be very unusual if after project professionals said during that critical scoping phase that it was a bad project, that management wouldn’t respond by telling congressional sponsors, “This isn’t something we really ought to do.” If you raise the issue as project professionals, most of the time you can help kill the bad projects. I don’t know any project professional who relishes that role, but in the long run the businesses in the private sector deeply appreciate it, and I would hope that your management would as well.

Mr. Porter: If you see something that you know is not right, then you have got to put that on the table, because if you don’t, then resources are going to be spent and value is going to be wasted, and that is money and time and talent that is not going to be available to do what the right thing was to do. The best way I have found [to address this issue] is either through the use of credible experts viewing an issue and commenting on it in a public way, in our case with some of our technologists, or through the use of people who can help you develop the data that then becomes the basis for the decision, and then people can decide anything they want if they have better data. And it helps put it more on a business footing.

What are companies doing to “evergreen” their organizations so that technical competence is maintained?

Suggested Citation:"8. Question-and-Answer Session." National Research Council. 2002. Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning. Washington, DC: The National Academies Press. doi: 10.17226/10343.
×

Mr. Porter: Despite the slow economy, DuPont Engineering is continuing to hire young engineers even though other parts of the company are not. We are trying to operate the company today a little differently from an engineering competency point of view than we operated it in the past. We are trying to run it as an integrated operation and to operate it at corporate critical mass as opposed to critical mass within the centralized competency, so that we can reach out and those people who have those competencies within the business units become a part of that project management group. One of the ways we are going to try to accelerate that training process is by running a project inside. Basically we are doing a DuPont lead project and starting to bring some of our better younger people into that project. It is about a $30 million job, and we set it up as a center and do a little training on the job.

We have created the DuPont Engineering University, which has brought together the sum and substance of all of what we know about what makes for best practice. We have also created a Project Leaders Academy and a Project Managers Academy, and we are starting to train people in a very focused and aggressive way.

How do agencies with dispersed implementing centers maintain consistent performance, planning, or implementation of projects?

Dr. Merrow: If top management doesn’t buy into what is required for a good project system, you will ultimately fail. However, I have seen a number of cases where there is a slow, steady, very effective educational effort by the senior management saying: This is good for our business. Let me show you how, give us an opportunity by supporting this and we will show you how it works.

Mr. Gregory: ChevronTexaco has a decentralized organization with business units all around the world working projects in their operational area. Each has its own delegation of authority, each is accountable for the business plan, for meeting the business plan, for setting up the business plan, and making sure that plan is in concert and alignment with the organization.

To what extent have integrated project teams been used during the front-end loading to assess risks, and the results used in crafting the project acquisition strategy, decision making, and execution management?

Mr. Porter: At DuPont, the integrated team is supposed to include all the competencies required to make up a whole project. Once the team has generated enough information to begin to understand the business outcome, DuPont will run a process called decision risk analyst. We refer to that as the DRA, and it is just another one of those discipline tools that you can use to go through and look at the various sensitivities that you have versus price, volume, capital, or what-

Suggested Citation:"8. Question-and-Answer Session." National Research Council. 2002. Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning. Washington, DC: The National Academies Press. doi: 10.17226/10343.
×

ever you are looking to assess. Its output is rolled up into a package that goes to the business managers who make the decision whether to pursue the project.

Dr. Merrow: It turns out that the critical risks for a project in the private sector are around whether or not anybody wants to buy what it is that we are going to make, and those are so fundamental that it is remarkable that we miss them so often. Like most other activities, there are ways to significantly mitigate the risk by doing the right things very early on.

How could private-sector project systems be applied to the federal government, which is not disciplined by market considerations?

Mr. Gregory: Project systems such as CPDEP or PACE can be used for any project, whether it is a road construction project, a disposal site, or a marine vessel. Any project, whether it is capital or not, can benefit and will benefit from a process such as the ones you saw today or we discussed today.The CPDEP process was used to implement the merger of Chevron and Texaco.

Dr. Merrow: Federal regulations make it difficult for project managers to develop the trust relationship needed to efficiently manage a project.

Mr. Porter: Appropriations rules require project managers to come back to Congress for action if their projects overshoot estimates by even a small amount. In this environment, people have a tendency to want to put in contingencies. Now, you have opened the door to other kinds of thought processes about how money gets managed. An owner tends to estimate a project on the basis of what it should cost, not what it will cost, and therein lies a difference in terms of the way you can think about the two types of project system, at least in terms of what I have seen in the past. The key is to come up with some lowest investment strategy, so that you are always only estimating what it really should cost to do that piece of work. If you’ve got a system that allows you to want to know how much it actually will cost, then you’ve probably got something that is awry in there. So appropriations rules can make a big difference.

Suggested Citation:"8. Question-and-Answer Session." National Research Council. 2002. Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning. Washington, DC: The National Academies Press. doi: 10.17226/10343.
×
Page 35
Suggested Citation:"8. Question-and-Answer Session." National Research Council. 2002. Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning. Washington, DC: The National Academies Press. doi: 10.17226/10343.
×
Page 36
Suggested Citation:"8. Question-and-Answer Session." National Research Council. 2002. Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning. Washington, DC: The National Academies Press. doi: 10.17226/10343.
×
Page 37
Next: 9. Wrap-Up Observations »
Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning Get This Book
×
 Proceedings of Government/Industry Forum: The Owner's Role in Project Management and Preproject Planning
Buy Paperback | $21.00 Buy Ebook | $16.99
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF

Recurrent problems with project performance in the U.S. Department of Energy (DOE) in the 1990s raised questions in Congress about the practices and processes used by the department to manage projects. The 105th Committee of Conference on Energy and Water Resources directed DOE to investigate establishing a project review process. Many of the findings and recommendations in this series of reports identified the need for improved planning in the early project stages (front-end planning) to get the project off to the right start, and the continuous monitoring of projects by senior management to make sure the project stays on course. These reports also stressed the need for DOE to act as an owner, not a contractor, and to train its personnel to function not as traditional project managers but as knowledgeable owner's representatives in dealing with projects and contractors.

The NRC Committee for Oversight and Assessment of Department of Energy Project Management determined that it would be helpful for DOE to sponsor a forum in which representatives from DOE and from leading corporations with large, successful construction programs would discuss how the owner's role is conducted in government and in industry. In so doing, the committee does not claim that all industrial firms are better at project management than the DOE. Far from it-the case studies represented at this forum were selected specifically because these firms were perceived by the committee to be exemplars of the very best practices in project management. Nor is it implied that reaching this level is easy; the industry speakers themselves show that excellence in project management is difficult to achieve and perhaps even more difficult to maintain. Nevertheless, they have been successful in doing so, through constant attention by senior management.

READ FREE ONLINE

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!