Appendix C
Engineered Management Systems and BCI

Engineered Management Systems

The U.S. Army’s Engineer Research and Development Center, Construction Engineering Research Laboratory (ERDC-CERL) has developed Engineered Management Systems (EMS), a family of tools that aid in assessing the condition of facilities and allocating funding. Each EMS provides a functional manager with automated procedures and tools to support the planning, programming, and budgeting of infrastructure facilities maintenance and repair. The fundamental idea of an Engineered Management System is sustainment, including timely repair or replacement of system components, to meet the design or expected service life, thereby avoiding untimely and excessive recapitalization costs.

The Navy has used EMS PAVER for many years to manage all naval airfield pavements, and the system is being put in place to manage roads and parking lots. The EMS ROOFER and RAILER are in use at some activities to manage roofs and railroad tracks.

EMS BUILDER and WHARFER, which will be applied to buildings and waterfront structures, respectively, are in development and beta application testing. EMS UTILITIER is planned for eventual development. All EMSs provide a procedure for calculation and use of condition indexes to assess the condition of the facility components and systems.

The EMS condition index is mathematically determined from identified distress types germane to the component section being assessed. Distresses are objectively defined flaws in the component section. Deduct values are amounts deducted from the theoretical component condition index of 100 for a given type, quantity, and size of distress. Deduct values for each EMS distress type have been determined through research.

Building Condition Index (BCI)

In BUILDER the CI for buildings is developed from a roll up of system component sections1 to component, to system, and finally to the building’s Condition Index (BCI). The CI provides an equivalent granularity to the traditional FCI in that the roll-up BCI is applicable to a single facility or structure.

1  

The component section is the management unit of the EMS structure. Component sections are system elements that share common material, age, or condition. Component sections become logical maintenance management units.

Suggested Citation:"Appendix C Engineered Management Systems and BCI." National Research Council. 2005. Key Performance Indicators for Federal Facilities Portfolios: Federal Facilities Council Technical Report Number 147. Washington, DC: The National Academies Press. doi: 10.17226/11226.
×

The BCI is an objective rating of the condition of the component, system, or facility and is not influenced by the personal bias of the individual inspector who specifies the scope of a corrective action. The disciplined nature of the distress survey requires the inspector to identify observed distresses from a finite list of well-defined possibilities. The inspector records a severity and density range for each observed distress from the appropriate list of predefined possibilities. The EMS determines the condition index from the sum of the modified deduct values associated with the observed distress. As a result, EMS condition indices are consistent and repeatable with little variation among trained inspectors and are not influenced by subjectively determined corrective action costs.

The EMS BCI also provides the needed metric to assist in maintenance planning. Quality maintenance planning requires knowing where and when to make a sustainment, restoration, and modernization (SRM) expenditure and how much money should be allocated. EMS directly calculates a BCI and then estimates costs for SRM expenditures as a function of component replacement or repair cost and BCI. Building components are inventoried and cost models are assembled from industry standard sources. Based on research-derived algorithms using BCI, estimated costs for component-section repair or replacement are calculated according to work rules as a percentage of component-section replacement value or predetermined unit costs.2 EMS uses a family of cost calculations that are specific to facility system, component, or component-section. Using these costs, BUILDER identifies a list of work items. Each work item is associated with an EMS-calculated component-section BCI. Each inventoried component-section that is below a user-defined standard condition is a candidate for corrective action.

2  

Both PAVER and RAILER set up work policies for correcting distresses or defects. Unit costs for these activities are derived from job order contracts, indefinite delivery contracts, or other sources. ROOFER also addresses distress fixes.

Suggested Citation:"Appendix C Engineered Management Systems and BCI." National Research Council. 2005. Key Performance Indicators for Federal Facilities Portfolios: Federal Facilities Council Technical Report Number 147. Washington, DC: The National Academies Press. doi: 10.17226/11226.
×
Page 42
Suggested Citation:"Appendix C Engineered Management Systems and BCI." National Research Council. 2005. Key Performance Indicators for Federal Facilities Portfolios: Federal Facilities Council Technical Report Number 147. Washington, DC: The National Academies Press. doi: 10.17226/11226.
×
Page 43
Next: Appendix D Space Utilization Index »
Key Performance Indicators for Federal Facilities Portfolios: Federal Facilities Council Technical Report Number 147 Get This Book
×
Buy Paperback | $29.00 Buy Ebook | $23.99
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF

More than 30 federal departments and agencies with a wide range of missions and programs manage large inventories of facilities, also called portfolios. These portfolios range in size from a few hundred to more than a hundred thousand individual structures, buildings, and their supporting infrastructure. They are diverse in terms of facility types, mix of types, and geographic dispersal. For federal senior executives, facilities portfolio-related decisions revolve around the allocation of resources (staff, funding, time) for acquisition, renovation, operation, repair, and disposition of facilities. To make informed decisions, senior executives require information that will allow them to answer such questions as:

  • What facilities do we have?
  • What condition are they in?
  • What facilities are needed to support the organization's missions?

This study lays out a framework for developing and evaluating trends in facilities portfolio conditions, investments, and costs and identifies a set of key indicators that can be used to track performance over time. Some of the indicators are currently in use in some federal agencies; others will need to be developed.

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!