Below is the uncorrected machine-read text of this chapter, intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text of each book. Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
9guidance can be obtained from the FHWA Con- tract Administration Core Curriculum Manual,45 which recognizes that it is unrealistic to expect con- struction projects to be built without deviating from the project plans. The manual provides that estab- lishing a strict set of rules to govern federal aid pol- icy in contract changes is not practical since the rules would need to recognize that contract changes involve unique circumstances. Generally the FHWA manual classiï¬es change orders by plan changes, speciï¬cation changes, and changes in cost and time. Federal policy requires that proposed major extra work or major changes in the contract plans be approved in advance, unless it is an emergency. Major change or major extra work means a change that would signiï¬cantly affect the cost of the project to the federal government, or alter the limits, character, or scope of work. Early coordination between the state transporta- tion agency and FHWA is essential to reviewing and handling change orders. FHWAâs review of proposed change orders includes federal aid eligibility, impacts on the âoriginal scope of work,â46 basis of payment, and time adjustments. The manual provides that in cases where the proposed work is beyond the âoriginal scope of work,â the FHWA Division Ofï¬ce must determine whether the additional work is a modiï¬cation of the original scope or a signiï¬cant change that would beneï¬t from competitive bidding. âThe indi- vidual circumstances associated with the magni- tude of the work and quality of the change, as well as the cumulative impact upon the whole project, should be reviewed.â47 Among the considerations are: s (AVE THE CONTRACT WORK ELEMENTS CHANGED s (OW DOES THE ADDITIONAL WORK IMPACT QUANTI- TIES AND COST s $O THE PROPOSED CHANGES IMPACT THE COMPLEX- ITY OF THE WORK s 7HAT IS THE CUMULATIVE IMPACT ON THE PROJECT s 7OULD THERE BE A SUBSTANTIAL BENElT TO THE public for the proposed change of work to be BID OUT48 VI. REPRESENTATIVE STATE REQUIREMENTS ON CONTRACT MODIFICATIONS A. Competitive Bidding Statutes A review of state case law on contract modiï¬cations reï¬ects that in certain deï¬ned situations, contract modiï¬cations do not require competitive bidding. The following statutory rules and principles can be ascer- tained from a review of state case law and statutes. Some states have strict monetary threshold lim- its for change orders that trigger competitive bid- ding. In Oklahoma, for example, the Oklahoma stat- utes provide that advertising for competitive bidding is required for change orders on contracts of $1 mil- lion or less where the change order exceeds 15 per- cent of the original contract amount, and advertis- ing for competitive bidding is required for change orders on contracts exceeding $1 million where the change order exceeds $150,000 or 10 percent cumu- lative increase in the original contract amount.49 South Dakota statutes provide an excellent example of state statutory requirements that gov- ern contract modiï¬cations. S.D. Codiï¬ed Law 5-18B- 19 (2015) provides as follows: Any amendment or change order to an existing contract for construction, reconstruction, or remodeling of a public improvement, does not need to be bid if: (1) the contract contains unit prices for the same type or class of work; (2) the change or extra work is necessitated by circum- stances related to soils, utilities, or unknown conditions directly affecting the performance of the work that were not reasonably foreseeable at the time the underlying contract was let and the change or extra work is necessary to the completion of the public improvement. In South Dakota, since most transportation project contracts are unit price contracts, the changed or mod- iï¬ed work must be the same type or class or work spelled out in the contract. If the contract is not a unit price contract, then the statute requires that the change is necessary for completion of the project and could not have been reasonably foreseeable at time of contract letting. For example, in Thomas Bozied v. City of Brookings, South Dakota,50 the case was remanded for retrial to determine whether the change order for additional parking lot work required for tenant improvements was necessary to complete the project and was unforeseen at the time of contract letting. Another example of statutory restrictions on change orders is the Virginia Code in Title 43, which provides as follows: § 2.2-4309. Modiï¬cation of the contract. 45 FHWA Contract Administration Core Curriculum Manual, Oct. 2014 (entire manual may be downloaded at http://www.fhwa.dot.gov/programadmin/contracts/coretoc. cfm (last visited Feb. 26, 2015)). 46 Id. at 153. 47 Id. 48 Id. 49 OKLA. STAT. tit. 61, § 121 (2014). 50 2001 SD 150, 638 N.W.2d 264 (2000).
10 A. A public contract may include provisions for modiï¬cation of the contract during performance, but no ï¬xed-price contract may be increased by more than twenty-ï¬ve percent of the amount of the contract or $50,000, whichever is greater, with- out the advance written approval of the Governor or his des- ignee, in the case of state agencies, or the governing body, in the case of political subdivisions. In no event may the amount of any contract, without adequate consideration, be increased for any purpose, including, but not limited to, relief of an offeror from the consequences of an error in its bid or offer. ⦠C. Nothing in this section shall prevent any public body from placing greater restrictions on contract modiï¬cations. Thus, VDOT has some statutory restrictions on the scope of contract modiï¬cations that can be approved by the Governor, but in this instance there is at least an implicit threshold where a decision could be made to competitively procure additional work. B. AASHTO Guide Speciï¬cations and Typical State Guidelines and Speciï¬cations The AASHTO Guide Speciï¬cations for Highway Construction contains sample changes clause provi- sions that many state transportation agencies have adopted or modiï¬ed in their contracts. The guide speciï¬cations recognize the need to make changes in the contract for time and cost of performance. The permissible changes include differing site condi- tions, signiï¬cant changes in the character of the work, suspensions of work ordered by the engineer, and extra work. The speciï¬cations provide: 104.02 Contract Revisions A. General. The Agency reserves the right to revise the con- tract at any time. These revisions do not invalidate the con- tract or release the surety, and the Contractor agrees to complete the contract as revised. Do not proceed with the work without the Engineerâs written authorization. Upon receiving written approval, proceed immediately with the revised work. The Agency will only consider requests from the Contractor for a revision to the contract amount or time if the Contrac- tor ï¬rst notiï¬es the Engineer as speciï¬ed in Subsection 104.03. If the Engineer determines that a revision is necessary, the Agency will revise the contract time as speciï¬ed in Subsec- tion 108.06 and will pay for the revised work at the contract unit bid prices unless the Contractorâs cost of production or the character of the work is materially changed, in which case the Agency may revise the contract as speciï¬ed in Sub- section 109.04. The Agency will not pay for lost or antici- pated proï¬ts resulting from a revision to the contract. If the Engineer decides that a potential contract revision identiï¬ed by the contractor is not necessary, and the Con- tractor does not agree with the Engineerâs decision, the Con- tractor may pursue a claim as speciï¬ed in Subsection 105.18. B. Differing Site Conditions. If either of the following condi- tions is encountered during the progress of the work, immediately notify the Engineer of the conditions as speci- ï¬ed in Subsection 104.03 before they are disturbed and before performing or continuing with the affected work. 1. A subsurface or latent physical condition differing mate- rially from those indicated in the contract; or 2. An unknown physical condition of an unusual nature, dif- fering materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract. C. Signiï¬cant Changes in the Character of Work. The Engi- neer may alter the contract quantities, the work, or both as necessary to satisfactorily complete the project. If such alterations signiï¬cantly change the character of the work, the Agency will make appropriate adjustments in the con- tract as speciï¬ed in Subsections 108.06 and 109.04. Consider either of the following to be a âsigniï¬cant changeâ: 1. When the character of the work as altered differs materi- alliy in kind or nature from that involved or included in the original proposed construction; or 2. When the quantity of a major item of work is increased in excess of 125 percent or decreased below 75 percent of the original contract quantity. Any allowance for an increase in quantity applies only to that portion in excess of 125 per- cent of original contract item quantity, or in the case of a decrease below 75 percent, to the actual amount of work performed. Before performing signiï¬cantly changed work, reach agree- ment with the Agency concerning the basis for the adjust- ment as speciï¬ed in Subsections 109.04 and 108.06. If the alterations do not signiï¬cantly change the character of the work speciï¬ed in the contract, the Agency will pay for the altered work at the contract unit price. If the Contractor disagrees as to whether an alteration con- stitutes a signiï¬cant change, use the notiï¬cation procedures speciï¬ed in Subsection 104.03. D. Suspension of Work Ordered by the Engineer. If the Engi- neer suspends or delays all or any portion of the work for an unreasonable period of time (not originally anticipated, cus- tomary or inherent to the construction industry), and the Contractor believes that additional compensation, contract time, or both is due because of the suspension or delay, the Contractor shall notify the Engineer as speciï¬ed in Subsec- tion 104.03. The Engineer will evaluate the Contractorâs request. If the Engineer agrees that the cost, time or both required for the performance of the contract has increased due to the suspe- nion or delay and the suspension or delay was caused by conditions beyond the control of and not the fault of the Contractor, its suppliers, or subcontractors at any approved tier and not caused by weather, the Engineeer will revise the contract as speciï¬ed in Subsections 108.06 and 109.04. The Agency will not grant or consider revisions based on an Engineer-ordered suspension 1. without timely written notice as speciï¬ed in Subsection 104.03; 2. to the extent that performance would have been sus- pended or delayed by any other cause;