National Academies Press: OpenBook
« Previous: G: NUCLEAR CRITICALITY
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

Appendix H Previous Decontamination and Decommissioning Efforts

This appendix summarizes information from other decontamination and decommissioning (D&D) efforts that the committee examined and identifies lessons learned. The only gaseous diffusion plant (GDP) that has undergone D&D is the Capenhurst GDP in the United Kingdom (see, for example, Baxter and Bradbury, 1991; Clements, 1994a,b; Spencer, 1988). The committee examined this program in detail as discussed below. The committee also benefited from briefings on the D&D of sites that were used to produce nuclear materials and components for the Manhattan Project and to fabricate nuclear fuel. Two D&D projects were reviewed in particular to glean any insights for the planning and execution of the D&D of the U.S. GDPs: the Formerly Utilized Sites Remedial Action Program and the Apollo Decommissioning Project (Kingsley, 1994). The first is an ongoing project to decontaminate and decommission facilities associated with the Manhattan Project (Hovey, 1994). The Apollo project involved decommissioning a fuel-fabrication complex that handled both enriched uranium and plutonium. Because the scope of these projects varied substantially from that of the D&D of the U.S. GDPs (these projects included substantial remedial action, such as cleanup of soils and groundwater), their costs were not useful for evaluating the GDP D&D costs.

The committee believes that the greatest opportunity to minimize the cost of D&D occurs during planning. Timely decisions on key issues are essential to execute the work efficiently within budget and schedule.

Capenhurst Gaseous Diffusion Plant

Description of Capenhurst Facility

The Capenhurst GDP enrichment cascade consisted of 4,808 stages in series, each containing a converter housing the diffusion barrier material that separates uranium-235 (235U) and uranium-238 (238U) isotopes, a compressor and associated drive motor, a cooler, and interstage piping and valves. The cascade components were housed in a single process building 1,200 m long by 150 m wide. The stages were on the ground floor, and auxiliary equipment, such as electrical and heating, ventilation, and air conditioning (HVAC) systems, were located on the second floor. There were seven different sizes of converters and compressor drive motors, the latter ranging in size up to 300 hp. The cascade equipment was arranged in process cells containing 8 to 12 stages each.

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

Uranium feed from reactor returns was introduced into the cascade in 1962, resulting in contamination of the low-enrichment stages with technetium-99 (99Tc) and neptunium-237 (237Np). The presence of 99Tc in particular made the decontamination effort more difficult.

Approach

Before shutting down the plant, radiological and criticality data were gathered for use in planning and executing the dismantling, decontamination, and disposal operations. Gaseous decontamination using chlorine trifluoride (ClF3), a fluorinating agent, was used to remove the bulk of the residual uranium deposits. Detailed radiological surveys were performed to locate these deposits.

A detailed D&D plan was developed. The initial phase involved cutout, removal, sealing, and outdoor storage of the cascade components. This removal allowed a part of the process building housing the cascade to be demolished and the land returned to greenfield status. Other parts of the process building were reused to house equipment for size reduction of components, chemical decontamination, and melting of metal components and pieces that were difficult to decontaminate.

Development Activities

A great deal of effort went into researching and developing cost-effective techniques for decommissioning. The key principle underlying this development work was to look outside the nuclear industry for off-the-shelf equipment that, with or without modification, would meet the D&D program needs.

The development activities performed during this period addressed the following technical issues:

  • selection of a cost-effective and safe means of disassembling the plant;
  • suitable size-reduction techniques and compatible ventilation and filtration systems;
  • decontamination processes to deal specifically with transuranic and fission products, copper, and other metals;
  • engineering safety in process equipment; and
  • ensuring compatibility of waste streams with regulatory requirements.

One of the main objectives of these development activities was to minimize D&D waste by maximizing recycle for unrestricted reuse.

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Decontamination and Disassembly

The decontamination and disassembly process consisted of the following activities:

  • gaseous decontamination, prior to plant shutdown, to convert solid uranium deposits, primarily uranyl fluoride (UO2F2), to volatile fluoride compounds;
  • plant characterization to identify and quantify residual deposits of radioactive materials;
  • removal of nonradioactive hazardous materials such as asbestos and polychlorinated biphenyls (PCBs);
  • removal and interim storage of plant equipment and removal of cell structures;
  • size reduction of components;
  • aqueous chemical decontamination;
  • melting difficult-to-decontaminate metal parts;
  • removal of process and ancillary building structures; and
  • disposal of radioactive and hazardous waste.

Many items, such as structural steel and concrete, required only minimal decontamination.

Gaseous Decontamination to Remove UO2F2

Gaseous ClF3 was circulated through the cascade prior to shutdown and dismantlement to convert solid deposits to volatile fluorides (e.g., converting UO2F2 to uranium hexafluoride, UF6) prior to opening up the system. Gaseous decontamination removed an estimated 80 percent of the UO2F2 deposits, and substantially reduced the probability of a criticality accident during subsequent D&D operations. Both HVAC and physical methods were used to protect the workers and the environment.

Following gaseous decontamination, further cleanup and pretreatment operations were carried out on the static plant to locate and deal with any significant pockets of contamination that remained to permit safe and cost-effective intrusions into the plant during the dismantling campaigns. Cleanup techniques included vacuuming, ridding, and machining.

Characterization

The initial characterization to identify and quantify residual radioactive contaminants was performed following gaseous decontamination. Gamma spectroscopy and neutron activation were

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

used to characterize uranium deposits. Counters and scintillation monitors were used to identify 99Tc and 237Np deposits.

The characterization provided data on the magnitude and location of alpha (uranium) and soft beta (technetium) radionuclides throughout the plant. Nonintrusive gamma spectroscopy and neutron activation measurements provided the necessary data on 237Np and 235U.

Removal of Nonradioactive Hazardous Materials

Hazardous materials, such as asbestos, PCBs, lubricants, and laboratory chemicals, were removed and disposed of using conventional technologies, including land burial for asbestos and incineration for PCBs.

Equipment and Cell Structures Disassembly

The initial phase of dismantling and disassembly consisted of cutting out, removing, and storing compressors, coolers, valves, large-diameter pipe, and large-process stage units.

Specialized workshops were built for component stripping and dry cleaning. Protection of personnel was achieved by effective ventilation and extensive alpha-in-air monitoring throughout the facility. A criticality detection system was installed, and strict criticality control procedures were applied at each stage of the dismantling process.

The low-enrichment stages of the cascade had been fed with reactor recycled UF6 during operations for civilian purposes. This material included small but significant quantities of transuranic elements and fission products. Safe handling of contamination such as 237Np and 99Tc had to be ensured during dismantling activities.

Following process equipment removal, the remaining cell enclosures were demolished. The materials were sold as clean scrap in the commercial metals market. The building shell was removed from about one-half of the total structure. The floors were scabbled and removed, returning that part of the structure to greenfield site status.

Interim Storage of Plant Components

Before the decontamination plant was available, a large section of the process building (including the building structure and floor slab) was completely cleared to make way for construction of a new centrifuge enrichment facility. The diffusion plant cascade equipment removed was stored outdoors for up to 9 years until the new decontamination facility was available. Approximately 6,000 metric tons of contaminated components were stored, including 700 large stages weighing up to 7 metric tons each.

Size Reduction

Large components, such as converter shells, piping, and compressors were reduced in size and weight to meet requirements of the decontamination plant and the melter. Cold cutting was preferred over hot cutting for aluminum components, because cold cutting does not generate

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

fumes or airborne aluminum oxide fines, thereby reducing the need for costly HVAC systems. Robotic plasma cutting was used for size reduction of large aluminum converter shells, and remotely controlled oxyacetylene methods were used for cutting steel converter shells and other steel components. A total of 1,400 seam-welded steel shells were cut using the latter method.

The HVAC system was divided into two stages. The first stage consisted of a self-cleaning filter unit in which intermittent reverse air pulses dislodged the dust that was collected in bags at the base of the unit. The balance of particulate matter was captured in a high-efficiency particulate air filter system. The effluent air stream was monitored by stack monitors before being released to the atmosphere. Overall filtration efficiency was greater than 99.997 percent.

Chemical Decontamination

A wet decontamination process was used to remove uranium contamination down to free-release levels. While chemical treatment for the removal of uranium and its daughter products is a well-established process, technetium is difficult to remove effectively. A means of removing 99Tc had to be developed before effective disposal routes could be determined. Following extensive laboratory and pilot plant investigation, a full-scale decontamination plant was built in 1989. The flowsheet was based on achieving plant discharges having a negligible impact on the environment, and on satisfying the United Kingdom statutory regulations for recycling scrap metals to the open market. Most of the uranium was removed with citric acid, followed by sulfuric acid, disodium citrate, and a hot water wash. The majority of the 99Tc and 237Np ended up in the citric acid (Anderson and Faulkner, 1989).

Separate processing plants were used to clean up the spent citric acid, sulfuric acid, and disodium citrate decontamination liquors. Ion exchange removed contaminants from the process solutions, substantially reducing the volume of waste. The ion exchange resins were encapsulated in concrete and sent to the low-level waste burial ground at Drigg.

Strict criticality control was maintained, with detectors placed at key points in the decontamination facility. The activity of each individual piece was monitored after decontamination to ensure it met the applicable release criteria.

Melting

A melter was used to handle metallic components that were difficult or impossible to decontaminate cost-effectively by chemical means. The melter had several functions:

  • removing impurities from aluminum, steel, and other metals to increase resale value;
  • homogenizing the radioactivity in materials with varying degrees of contamination, shapes, and sizes; and
  • reducing waste volume.
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Ancillary Structures Removal

A number of ancillary buildings and structures were demolished, including 11 large natural draft cooling towers, their pump houses, and an electrical substation. Including the floor slab, this operation produced 46,000 metric tons of clean concrete rubble for off-site disposal.

Waste Treatment and Disposal

Metallic materials recovered from the plant were categorized according to their potential for sale to the commercial metals market as follows:

  • clean scrap;
  • contaminated scrap economical to decontaminate to de minimis level; and
  • contaminated scrap uneconomical to decontaminate to de minimis level.

Clean scrap, such as cell cubicle structures, base plates, and some motors, was sold directly to the metals market. Scrap that was economical to decontaminate to de minimis levels was reduced in size, decontaminated and/or melted to homogenize the contamination, and sold. This approach was used for the bulk of the steel, copper, and aluminum components. Scrap that was uneconomical to recover, such as small-bore pipe and instruments, was dispatched to the low-level radioactive waste site at Drigg.

Approximately 99 percent of the material removed from the Capenhurst plant was recycled to the commercial markets, including bulk concrete as well as metals.

Personnel Protection During Decommissioning

Personnel protection was achieved through multiple methods:

  • strict criticality control with criticality detectors on selected operations;
  • extensive alpha-in-air monitoring; and
  • special HVAC systems with high-efficiency particulate air filters.
Criticality Control

Criticality control was achieved by a number of actions:

  • removing as much uranic contamination as possible during the size reduction, decontamination, and preparation stages;
  • designing the plant to minimize the likelihood of criticality incidents; and
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
  • using batch metering techniques to control spent citric acid movements and concentrations of 235U.
Air Monitoring

Static personnel air samples and film badges were used throughout the project. Whole body monitoring was performed twice yearly for each D&D worker. No special dispensation or relaxation of exposure limits was given for this work.

Very low-levels of exposure were experienced by the work force. The mean total dose for 1993 was 0.03 mSv. These low-levels were achieved by sound engineering design, safe operational practices, and a methodical approach to safety.

Similarities And Differences Between Capenhurst And The U.S. Enrichment Plants

Although the Capenhurst plant was substantially smaller than the U.S. GDPs, they have many similarities:

  • similar process flowsheets and cascade arrangement;
  • multistory, steel-frame and concrete buildings with transite siding;
  • stages grouped into cells;
  • Freon-cooled stages;
  • same species of radiological contamination, including uranium (from depleted to highly enriched), 99Tc, and 237Np;
  • large quantities of hazardous materials, such as asbestos, PCBs, and Freon®;
  • mixture of aluminum and nickel-plated stage components;
  • steam-heated autoclaves for feed vaporization; and
  • purge cascade for removal of light gases.

The principal differences between Capenhurst and the U.S. GDPs are the following:

  • Physical size and separative work capacity of the U.S. plants are substantially larger.
  • Most of the large interstage piping at Capenhurst was aluminum, whereas U.S. GDPs use nickel-plated steel exclusively.
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
  • U.S. GDPs have a larger number of support facilities to decontaminate and decommission than Capenhurst had. For example, the D&D scope at the Oak Ridge and Portsmouth GDPs includes centrifuge enrichment facilities. However, these were not included in the cost estimates under review by the committee.
  • Capenhurst cascade equipment was located on the first floor of the process building; this equipment is located on the second floor in the U.S. plants.

Quantity Comparisons Of Capenhurst And The Oak Ridge GDP

Since the technology employed in the Capenhurst plant was very similar to that in the U.S. enrichment plants, a comparison of various quantities associated with them provides a means to estimate the relative cost of cleaning up the U.S. facilities. Selected quantities and design features of the Capenhurst and the Oak Ridge GDPs are shown in Table H-1. A breakdown of the quantities of various metals at Capenhurst and the three U.S. GDPs is presented in Table H-2. Table H-3 presents the ratio of Oak Ridge to Capenhurst GDP for total metals contained in the cascade, building footprint, total area under roof, weight of largest converter, and peak electric power.

A direct comparison of plant separative work capacities was not possible because the Capenhurst capacity is considered to be proprietary information. However, enrichment plant capacity (in separative work units [SWUs]/year) is nearly directly proportional to power consumption because most plant electric power usage is to drive the UF6 compressors. For example, specific power consumption is reported as 2,433 Kwh/SWU for U.S. enrichment plants and 2,538 Kwh/SWU for the Eurodif plant in France, although these facilities have substantially different stage designs (Kroschwitz and Howe-Grant, 1993). Other things being equal, total UF6 flow through the cascade is proportional to power and plant capacity and would also be indicative of equipment size and its associated D&D cost. Peak power delivered to the Oak Ridge GDP facilities was 1,725 MW, compared with 300 MW for Capenhurst, a ratio of 5.7.

Another consideration is that 19.7 percent of the total Capenhurst D&D cost was for technology development, which is excluded from the Ebasco cost estimate. Subtracting the cost of technology development would reduce the total Capenhurst cost from $160 million to $128 million. The cost of planning for the Capenhurst D&D was 11.6 percent of the total cost. This should not be appreciably larger for a large plant than a smaller plant when the two plants have similar systems, structures, and contaminants. Similarly, the cost of selecting the most cost-effective D&D techniques should not be substantially different, particularly when there is a substantial experience base available from Capenhurst and other successful D&D projects.

There are other factors that may increase or decrease the cost of D&D of the U.S. GDPs relative to Capenhurst. Differences in the management and contracting approach, wage rates, labor productivity, and regulatory requirements are some of the important considerations. Although the Capenhurst D&D was a government program sponsored by the Central Electricity Generating Board and the United Kingdom's Ministry of Defense, there was apparently a very high commitment to cost control, as evidenced by the relatively small number of management

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

TABLE H-1 Comparison of Capenhurst and Oak Ridge GDP Design Characteristics

Plant Design Characteristic

Oak Ridge

Capenhurst

Number of buildings/structures

82

19

Process buildings

 

 

Number

5

1

Total area under roof (acres)

116.3

31

Total floor space (acres)

250.6

64.4

Length/width (ft)

 

2,880/480

Structure type

Steel frame/concrete with transite siding

Steel frame/concrete with transite siding

Number of stages in cascade

5,098

4,808

Weight of largest converters (tons)a

51

7

Total quantity of metal, not including structural steel (tons)

276.8

27.1

Largest compressor motors (hp)

3,300

300

Maximum electric power (MW)

1,725

300

Materials of construction (cascade)

 

 

Process pipingb

Steel/aluminum

Aluminum/steel/nickel

Convertersc

Aluminum/steel

Aluminum/steel/nickel

Compressor balding

Aluminum

Aluminum

a Because the largest Capenhurst converter had an integral compressor, the weight of the converter shown for the Oak Ridge GDP includes the converter and the compressor as well.

b The Oak Ridge GDP has a limited quantity of aluminum for small piping. Capenhurst used a limited quantity of nickel-plated steel for large piping.

c Oak Ridge GDP has aluminum for the small converters. Capenhurst used nickel-plated steel for the large converters. All steel is nickel plated. Converter barrier material is primarily nickel.

SOURCE: Clements (1993; 1994a,b); DOE (1991); briefings to committee at site visits.

personnel (Clements, 1994b). The management and contracting approach appears to include a much larger portion of the total costs associated with performing the work rather than managing it.

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

TABLE H-2 Comparison of Capenhurst and U.S. GDP Material Quantities (thousands of tons)

Material

Oak Ridge

Portsmouth

Paducah

3 U.S. GDPs

Capenhurst

Aluminum

8.5

7.6

6.1

22.2

8.3

Ferrous metals/steel

103.7

91.4

74.0

269.1

14.2a

Nickel

22.1

19.8

15.9

57.8

0.4

Copper and brass

17.6

15.0

11.7

44.3

--b

Monel

1.7

1.5

1.2

4.4

--b

Miscellaneous metals

123.2

105.0

81.9

310.1

4.5

Total quantity

276.8

240.3

190.8

707.9

27.4

a For Capenhurst, nonstructural steel was assumed to be 40 percent of the total quantity of steel; total quantity of steel (building structure plus steel components) in the Capenhurst plant was 35,500 metric tons (Clements, 1994b).

b Included in miscellaneous metals.

SOURCE: Clements (1993; 1994a,b); DOE (1991); briefings to committee at site visits.

TABLE H-3 Quantity Ratios of the Oak Ridge GDP to the Capenhurst GDP

Quantity

Oak Ridge

Capenhurst

Ratio

Total metal quantity (tons)

276,800

27,100

10.0

Full density volume (ft3)a

1,208,117

178,742

6.8

Total area under roof (acres)

116.3

31

3.8

Total floor space (acres)

250.2

64.4

3.9

Weight of largest converter (tons)b

51

7

7.1

Peak electric power (MW)

1,725

300

5.7

a Calculated from Table H-2 by dividing the weight of each type of metal by its density and summing over all types.

b Because the largest Capenhurst converter had an integral compressor, the weight of the converter shown for the Oak Ridge GDP includes the converter and the compressor as well.

SOURCE: Clements (1993; 1994a,b); DOE (1991); briefings to committee at site visits.

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

References

Anderson, R.W., and R.L. Faulkner. 1989. British Nuclear Fuels plc Process for Decontamination and Decommissioning of Capenhurst Gaseous Diffusion Plant and Information from the International Conference on Decommissioning of Major Radioactive Facilities. K/QT-254. Washington, D.C.: Oak Ridge Gaseous Diffusion Plant for U.S. Department of Energy (DOE).


Baxter, S. G. and P. Bradbury. 1991. BNFL's [British Nuclear Fuel Limited's] Capenhurst Diffusion Plant Decommissioning. August. Chester, U.K.: BNFL.


Clements, D.W. 1993. BNFL Capenhurst Works. Minimizing Nuclear Waste by Special Recovery Techniques. Presented at the 4th International Environmental and Waste Management Conference held April 18–21, 1993 in Knoxville, Tennessee.

Clements, D. 1994a. Capenhurst Diffusion Plant Decommissioning, BNFL, Enrichment Division. Presented to the Committee on Decontamination and Decommissioning of Uranium Enrichment Facilities at the National Academy of Sciences, Washington, D.C. March 28, 1994.

Clements, D. 1994b. Personal communication to committee member Ray Sandberg, November 6, 1994.


DOE. 1991. Environmental Restoration of the Gaseous Diffusion Plants. Technical Summary Document, vol. 1. Washington, D.C.: Ebasco Environmental and Main-1893 for the DOE. October.


Hovey, G. 1994. D&D Project Management Perspectives From Formerly Utilized Sites Remedial Action Program (FUSRAP). Presented to the Committee on Decontamination and Decommissioning of the Uranium Enrichment Facilities at the National Academy of Sciences, Washington, D.C., June 16, 1994.


IMF (International Monetary Fund). 1993. International Financial Statistics Yearbook. Washington, D.C.: IMF.


Kingsley, R.S. 1994. Apollo Decommissioning Project, Decommissioning a LEU/HEU [Low Enriched Uranium/Highly Enriched Uranium] Fuel Fabrication Complex, Babcock and Wilcox Nuclear Environmental Services, Inc. Presented to the Committee on Decontamination and Decommissioning of the Uranium Enrichment Facilities, National Academy of Sciences, Washington, D.C., June 15–16, 1994

Kroschwitz, J.I., and M. Howe-Grant, eds. 1993. P. 175 in Kirk Othmer Encyclopedia of Chemical Technology, 4th Edition. New York: Wiley.

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×

Spencer, A.N. 1988. Decommissioning and Decontamination of Enrichment Facilities. Presented at the 15th Annual Meeting of the World Nuclear Fuel Market, held in Seville, Spain, October 16–19, 1988.

Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 244
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 245
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 246
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 247
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 248
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 249
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 250
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 251
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 252
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 253
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 254
Suggested Citation:"H: PREVIOUS DECONTAMINATION AND DECOMMISSIONING EFFORTS." National Research Council. 1996. Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities. Washington, DC: The National Academies Press. doi: 10.17226/5114.
×
Page 255
Next: I: WASTE TREATMENT »
Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities Get This Book
×
 Affordable Cleanup?: Opportunities for Cost Reduction in the Decontamination and Decommissioning of the Nation's Uranium Enrichment Facilities
Buy Paperback | $85.00 Buy Ebook | $69.99
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF

The Energy Policy Act of 1992 called on the National Academy of Sciences to conduct a study and provide recommendations for reducing the costs of decontaminating and decommissioning (D&D) the nation's uranium enrichment facilities located at Oak Ridge, Tennessee; Raducah, Kentucky; and Portsmouth, Ohio. This volume examines the existing plans and cost estimates for the D&D of these facilities, including such elements as technologies, planning and management, and identifies approaches that could reduce D&D costs. It also assesses options for disposition of the large quantities of depleted uranium hexafluoride that are stored at these sites.

READ FREE ONLINE

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    Switch between the Original Pages, where you can read the report as it appeared in print, and Text Pages for the web version, where you can highlight and search the text.

    « Back Next »
  6. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  7. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  8. ×

    View our suggested citation for this chapter.

    « Back Next »
  9. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!