Below are the first 10 and last 10 pages of uncorrected machine-read text (when available) of this chapter, followed by the top 30 algorithmically extracted key phrases from the chapter as a whole.
Intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text on the opening pages of each chapter.
Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
Do not use for reproduction, copying, pasting, or reading; exclusively for search engines.
OCR for page 88
88 A Guidebook for the Evaluation of Project Delivery Methods
Document
Results
Yes
No Select project
Qualitative Approach: Quantitative Approach: Cost/
Selection? delivery method;
Risk-allocation matrix schedule impact
Document Results
Figure 6.1. Overview of the risk-based qualitative and quantitative approaches.
was found that projects in which more attention was paid to risk analysis fared better than other
projects in terms of meeting budget and schedule goals.
The following sections describe the qualitative and quantitative phases of the Tier 3 approach
in more detail.
Qualitative Analysis
Figure 6.3 shows the risk-based approach superimposed on the project lifecycle. The most
likely times to decide on the project delivery method are at the end of the Conceptual Design
Phase or during the Preliminary Engineering Phase. If a project goes into the Final Design Phase
without a decision on a project delivery method, the agency will lose the opportunity to effec-
tively use alternative delivery methods and will be limited to the traditional DBB approach. At
the end of the Conceptual Design Phase, the agency usually has not done a detailed risk analy-
sis. If an agency is unable to select a project delivery method upon completion of the Tier 1 and
Tier 2 approaches, it would need to conduct a preliminary risk analysis in order to make an
informed choice of project delivery method.
The result of this preliminary risk analysis is a risk-allocation matrix. The risk-allocation
matrix has become an industry standard for legal teams when authoring alternative contracts for
large infrastructure projects. For example, a risk-allocation matrix was a first step in creating the
contract for the T-REX multimodal DB project in Colorado. Table G-1 in Appendix G (avail-
able on the TRB website at http://trb.org/news/blurb_detail.asp?id=10054) presents a generic
risk-allocation matrix that can be used for accomplishing the qualitative analysis. It should be
noted that the matrix of Table G-1 will most likely consist of only two (and in rare cases maybe
three) delivery methods because the completion of the Tier 1 and Tier 2 approaches should
0.1
0.08
Probability
0.06
0.04
0.02
0
2500
2700
2900
3100
3300
3500
3700
3900
Total Project Cost
(Year of Expenditure $M)
Figure 6.2. Distribution of
project costs.
OCR for page 88
Tier 3--Optimal Risk-Based Approach 89
Qualitative Quantitative
Method (PDM) Selection
Document Results
Project Delivery
and Stop Document Results
and Stop
Successful? Evaluate Decision
Preliminary Risk-Allocation Verify
Risk Analysis Matrix PDM Selection Risk Analysis Selected
PDM
Project Lifecycle
Preliminary
Conceptual Design Final Design
Engineering
Figure 6.3. Risk-based approach superimposed on project lifecycle.
reduce the number of possible alternatives. Table 6.1 shows a risk-allocation matrix for a hypo-
thetical project. A description of the development of this risk-allocation matrix is given below.
Risk factors (shown the first column in Table 6.1 and typically arranged in a matrix according
to either their impact [rank] or chronology) are major events or conditions that can affect a proj-
ect in a negative way (the events that can affect the project in a positive way are called "opportu-
nities," and traditionally there are far fewer opportunities than risks). Only significant risks should
be considered because identifying and measuring all project risks would be a major effort. Under
each project delivery method listed in the matrix, a main responsible party should be identified
for each risk factor. For example, in the matrix shown in Table 6.1, the party responsible for
design defects in a DBB contract is the owner, whereas in the DB contract, the responsible party
is the constructor.
Risk factors are rated, always from the perspective of the owner agency, according to the effect
of a particular project delivery method on that risk factor. In the hypothetical case shown in
Table 6.1, from the agency perspective, DBB is seen as having a favorable effect on the risk fac-
tor of "permits/approvals." The agency thinks that it is the best party to obtain permits/approvals
and that it can most effectively do this using a DBB approach. Therefore, the risk factor of
Table 6.1. Risk-allocation matrix for a hypothetical project.
DBB DB
Risk Factor
Responsible Party Rating Responsible Party Rating
Permits/Approval Owner + Constructor/Owner
Different Site Conditions Owner 0 Constructor/Owner +
Design Defects Owner Constructor +
Quality Assurance/ Constructor/Owner 0 Constructor +
Quality Control
Exchange Rate Risk Owner Owner
Other Risk Factors