Suggested Citation:"Chapter 5 - Conclusions and Proposals." National Research Council. 2022. Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders. Washington, DC: The National Academies Press. doi: 10.17226/26677.
×
Page 141
Page 142
Suggested Citation:"Chapter 5 - Conclusions and Proposals." National Research Council. 2022. Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders. Washington, DC: The National Academies Press. doi: 10.17226/26677.
×
Page 142
Page 143
Suggested Citation:"Chapter 5 - Conclusions and Proposals." National Research Council. 2022. Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders. Washington, DC: The National Academies Press. doi: 10.17226/26677.
×
Page 143
Page 144
Suggested Citation:"Chapter 5 - Conclusions and Proposals." National Research Council. 2022. Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders. Washington, DC: The National Academies Press. doi: 10.17226/26677.
×
Page 144
Page 145
Suggested Citation:"Chapter 5 - Conclusions and Proposals." National Research Council. 2022. Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders. Washington, DC: The National Academies Press. doi: 10.17226/26677.
×
Page 145

Below is the uncorrected machine-read text of this chapter, intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text of each book. Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.

141   Conclusions and Proposals 5.1 Conclusions An integrated multilevel analytical and experimental research program was conducted to investigate the potential benefits, fabrication challenges, and design issues of using 0.7-in. strands in pretensioned girders. From simulation results in conjunction with experimental data and observations, the primary conclusions of this study are as follows: 1. Current design procedures for prestressed concrete bridge girders, including the calculation of flexural and shear capacities and all required stress checks, are adequate for girders using 0.7-in. strands. 2. Permitted release stresses, the maximum allowed number of partially debonded strands, and prestressing bed capacity could limit the number of 0.7-in. strands that can be used in current prestressed girder shapes. Moreover, the span length of girder shapes optimized for 0.6-in. strands is not appreciably increased by using 0.7-in. strands. Reducing congestion by minimizing the number of strands required to achieve the same prestressing force appears to be the more beneficial application of 0.7-in. strands. 3. The use of 0.7-in. strands does not affect issues of girder stability per se. If, however, longer spans are fabricated using 0.7-in. strands, greater care must be taken in stability analysis although by revising hanging and dunnage support locations and providing adequately stiff support conditions in transport, stability checks can be satisfied. For exceptionally long girders, extending the width of the top flange has been shown to improve stability consider- ations. Girders with relatively thin bottom flanges, such as bulb tees, benefit more in terms of potentially increasing achievable span length by using 0.7-in. strands. However, such girders exhibit greater susceptibility to rollover while supported on dunnage or in transportation, thereby requiring greater consideration of these effects. 4. Similar to previous studies, experimentally determined transfer and development lengths were found to be less than those prescribed by the AASHTO LRFD Bridge Design Specifications (AASHTO, 2020). While overestimating the development length is conservative in terms of capacity calculation, overestimation of transfer length underestimates concrete tensile stresses at release, potentially leading to cracking in the girder end region affected by the transfer length. 5. Transfer and development lengths prescribed by NCHRP Report 603 (Ramirez and Russell, 2008) were observed to be more representative of the data measured in this study. 6. No deleterious effects from using 0.7-in. strands spaced at 2 in. center-to-center were identi- fied analytically and experimentally. 7. The extension of bottom flange confinement reinforcement was found to be inadequate for cases with partially debonded 0.7-in. strands, but the extension of bottom flange confinement reinforcement to 1.5d beyond the end of the girder was adequate for cases with no debonded C H A P T E R   5

142 Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders strands. The minimum amount of confinement reinforcement required (No. 3 at spacing not exceeding 6 in.) was found to be sufficient to confine 0.7-in. strands. 8. Industry acceptance of 0.7-in. strands requires fabricators’ willingness to deal with an “unfamiliar” strand and having the infrastructure, such as higher-capacity stressing jacks, prestressing beds, and harping hold-downs, to apply the greater prestressing force for 0.7-in. strands (35% greater than for a 0.6-in. strand). 5.2 Proposed Detailing Guidelines for Prestressed Girders Having 0.7-In. Strands The reported analytical and experimental studies indicate relatively few changes are necessary for the design and detailing guidelines of girders with 0.7-in. strands. Current AASHTO LRFD Bridge Design Specifications articles (AASHTO, 2020) are applicable to 0.7-in. strands unless noted in the following. Specific recommendations for inclusion in AASHTO LRFD Bridge Design Specifications articles are provided in Appendix L. 1. AASHTO LRFD Bridge Design Specifications Article 5.9.4.4.1 (AASHTO, 2020) splitting rein- forcement is sufficient for 0.7-in. strands to resist bursting stresses at release. However, in cases where the maximum number of possible 0.7-in. strands is used, the greater splitting forces could lead to potentially more congested vertical splitting reinforcing steel requirements at the beam ends. Therefore, it should be permitted to extend the required splitting reinforcement beyond the current h/4 limit. 2. The minimum bottom flange confinement reinforcement required by the existing AASHTO LRFD Bridge Design Specifications Article 5.9.4.4.2 (AASHTO, 2020) must be extended to at least 1.5d beyond the termination of the longest debonded length of 0.7-in. strands. 3. AASHTO LRFD Bridge Design Specifications Article 5.9.4.4.2 (AASHTO, 2020) confine- ment reinforcement does not account for the influence of support-bearing width and the impacts of a wheel load being close to the support. The minimum confinement required by Article 5.9.4.4.2 may be insufficient in some cases. The strut-and-tie approach discussed in Section 2.4.1 is a more comprehensive method for determining the required bottom flange confinement reinforcement near the support. 4. The existing transfer length from AASHTO LRFD Bridge Design Specifications Article 5.9.4.3.2 (AASHTO, 2020) is appropriate for strength calculations. A reduced transfer length, equal to that recommended by NCHRP Report 603 (Ramirez and Russell, 2008), should be adopted for girder end-region stress checks at prestress transfer. 5.3 Fabrication, Handling, Shipping, and Erection Guidelines 1. Fabricators need to check the adequacy of their prestressing bed and hold-down devices and provide this information to the engineer of record. Accordingly, the design may have to be changed based on the number of 0.7-in. strands that can be stressed or the jacking force may have to be lowered. More hold-down locations may need to be used if 0.7-in. strands are to be harped (deflected). 2. Current shipping strands by weight result in 35% less length of 0.7-in. strand on a given reel. Fabricators need to account for this information as part of their bidding process. 3. Fabricators must pay special attention to the greater binding tension of 0.7-in. strand reel, which is 1.85 times larger than that of 0.6-in. strand. This larger energy in the spool could pose a safety hazard when strands are pulled out of the reel. Workers are advised not to hold 0.7-in. strands tightly in their hands as they pull them out of reels; they need to let the

Conclusions and Proposals 143   strands twist while being pulled out. Workers need to be informed that 0.7-in. strands are 35% heavier than 0.6-in. strands to prevent injury. 4. Use established procedures to check the stability of girders using 0.7-in. strands and (1) revise hanging and dunnage support locations as needed, (2) provide stiff support conditions in transport, and (3) extend the width of the top flange to enhance the stability of exceptionally long girders. 5.4 Suggestions for Future Research The following is a list of recommended future research activities. 1. The performance of additional girders utilizing 15-ksi concrete needs to be evaluated. 2. Companion girders with 0.6-in. and 0.7-in. strands should be tested to understand whether the recommended extension of 1.5d beyond the termination of the longest debonded length is also necessary for 0.6-in. strands. 3. Due to the marginally reduced cover when using the same center-to-center strand arrange- ments, the long-term performance of bridges using 0.7-in. strands under field conditions needs to be studied. 5.5 Proposed Revisions to AASHTO LRFD Bridge Design Specifications The following changes, indicated by underlines, are proposed. In Table 5.4.4.1-1—Properties of Prestressing Strand and Bar revise the row for the strand to include 0.7-in. diameter as the largest strand size in the indicated specifications: Material Grade or Type Diameter (in.) Tensile Strength, fpu (ksi) Yield Strength, fpy (ksi) Strand 270 ksi 0.375 to 0.6 0.7 270 90% of fpu Bar Type 1, Plain Type 2, Deformed 0.75 to 1.375 0.625 to 2.5 150 150 85% of fpu 80% of fpu Revise Table 5.9.4.1-1—Center-to-Center Spacings by adding 0.7-in.-diameter strand to the row with a spacing of 2.00 in.: Strand Size (in.) Spacing (in.) 0.7 0.6 0.5625 Special 0.5625 2.00 0.5000 0.4375 0.50 Special 1.75 0.3750 1.50 Revise Article 5.9.4.4.2—Confinement Reinforcement as follows: For the distance of 1.5d from the end of the beams other than box beams, reinforcement shall be placed to confine the prestressing steel in the bottom flange. With a 0.7-in.-diameter partially debonded strand, reinforcement shall be placed to confine the prestressing steel in the bottom

144 Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders flange from the end of the beam for a distance not less than 1.5d beyond the termination of the longest debonded length. The reinforcement shall not be less than No. 3 deformed bars, with spacing not exceeding 6.0 in., and shaped to enclose the strands. For box beams, horizontal transverse reinforcement shall be provided and anchored by extending the leg of the stirrup or tie into the web of the girder beam. Add new Article 5.9.4.4.3 as follows: 5.9.4.4.3—Horizontal Transverse Tension Tie Reinforcement Horizontal transverse reinforcement provided to satisfy Articles 5.9.4.4.1 and 5.9.4.4.2 may also be used to satisfy this article. In lieu of the requirements of this article, steel sole plates shall be embedded at the girder ends. Articles 5.9.4.4.1 and 5.9.4.4.2 shall still be applicable when a steel sole plate is used. For all single-web beam sections with a bottom flange, horizontal transverse tension tie rein- forcement shall be provided to resist potential longitudinal splitting cracks in the bottom flange. For single-web sections, the strut-and-tie model and the associated equation shown in Figure 5.9.4.4.3-1 shall be used to determine the required amount of horizontal transverse tie reinforcement. The horizontal transverse tie reinforcement shall be uniformly distributed over the length of the bearing plus a distance equal to one-quarter of the overall height of the beam or girder element in its final configuration (including a composite slab if provided) on the span side of the bearing. , where where Atie = area of tie reinforcement (in.2) bb = width of bearing (in.) cb = distance from the bearing reaction forces to the centerline of section (in.) Figure 5.9.4.4.3-1—Strut-and-tie model for confinement

Conclusions and Proposals 145   fy,tie = yield strength of tie reinforcement (ksi) hb = depth of bottom bulb (in.) Nw = total number of bonded strands aligned with web nf = number of bonded strands in one side of the outer portion of the web xp = the horizontal distance from girder centerline to the centroid of nf strands in the outer portion of the bulb (in.) yp = the vertical distance from girder soffit to the centroid of nf strands in the outer portion of the bulb (in.) Add new Commentary C5.9.4.4.3 as follows: The development of tension oriented transversely across the bulb of single-web flanged sections is a potential failure mode requiring tie reinforcement across the bottom flange to control the potential longitudinal cracking at the Strength I limit state. The nature of the result- ing failure, however, is related to excessive transverse deformation and cracking of the flange and is not likely to be catastrophic in nature. Minimum confinement reinforcement satisfying Article 5.9.4.4.2 contributes to the tie capacity, and in many instances will be sufficient to fully resist the horizontal transverse tie force calculated using Article 5.9.4.4.3. The horizontal portion of splitting reinforcement required by Article 5.9.4.4.1, if present, contributes to the tie capacity force calculated using Article 5.9.4.4.3. In some instances, these requirements may result in impractical horizontal transverse tie reinforcement details. An embedded sole plate would likely be more practical in such cases. Add the following reference to Article 5.15: Shahrooz, B. M., K. A. Harries, R. W. Castrodale, and R. A. Miller (2022) NCHRP Research Report 994: Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders. Transportation Research Board, Washington, DC.

Next: References »
Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders Get This Book
×
 Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders
MyNAP members save 10% online.
Login or Register to save!
Download Free PDF

Long-span bridges are often used in environmentally sensitive terrains, water crossings, and in locations with traffic and geometric restrictions.

The TRB National Cooperative Highway Research Program's NCHRP Research Report 994: Use of 0.7-in. Diameter Strands in Precast Pretensioned Girders presents the design methodology for precast pretensioned girders using 0.7-in. diameter strands based on comprehensive analytical and testing programs. The use of 0.7-in. diameter strands would help bridge designers extend the spans of the existing girder shapes.

Supplemental to the report is NCHRP Web-Only Document 315: Details of the Study on the Use of 0.7-in Diameter Strands in PrecastPretensioned Girders.

READ FREE ONLINE

  1. ×

    Welcome to OpenBook!

    You're looking at OpenBook, NAP.edu's online reading room since 1999. Based on feedback from you, our users, we've made some improvements that make it easier than ever to read thousands of publications on our website.

    Do you want to take a quick tour of the OpenBook's features?

    No Thanks Take a Tour »
  2. ×

    Show this book's table of contents, where you can jump to any chapter by name.

    « Back Next »
  3. ×

    ...or use these buttons to go back to the previous chapter or skip to the next one.

    « Back Next »
  4. ×

    Jump up to the previous page or down to the next one. Also, you can type in a page number and press Enter to go directly to that page in the book.

    « Back Next »
  5. ×

    To search the entire text of this book, type in your search term here and press Enter.

    « Back Next »
  6. ×

    Share a link to this book page on your preferred social network or via email.

    « Back Next »
  7. ×

    View our suggested citation for this chapter.

    « Back Next »
  8. ×

    Ready to take your reading offline? Click here to buy this book in print or download it as a free PDF, if available.

    « Back Next »
Stay Connected!