... This chapter describes the who, what, where, when, and how of airspace protection. Specifically, it outlines the mechanisms and processes, and the roles and responsibilities of the various parties to the process.
From page 26...
... the aeronautical review process; and (3) when the structure is complete, notification of actual construction.
From page 27...
... Mechanisms and Processes of Airspace Protection 27 Sources: FAR Part 77, FAA Order 7400-2 Prepared by: Jacobs Consultancy Figure 3.1. Major steps in the FAA's Obstruction Evaluation/Airport Airspace Analysis (OE/AAA)
From page 28...
... (2) When the Form 7460-1 has been filed, the FAA acknowledges receipt, assigns an aeronautical study number (ASN)
From page 29...
... (5A) At the conclusion of further aeronautical study, if the FAA determines that the original proposal would not constitute a hazard to air navigation, the FAA issues a DNH with obstruction marking and lighting requirements.
From page 30...
... local regulations may be lacking. In these cases, the airport manager must coordinate with local authorities to encourage construction proponents to file FAA Form 7460-1 where required, and work with construction proponents and other stakeholders to mitigate or remove objectairspace conflicts.
From page 31...
... 3. When a specific structure proposal is submitted to the FAA, the FAA provides its assessment of the proposal through the OE/AAA process, concluding with a final determination.