Appendix B - Example of Pavement-Type Selection in Alternate Bidding
Pages 51-56

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 51...
... The agency has identified three noneconomic factors necessary for evaluation in the selection process: • Material recycling. • Stimulation of competition.
From page 52...
... The summary of the LCCA is presented in Table B5. Step 5: Evaluation Using Economic Factors Upon computing the life-cycle costs, the agency conducts an economic evaluation of alternatives to assess their cost feasibility at the project level as well as the agency level.
From page 53...
... 53 Figure B1. Salvage value calculation for Alternative 3.
From page 54...
... Evaluation of alternatives using noneconomic factors. Cost Factor Alternative 1 Alternative 2 Alternative 3 Initial costs $2,650,000 $3,100,000 $2,910,000 Present value of future rehabilitation costs $338,232 $90,029 $548,336 Present value of future maintenance costs $49,650 $47,836 $55,167 Present value of total costs $3,037,882 $3,237,865 $3,513,503 Noneconomic Factors Alternative 1 Alternative 2 Alternative 3 Material recycling More recycling possibilities Some recycling possibilities More recycling possibilities Stimulation of competition Encourages competition Encourages competition Encourages competition Maintenance capability Common experience Common experience Common experience
From page 55...
... Economic Factors Difference in Cost Estimate (%) Alternative 1 Alternative 2 Alternative 3 Initial costs 0 17 10 Present value of future rehabilitation costs 276 0 509 Present value of future maintenance costs 4 0 15 Net present value of life- cycle costs 0 7 16 Note: "0" indicates the alternative having the lowest cost estimate for the specific economic factor.
From page 56...
... Group Factor Alternative 1 Alternative 2 Alternative 3 Economic factors Initial costs High Low Medium Rehabilitation costs Low High Low Maintenance costs High High Low Life cycle costs High Medium-high Low Noneconomic factors Material recycling Medium-high Medium Medium-high Stimulation of competition High High High Maintenance capability No difference No difference No difference Table B11. Summary of the alternative-preference screening matrix scores.