Skip to main content

Currently Skimming:

J: REVIEW OF EXISTING COST ESTIMATES
Pages 262-295

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 262...
... This estimate was made by applying the "Hanford Cost Estimating Formula" to the Oak Ridge GDP. This method applies a labor-cost formula to the cubic feet of waste in the Oak Ridge GDP facilities for three scenarios: protective (safe)
From page 263...
... waste disposal costs to waste volumes. The labor cost formula was modified by MMES, as described in its 1988 report: Since ORGDP [Oak Ridge gaseous diffusion plant]
From page 264...
... ; D&D of Gaseous Diffusion Plants, prompt cost summary, all case studies table in Ebasco Environmental (199lb)
From page 265...
... Appropriate factors for contractor overhead and profit will be applied to all direct costs. · A factor of 5 percent for contract management will be applied to all cost elements except Program Integration.
From page 266...
... The gaseous decontamination process will remove at least 90 percent of residual uranium in the process equipment, reducing-the content to below the special nuclear materials security control limit. Construction and operation of two decontamination facilities the high-assay decontamination facility (HADF)
From page 267...
... The postulated LADE, which is intended to handle equipment and materials contaminated with uranium enriched to less than 20 percent 23su, contains 1,241,600 gross square feet of floor space, comparable in size to the K-27 or K-31 gaseous diffusion buildings. Each facility contains equipment for decontamination and s~ze-reduction of GDP components and waste materials and equipment for assaying packaged wastes to ensure that the residual uranium content of the packages meets disposal site acceptance criteria for uranium contamination before shipment.
From page 268...
... For estimates May through August, the indirect rate is equal to 50 percent, a value equal to a 30 percent add-on for field indirects, a 3.3 percent add-on for home office overhead (3.3 percent of both direct and field indirects) , and a contractor's profit of 12 percent (12 percent of direct and indirect costs and overhead)
From page 269...
... Direct costs, not including direct program integration costs, increased as a percent of total costs from 34 to 41 percent from the May estimate to the September estimate. Indirect costs plus program integration costs as a percent of total costs declined from 36 percent to 33 percent from the first to last estimate.
From page 270...
... SOURCE: MMES (1988~; Prompt Cost Summary Table, Case 1, Initial Estimate, in Ebasco Environmental (1991a) ; tables 3.2-1 and 3.2-2 in DOE (1991a)
From page 271...
... To compare the estimates, indirect costs and rollups are assumed to be included in the MMES labor cost and waste disposal formulas. Second, $2.751 billion of remedial action activities have been included in the MMES greenfield cost estimate.
From page 272...
... TLG COST ESTI1\IATE Following completion of the Ebasco cost estimate, DOE contracted with TLG to perform another bottom-up estimate for the GDPs (DOE, l991b)
From page 273...
... $2 436$359 Direct , 43%14% Indirect percentage Total $3,483$409 Waste Management (WBS 1.2) $689$446 Direct 43%14% Indirect percentage $985$508 Total Program Integration (WBS 1.1)
From page 274...
... . constructing and operating LADFs at Paducah and Portsmouth, which increases costs by 17.2 percent; refurbishing buildings undergoing D&D, which increases costs by 3.3 percent; constructing new administration buildings at Paducah and Portsmouth instead of refurbishing existing buildings, which increases costs by 0.3 percent; incorporating electrorefining capabilities at Oak Ridge, which decreases costs by 1.8 percent; providing HADFs at Oak Ridge and Portsmouth and LADFs at all sites, which increases costs by 21.6 percent; transporting Portsmouth X-326 equipment (processed highly enriched uranium)
From page 275...
... Levels of confidence were calculated from the resulting cost estimates. Using this approach, under these probability distributions, TEG determined that there was a 50 percent chance that the cost of the project would be below $16.2 billion and a 100 percent chance that the cost would be below $28.7 billion (in 1992 dollars)
From page 276...
... D&D operations; and (5) site preparation and construction of storage facilities, including design and construction of waste disposal facilities and transportation and final disposal of waste.
From page 277...
... The Ebasco cost estimate also includes the cost in each period by determining the work hours, necessary materials and equipment, and associated indirect costs for each activity. The calculation of labor, materials, and equipment costs is a straightforward multiplication of costs per unit multiplied by the number of units.
From page 278...
... . It is noted that this was not done for Program Integration, as indirect costs/workhours were considered in the original estimate basis and therefore no additional mark-up was necessary.
From page 279...
... Other associated costs include indirect costs, home office overhead costs, and profit, amounting to a total of 43.17 percent, which were added to the direct cost. Under the category of Program Integration in the Ebasco cost estimate, a certain amount of personnel time was also allocated to waste management activities.
From page 280...
... Costs Related to Waste Management (WM) (in 1992 dollars)
From page 281...
... Table I-13 describes the local transportation cost summary for each GDP site. Interstate Transportation to the Oak Ridge LADE for Processing Appropriate Paducah and Portsmouth waste materials will be transported to the Oak Ridge GDP LAD F for processing, and the processed wastes will be returned to their originating
From page 282...
... 282 Cal Ct o ._ Ct o Ct I Cal o V Cal Cal F
From page 283...
... 283 Cq Cal o v ax V Ct v 'V Ct 4-04 Ct En 4U.
From page 284...
... 284 Cal Ct - o He Cal ._ _' 2 o Cq no so no Ct V, 4 C~ o 4 Ct Ct 4Cal Ct 3 o Ct Ct Ct au ._ C)
From page 286...
... Transportation costs include loading and line-haul costs. Table J-14 summarizes the round-trip transportation costs between the Paducah and Portsmouth GDPs and the Oak Ridge GDP LADE.
From page 287...
... . TABLE J-14 Interstate Transportation Cost Summary for Waste from the Paducah and Portsmouth GDPs Paducah (Direct Cost)
From page 288...
... Waste Management Unit Cost Summary Based on the unit cost component developed by Ebasco, the total direct unit cost by waste type is presented in Table J-17. Tables J-18 to J-21 summarize waste management unit costs by type.
From page 289...
... 7,161,000 3,370,000 4,340,000 Unit cost ($/ft3) 0.54 0.89 0.75 Direct cost ($)
From page 290...
... TABLE I-18 Waste Management Unit Cost Summary for Level ~ Waste (1992$/f~c3) Packaging TransporP Disposal Storage Total GDP Site Net Gross Net GrossNet Gross Net GrossNet Gross Oak Ridge 7.13 11.11 0.68 1.0614.34 22.35 0.64 0.8422.69 35.36 Paducah 7.14 10.51 0.68 1.0014.47 21.30 0.89 1.3123.18 34.12 7.14 10.51 13.72 20.1914.47 21.30 0.89 1.3136.22 53.31 Portsmouth 7.13 10.64 0.68 1.0214.43 21.54 0.75 1.1222.99 34.32 7.13 10.64 14.37 21.4514.43 21.54 0.75 1.1236.68 54.75 NOTE: Net, direct cost only; gross, including all indirect costs, except contingency.
From page 291...
... 291 Packaging Transporta Disposal Storage Total ~ GDP SiteNet Gross Net GrossNet Gross Net GrossNet Gross Oak Ridge15.90 24.78 0.67 1.0432.19 50.16 0.54 0.8449.30 76.82 Paducah16.16 23.78 0.64 0.9432.71 48.14 0.89 1.3150.40 74.17 16.16 23.78 13.93 20.5032.71 48.14 0.89 1.3163.69 93.73 Portsmouth 16.25 24.26 0.64 0.96 32.71 48.83 0.75 1.12 50.35 75.17 16.25 24.26 14.58 21.76 32.71 48.83 0.75 1.12 64.29 95.97 NOTE: Net, direct cost only; gross, including all indirect costs, except contingency. a For the Oak Ridge GDP, local transportation costs to disposal site only.
From page 292...
... Packaging Transporta Disposal Storage Total GDP SiteNet Gross Net Gross Net Gross Net Gross Net Gross _ Oak Ridge0.38 0.59 0.69 1.08 0.00 0.00 0.54 0.84 1.61 2.51 Paducah0.35 0.52 0.69 1.02 0.00 0.00 0.89 1.31 1.93 2.58 0.35 0.52 9.93 14.61 0.00 0.00 0.89 1.31 11.17 16.44 Portsmouth0.36 0.54 0.69 1.03 0.00 0.00 0.75 1.12 1.80 2.69 0.36 0.54 11.24 16.78 0.00 0.00 0.75 1.12 12.35 18.44 NOTE: Net, direct cost only; gross, including all indirect costs, except contingency. a For the Oak Ridge GDP, local transportation costs to disposal site only.
From page 293...
... l991b. Design Services in Support of the Oak Ridge Operations Environmental Restoration and Waste Management Program.
From page 294...
... pertaining to responses to questions on GDP (Gaseous Diffusion Plant) cost estimates to J
From page 295...
... 1994b. DOE EM-40 Analysis of Gaseous Diffusion Plant Decontamination and Decommissioning Estimates and Draft Program Planning.


This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.