6 Risk Management
Pages 22-23

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 22...
... SCHEDULE RISK Another risk that must be considered is associated with the schedule of project development and design, construction, start-up, operations, and shutdown. Schedule delays not only affect cost and meeting CWC obligations, but also increase public risk due to continued storage.
From page 23...
... Recommendation 6-2. Schedule risk should be evaluated for the Aberdeen and Newport facilities in the context of program implications and public risks and appropriate contingency plans developed if needed.