Skip to main content

Currently Skimming:


Pages 49-72

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 49...
... CHAPTER 4 RIGHT OF WAY PROCEDURE DEVELOPMENT The goal of Task 4, Develop Procedures on ROW Cost Estimation and Management was to develop a "how to" Procedures Guide to support right-of-way cost estimating and management processes. The framework for the procedures guide is the series of process flowcharts that describe the right-of-way cost estimation and cost estimate management processes during project development phases.
From page 50...
... 1. Determine Estimate Basis; 2.
From page 51...
... September 2007 although no major changes or revisions to the flowcharts were suggested. The panel was interested in how the inputs might change from one cost estimate to another.
From page 52...
... Figure 6. Agency-level right-of-way cost estimating and cost management flowchart 49
From page 53...
... The intent of displaying the project development phases linked to right-of-way cost estimating and cost estimate management is to communicate the critical relationship that exist between the two activities. Moreover, it stresses the relationship that should exist between the personnel who estimate and procure right-of-way and the project development team.
From page 54...
... Right-of-way Cost Estimating and Estimation Management The flowcharts documenting Conceptual Right-of-way Cost Estimating, Baseline rightof-way Cost Estimating, and Update Right-of-way Cost Estimating are shown in Figure 7, Figure 8, and Figure 9, respectively. These flowcharts are discussed in combination here due to similarities in the process steps.
From page 55...
... Figure 7. Conceptual Right-of-way cost estimating process flowchart 52
From page 56...
... Figure 8. Baseline Right-of-way cost estimating process flowchart 53
From page 57...
... Figure 9. Update Right-of-way cost estimating process flowchart 54
From page 58...
... The Conceptual Right-of-way Cost Estimate process flowchart, Figure 7, is so named because it is based on a conceptual definition of project scope. The conceptual scope sets the general right-of-way requirements.
From page 59...
... Table 4. General process steps and descriptions for right-of-way cost estimating Process Step Activity Description ROW Requirements from Development Team Development team communicates ROW requirements to ROW personnel.
From page 60...
... Input: Right-of-way Requirements from Development Team The primary input to the cost estimating flowcharts is the set of right-of-way requirements as defined by the development team and communicated to right-of-way section. The major difference between right-of-way estimates is the varying amount of certainty (or uncertainty)
From page 61...
... A robust effort must be made by the right-of-way estimator to define the estimate basis in as much detail as possible so that a deterministic cost value can produced. If the estimate basis is not defined accurately the estimator has little solid data on which to base the projected cost.
From page 62...
... lessens, therefore, the amount of contingency that is applied to subsequent estimates should be less, but risk analysis and the application of contingency should still be performed as there are always cost and schedule risks. The amount of detail involved in the Conceptual Right-of-way Cost Estimate is usually minimal when compared to later estimates, but it is critical for the right-of-way estimator to identify the major risks to project cost and schedule.
From page 63...
... Figure 9, as a decision milestone following "Review Updated ROW Cost Estimate" and denoted by a diamond. If the estimate is within the Baseline Right-of-way Cost Estimate budget, then the estimate should be approved for release back to the development team.
From page 64...
... Cost Estimating Inputs In addition to the right-of-way requirement input and estimate output shown in the Table 4, there are other keys inputs needed to perform the process steps. As previously discussed, the major input into the process flowcharts are the right-of-way requirements which are used to establish the estimate basis for right-of-way cost estimates and to determine whether changes have occurred in Right-of-way Cost Management.
From page 65...
... should include documenting existing conditions and making notes of potential damages and improvements or other issues that may impact the cost of acquiring the right-of-way. Although the field visit gathers the same information for each of the estimates, the level of detail and certainty varies.
From page 66...
... the future. The inflation rate becomes somewhat less uncertain with a shorter duration between the estimate and acquisition but the rate can still be volatile.
From page 67...
... fees, appraisals, and other costs. Moreover, condemnation is a risk to the project schedule.
From page 68...
... Figure 10. Right-of-way cost management process flowchart 65
From page 69...
... Right-of-way Cost Management Process Steps The process flowchart documenting right-of-way activities during final design is primarily describing the Right-of-way Cost Management steps during real estate acquisition. The process steps used in the Right-of-way Cost Management Flowchart are presented and explained in Table 5.
From page 70...
... Input: ROW Requirements from Design The final right-of-way plans (requirements) are the major input into the Right-of-way Cost Management process.
From page 71...
... Output: Forecasted Total ROW Cost Following adjustment of the budget and notification to the project manager of expected right-of-way cost, the adjusted budget should be communicated to the project development team. The Right-of-way Cost management process continues until all rightof-way is acquired.
From page 72...
... Tools – illustrations and references to the Tool Appendix Tips for Success – important points to remember Outputs – main deliverable(s) of the step Flowchart Step (e.g., Prepare Base Estimate)

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.