Skip to main content

Currently Skimming:


Pages 56-104

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 56...
... 56 Experimental Testing 3.1 Introduction Experimental testing was performed on the UHPC longitudinal joint and the continuity connection. This was to verify analytical results and determine differences that cannot always be modeled.
From page 57...
... Experimental Testing 57   Figure 3.1. Top view of girder layout.
From page 58...
... 58 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.4. Surface temperature.
From page 59...
... Experimental Testing 59   Figure 3.6. Internal sensor locations.
From page 60...
... 60 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.8. Temperature gradient, 2:21 p.m.
From page 61...
... Experimental Testing 61   of the unrestrained joints due to the thermal cycle. Figure 3.11 shows the location of the vibrating wire gauges used to measure the joint displacements.
From page 62...
... 62 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.12 shows the results of the joint gauges during a thermal cycle run on November 20. As shown by Figure 3.12, the top of the joint contracted more than the bottom.
From page 63...
... Experimental Testing 63   the United States. The research team (RT)
From page 64...
... 64 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections e UHPC was transferred from the mixer in buckets into chimneys (orange and white buckets in Figure 3.13) at approximately the third points along the joint.
From page 65...
... Experimental Testing 65   was used to ensure the UHPC did not leak out of the joint and gave an approximately ⅛-in. height above the joint.
From page 66...
... 66 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.15. Temperature gradient during UHPC placement, 12/21/2020.
From page 67...
... Experimental Testing 67   Figure 3.17. Strains across joint 12, 12/21/2020.
From page 68...
... 68 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.19. Vibrating wire gauges across the joints.
From page 69...
... Experimental Testing 69   The temperature gradient was determined from the average temperatures of the gauges near the top surface of the girder (gauges 5 and 6 in Figure 3.6) compared to the internal gauge near the bottom surface of the girder (gauge 1 in Figure 3.6)
From page 70...
... 70 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.22. Girder reactions, 12/22/2020.
From page 71...
... Experimental Testing 71   Figure 3.24. Temperature gradient 2 days after UHPC placement, 12/23/2020.
From page 72...
... 72 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections 3.2.1.6 Thermal Behavior 5 Days after UHPC Placement and Formwork Removal On December 26, 2020, girder 2 had the largest thermal gradient and girders 1 and 3 had similar lower gradients, as shown in Figure 3.27 for this thermal cycle. The camber of girder 2 remained the largest, while girder 1's camber was slightly more than that of girder 3, as shown in Figure 3.28.
From page 73...
... Experimental Testing 73   Figure 3.27. Temperature gradient, 12/26/2020.
From page 74...
... 74 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.29. Girder reactions, 12/26/2020.
From page 75...
... Experimental Testing 75   Figure 3.31. Temperature gradient, 1/25/2021.
From page 76...
... 76 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.33. Girder reactions, 1/25/2021.
From page 77...
... Experimental Testing 77   3.2.1.8 Thermal Behavior over a Month after UHPC Placement and Formwork Removal The thermal cycle on January 27, 2021, was very similar to that on January 25. However, unlike December 26, 2020, and January 25, 2021, girders 1 and 3 had larger thermal gradients than girder 2, as shown in Figure 3.36.
From page 78...
... 78 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.36. Temperature gradient, 1/27/2021.
From page 79...
... Experimental Testing 79   with the strain at location J12-2 again increasing positively with the increase in temperature and then dropped off during cooling. 3.2.1.10 Cyclic Live Loading After the thermal cycles were completed, cyclic live loading was applied to the system from a load of 0 kips to 70 kips for 100,000 cycles.
From page 80...
... 80 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections (a) End view with midspan loading also shown: test 1 with girders 1–3 (b)
From page 81...
... Experimental Testing 81   Figure 3.41. Load frame with insulated box.
From page 82...
... 82 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.43. Camber, 4/26/2021.
From page 83...
... Experimental Testing 83   Figure 3.45. Joint 12 rebar strains, 4/26/2021.
From page 84...
... 84 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections not indicate any cracking. However, the RT had concerns about cracking based on some of the instrument strain reading jumps.
From page 85...
... Experimental Testing 85   Interface crack Figure 3.49. Interface leakage.
From page 86...
... 86 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Overlapping UHPC UHPC crack Figure 3.51. Joint 2-3 UHPC cracking.
From page 87...
... Experimental Testing 87   (a)
From page 88...
... 88 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.53. Differential camber.
From page 89...
... Experimental Testing 89   Figure 3.56. Removal of differential camber.
From page 90...
... 90 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections The load used to remove the differential camber was then released gradually in steps as shown by the girder reactions in Figure 3.58. The girder cambers are provided in Figure 3.59: girder 4 had the largest midspan camber of slightly more than 0.20 in.
From page 91...
... Experimental Testing 91   Figure 3.58. Girder reactions from load release.
From page 92...
... 92 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections (a)
From page 93...
... Figure 3.61. Camber from static loading, 6/16/2021.
From page 94...
... 94 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Figure 3.63. Reactions from static loading, 6/16/2021.
From page 95...
... Experimental Testing 95   Figure 3.65. Core slice with crack.
From page 96...
... 96 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections 3.3 Continuity Joint Testing The continuity joint test consisted of two 20-ft. PCEF 39-in.-deep girders placed end to end.
From page 97...
... Experimental Testing 97   Figure 3.68. Continuity joint reinforcement.
From page 98...
... 98 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections Embedded Strain Gauge Figure 3.70. Continuity joint top reinforcement instrumentation.
From page 99...
... Experimental Testing 99   Age (days) Average Compressive Strength (psi)
From page 100...
... 100 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections shown in Figure 3.74, were very small. As expected, gauge 1 near the bottom of the connection experienced tension, while the gauges in the flanges (gauges 3–5)
From page 101...
... Experimental Testing 101   Gauge 1 Gauge 2 Gauge 3 Gauge 4 Gauge 5 Figure 3.74. Continuity joint strains from positive moment.
From page 102...
... Figure 3.77. Strains in reinforcement from west girder.
From page 103...
... Experimental Testing 103   increase and indicated yielding. The load of 98 kips corresponds to a total moment of 1,357 kip-ft., including the self-weight.
From page 104...
... 104 Design and Construction of Deck Bulb Tee Girder Bridges with UHPC Connections in the east end of the joints. The UHPC was placed in the east ends last and seemed to have slower flow.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.