B Text of Pertinent Regulations
Pages 148-159

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 148...
... c. The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the design phase in accordance with the approved schedule required by §250.911(d)
From page 149...
... c. The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the fabrication phase in accordance with
From page 150...
... Alignment procedures; (xiii) Dimensional check of the overall structure, including any turrets, turret-and-hull interfaces, any mooring line and chain and riser tensioning line segments; and (xiv)
From page 151...
... c. The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the installation phase in accordance with the approved schedule required by §250.911(d)
From page 152...
... Final deck and component installations; and (viii) Installation at the approved location according to the approved design and the installation plan.
From page 153...
... Ensure that your facilities are designed, fabricated, and installed in conformance with accepted engineering practices and the Facility Design Report and Fabrication and Installation Report; 2. Ensure that repairs and major modifications are completed in con formance with accepted engineering practices; and 3.
From page 154...
... Previous experience in third-party verification or experience in the design, fabrication, installation, or major modification of offshore energy facilities; 2. Technical capabilities of the individual or the primary staff for the specific project; 3.
From page 155...
... The CVA must use good engineering judgment and practices in con ducting an independent assessment of the design of the facility. The CVA must certify in the Facility Design Report to MMS that the facility is designed to withstand the environmental and functional load condi tions appropriate for the intended service life at the proposed location.
From page 156...
... Make periodic onsite inspections while installation is in progress and satisfy the requirements of §295.710; and 5. Certify in a report that project components are fabricated and installed in accordance with accepted engineering practices; your approved COP, SAP, or GAP (as applicable)
From page 157...
... Alignment procedures; 13. Dimensional check of the overall structure, including any turrets, turret-and-hull interfaces, any mooring line and chain and riser tensioning line segments; and 14.
From page 158...
... Installation at the approved location according to the Facility Design Report and the Fabrication and Installation Report.
From page 159...
... After the CVA or project engineer files the certification report, you must notify MMS within 10 business days after commencing commercial operations.