From page 12...
... 13 and construction projects, the fundamental project delivery methods are D-B-B, D-B, and CM/GC. The primary procurement procedures are low bid, best value, qualification-based selection, and sole source selection.
From page 13...
... 14 In the second phase, the short-listed teams submit technical and price proposals. The TRC evaluates the technical proposals before opening the price proposals (ODOT 2006; MnDOT 2011; GDOT 2014)
From page 14...
... 15 best value process for this project involved evaluations for both cost and a set of best value criteria. The best value criteria included impact to the traveling public, speed of construction, and a proposer's ability to perform the work.
From page 15...
... 16 assure the various stakeholders that the proposal fulfils the larger public objectives (Hilger 2009)
From page 16...
... 17 required for D-B-B projects with minimal selection criteria. However, interviews, and sometimes presentations, may be required with large D-B projects that have complex technical or aesthetic features.
From page 17...
... 18 after GDOT's issuance of the Project's Notice to Proceed.
From page 18...
... 19 TRAINING Figure 8 illustrates the results of the survey with regard to training for best value procurement selection. Fourteen of 35 agencies (40%)
From page 19...
... 20 retained by a local unit of government to prepare or evaluate solicitation documents must be trained, either by the department or through other training, in the RFP process used for best value contracting for construction projects. Application of this manual cannot be substituted for the required training (MnDOT 2013)
From page 20...
... 21 the scoring of an Expanded Letter of Interest (ELOI)