Skip to main content

Currently Skimming:


Pages 62-78

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 62...
... 62 CHAPTER 6 Pilot Testing and Analysis on SHRP 2 L07 Product 6.1 Tool Introduction and Interface The objective of SHRP 2 L07 is to evaluate the cost-effectiveness of geometric design treatments in reducing nonrecurrent congestion. The L07 products help estimate traffic operational effectiveness and measure economic benefits of various design treatments.
From page 63...
... 63 o Emergency pull-off (rural area) o Extra high median barrier (eliminate rubbernecking)
From page 64...
... 64 Figure 6.3. Warning dialog for the OS X 10.6.8 operating system.
From page 65...
... 65 Figure 6.6 for freeways. Figure 6.5.
From page 66...
... 66 the incident duration reaches T The default values of T can be found in Figure 6.8.
From page 67...
... 67 L07 team should help provide more details about how they get these values and the reasons for setting up such coefficients so that users can decide whether they need to update these factors regarding different roadway geometries, locations, weather characteristics, culture, and more. Figure 6.9.
From page 68...
... 68 6.4 Performance Test Testing of L07 tool performance is conducted in three folds: (1) a comparison study is made with the DRIVE Net system to test the MOE sub-output, (2)
From page 69...
... 69 (a) Output of DRIVE (b)
From page 70...
... 70 Figure 6.12 shows the TTI curves calculated from single-loop data and the L07 tool. Three different hours (3:00 a.m., 8:00 a.m., and 5:00 p.m.)
From page 71...
... 71 Figure 6.12. Comparison of outputs from single-loop detector data and L07 tool.
From page 72...
... 72 6.4.3 Case Study To test the effectiveness of the L07 tool, the research team prefers finding a completed project with the same scope within Washington State. However, as the tool involves only 16 specific design treatments as mentioned in Section 6.1, an effective comparison requires a rigorous selection among previous construction projects.
From page 73...
... 73 Existing southbound cable barrier was left in place to provide redundant protection. The project also widened the median shoulders to 10 feet, bringing them to current standards.
From page 74...
... 74 hour demand slightly increased after the construction. Thus, the treatment did not result in a significant increase in traffic demand.
From page 75...
... 75 Table 6.1. Incident Numbers for I-5 Mileposts 199–209 Before After Decrease Year 2006 2007 2008 Mean 2011 2012 Mean % Property damaged only 17 23 30 23.3 2 8 5 78.6 Minor injury 6 3 7 5.3 3 2 2.5 53.1 Fatality 1 1 2 1.3 0 0 0 100 Non-crash 575 625 627 609 136 130 133 78.2 Total 599 652 666 639 141 140 140.5 78.0 Summarizing Table 6.1, the conclusion can be drawn that the treatment had a significantly positive effect on reducing traffic incidents, especially severe incidents.
From page 76...
... 76 Figure 6.16. L07 tool crash when crash reduction percentage is input at or near 100% (as in box for Minor Injury crashes at left)
From page 77...
... 77 Figure 6.17. L07 tool output for benefit–cost analysis.
From page 78...
... 78 6.5 Test Conclusions The research team believes that the L07 methodology on computing TTI curves should be further studied and compared. Neither the output comparison between L07 and DRIVE Net nor the software accuracy comparison between L07 before-treatment curve [see Figure 6.18 (b)

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.