Skip to main content

Currently Skimming:


Pages 1-215

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 1...
... SHRP 2 Reliability Project L38B Pilot Testing of SHRP 2 Reliability Data and Analytical Products: Minnesota
From page 2...
... SHRP 2 Reliability Project L38B Pilot Testing of SHRP 2 Reliability Data and Analytical Products: Minnesota Michael Sobolewski Minnesota Department of Transportation Roseville, Minnesota Todd Polum, Paul Morris, Ryan Loos, and Krista Anderson SRF Consulting Group, Inc. Minneapolis, Minnesota TRANSPORTATION RESEARCH BOARD Washington, D.C.
From page 3...
... © 2015 National Academy of Sciences. All rights reserved.
From page 4...
... DISCLAIMER The opinions and conclusions expressed or implied in this document are those of the researchers who performed the research. They are not necessarily those of the second Strategic Highway Research Program, the Transportation Research Board, the National Research Council, or the program sponsors.
From page 5...
... The National Academy of Sciences is a private, nonprofit, self-perpetuating society of distinguished scholars engaged in scientific and engineering research, dedicated to the furtherance of science and technology and to their use for the general welfare. On the authority of the charter granted to it by Congress in 1863, the Academy has a mandate that requires it to advise the federal government on scientific and technical matters.
From page 6...
... Contents 1 Executive Summary 1 Key findings and recommendations 5 CHAPTER 1 Introduction 5 Overview of Pilot Testing Process 7 Refined Testing Analysis 8 CHAPTER 2 TTRMS Development 8 Travel Time and Traffic Data 8 Transportation Information and Condition Analysis System Tool 11 Travel Time Data Extraction Process 13 Weather Data 20 Event Data 24 Crash and Incident Information 31 Road Work Data 32 TTRMS Database Development 32 Input Data Processing 34 TTRMS Database Format 34 TTRMS Analysis Tool 40 Aggregate Reliability Measures 45 CHAPTER 3 Reliability Report 45 Description of Facilities 45 Results Summary 55 Facility Observations 58 CHAPTER 4 Evaluation of the Project L07 Tool 58 Introduction 58 Initial Investigation 59 Findings Summary 59 Evaluation Process 65 Validation Comparison 73 Additional Sensitivity Testing and Exploration 77 Detailed Summary of Findings 79 Recommended Refinements 81 Opportunities for Future Testing of the L07 Tool 82 CHAPTER 5 Minnesota Reliability Workshop 82 Overview 83 Workshop Introduction 83 SHRP 2 Background and Concept 93 Technical Analysis of the SHRP 2 Tools 118 Utility of the SHRP 2 Tools 141 Review of Background and Concepts
From page 7...
... 142 Example Applications for Travel Time Reliability 176 Conclusions and Next Steps 182 Key Findings 186 CHAPTER 6 Refined Technical Analysis 186 Alternative Time Intervals 192 Disaggregation of Delay Causes 195 Demand Regimes 200 SMART Signal Traffic Data 201 Updated L07 Benefit-Cost Tool 204 CHAPTER 7 Findings and Recommendations 204 Project L02 205 Project L07 205 Project L05 207 References A-1 APPENDIX A Study Facility Reliability Reports B-1 APPENDIX B Test Results of L07 Tool Evaluation
From page 8...
... EXECUTIVE SUMMARY The Minnesota pilot site has undertaken an effort to test data and analytical tools developed through the Strategic Highway Research Program (SHRP) 2 Reliability focus area.
From page 9...
... A wide variety of graphical products and performance measures can be produced using results from the TTRMS database. The Minnesota pilot team found the following items provide the greatest value to potential audiences: • Surface plots • Pie charts • Cumulative density function (CDF)
From page 10...
... Minnesota team recommends restoration of this feature to provide more flexibility for performing cost-benefit analyses. The tool does not provide any functionality for traffic growth over the project's lifetime.
From page 11...
... Following the pilot testing technical work and outreach, MnDOT is committed to advancing reliability evaluation in its business practices. This was most clearly demonstrated by the success of the project example used for the I-94 traffic study conducted alongside the pilot testing work.
From page 12...
... CHAPTER 1 INTRODUCTION The Minnesota pilot site has undertaken an effort to test data and analytical tools developed through the second Strategic Highway Research Program (SHRP) 2 reliability focus area.
From page 13...
... Project L02 The L02 guidance was utilized to establish a framework for collection, storage, processing, and analysis of travel time data to evaluate reliability performance. First, the mechanics of this process were established in terms of data sources and their collection and processing techniques.
From page 14...
... Project L05 The Minnesota pilot team carried forward guidance developed in the L05 project to initiate a dialog regarding incorporation of reliability evaluation in the planning and programming process. This was accomplished through an extensive outreach effort over the course of the pilot testing work.
From page 15...
... CHAPTER 2 TTRMS DEVELOPMENT This chapter documents the development of a travel time reliability monitoring system (TTRMS) for the Minnesota pilot site.
From page 16...
... of Minnesota Duluth. This has led to the development of an interface program named the Transportation Information and Condition Analysis System (TICAS)
From page 17...
... Figure 2.2. Schematic of TICAS travel time calculation.
From page 18...
... Travel Time Data Extraction Process TICAS was used to extract the traffic data for the TTRMS and to perform additional calculations to derive the travel time and VMT information. TICAS calculates and provides cumulative travel time with records every 0.1-mile from the specified start point to the end point along the highway.
From page 19...
... Table 2.3 and Table 2.4 provide an example of the travel time and VMT data downloaded using TICAS. Table 2.3.
From page 20...
... Table 2.5. TTRMS Traffic Data Format Time Stamp Travel Time VMT 20090101 00:05 13.98 647.90 20090101 00:10 13.71 659.07 20090101 00:15 13.92 801.09 20090101 00:20 14.22 934.82 20090101 00:25 13.92 1089.63 20090101 00:30 13.68 1202.14 20090101 00:35 13.96 1238.10 This format provided the backbone for the TTRMS data structure.
From page 21...
... For each site, R/WIS has atmospheric (weather condition) and precipitation history tables available to view and export.
From page 22...
... The attributes reported from the precipitation history are the following: • Precipitation type • Precipitation intensity • Precipitation rate • Precipitation start time • Precipitation end time • 10 Minute precipitation accumulation • 1 Hour precipitation accumulation • 3 Hour precipitation accumulation • 6 Hour precipitation accumulation • 12 Hour precipitation accumulation • 24 Hour precipitation accumulation After reviewing the data provided by the atmospheric and precipitation history tables, it was determined that the four key attributes to be referenced in the database spreadsheet are • Precipitation Intensity: Intensity of the precipitation as derived from the precipitation rate. The National Weather Service defines the following intensity classes: light, moderate, or heavy.
From page 23...
... that reduced the rate at which data could be downloaded is that every 2 to 3 hours the website would become unavailable for up to 10 minutes. One year of atmospheric and precipitation history at one site requires approximately 10 hours of work.
From page 24...
... Weather Underground The third source of weather data considered was the online service Weather Underground, which was developed in 1995 as an offshoot of the University of Michigan's Internet weather database. Jeff Masters, a Ph.D.
From page 25...
... Figure 2.4. Weather Underground station locations.
From page 26...
... The one key attribute that the Weather Underground data was missing that was provided by the R/WIS data was the precipitation type. The R/WIS data reported the precipitation type as none, rain, frozen, snow, or other.
From page 27...
... precipitation totals from both sources were compared to historical weather data from the Minnesota Climatology Working Group and KARE 11 News. The precipitation reported by Weather Underground was much more consistent than the amount reported by R/WIS.
From page 28...
... Speed and volume observations were made for the following highways: • I-94: The selected loop detectors were located just east of the 5th Street off-ramp and the 6th Street on-ramp. The following results were recorded: − Arrival duration lasted 100 minutes and occurred up to 15 minutes before the start of the game.
From page 29...
... Minnesota Twins The Minnesota Twins are a Major League Baseball team that plays home games in downtown Minneapolis. For the Minnesota Twins, game data from 2006 to 2012 was found on Wikipedia, and game start times were identified from ESPN.com because they were not provided in the Wiki data.
From page 30...
... Additional Sources Two additional sources were used to collect information on events taking place in downtown Minneapolis. The Minneapolis Event Log, collected by the City of Minneapolis, provides data on the start and end time for events taking place in Minneapolis in 2012 (it did not exist prior to 2012)
From page 31...
... Table 2.7. TTRMS Even Data Formatting Event Record Number Date Start Time End Time Event Type 11 11/11/2012 11/11/2012 9:00 11/11/2012 12:00 Vikings_A 12 11/11/2012 11/11/2012 15:00 11/11/2012 17:00 Vikings_D 13 12/9/2012 12/9/2012 9:00 12/9/2012 12:00 Vikings_A 14 12/9/2012 12/9/2012 15:00 12/9/2012 17:00 Vikings_D 15 12/30/2012 12/30/2012 12:25 12/30/2012 15:25 Vikings_A 16 12/30/2012 12/30/2012 18:25 12/30/2012 20:25 Vikings_D 17 4/9/2012 4/9/2012 12:10 4/9/2012 15:10 Twins_A 18 4/9/2012 4/9/2012 17:40 4/9/2012 19:40 Twins_D 19 4/11/2012 4/11/2012 16:10 4/11/2012 19:10 Twins_A 20 4/11/2012 4/11/2012 21:40 4/11/2012 23:40 Twins_D Crash and Incident Information Crashes and other incidents are significant sources of travel time unreliability on the highway system.
From page 32...
... Computer Aided Dispatch Data The research team obtained the CAD database for the analysis years from the RTMC, which hosts the joint dispatch center with the State Patrol. The CAD data provide information about calls received by State Patrol 911 operators, call records, and emergency response actions.
From page 33...
... Figure 2.6. Schematic of DMS event detail description extraction.
From page 34...
... Conflation of Crash and Incident Records Many of the crash and incident records in the CAD, DMS, and MnCMAT databases are believed to represent the same events occurring on the highway. For example, in the case of a crash, the dispatcher would receive a 911 call and make an entry in the CAD system.
From page 35...
... Figure 2.8. Schematic of crash and incident record spatial join relationships.
From page 36...
... Table 2.8. DMS Crash and Incident Type and Estimated Duration Crash and Incident Type Estimated Duration (minutes)
From page 37...
... Crash Impact: The DMS records provided the best data source for roadway capacity, since the displays typically included messages such as "Crash on Shoulder" or "Left Lane Closed.". CAD data included less reliable impact data, subject to what the dispatcher elected to include in the database.
From page 39...
... effort, road work is defined as any agency activity to maintain or improve the roadway that may result in impacts to capacity. This may include short-term activities such as guardrail, sign, or lighting repair as well as more significant, long-term construction actions.
From page 40...
... to the other attributes. The code was eventually modified to include all timestamps, even for days with no traffic data.
From page 41...
... arrival) or "Vikings_D" (for departure)
From page 42...
... The analysis tool references the TTRMS database with all the associated records shown in Table 2.13. It is a macro-enabled spreadsheet which produces basic travel time reliability measures such as cumulative density function (CDF)
From page 43...
... Figure 2.9. Query tool CDF curve example.
From page 44...
... Figure 2.10. 2012 travel time surface plot for TH-100 northbound.
From page 45...
... Figure 2.12. 2012 weather surface plot for TH-100 northbound.
From page 46...
... Figure 2.14. 2012 incident surface plot for TH-100 northbound.
From page 47...
... Aggregate Reliability Measures The TTRMS analysis tool also provides users with aggregate reliability measures for the facility under evaluation. These measures include many of the tools described in previous SHRP 2 reliability literature, such as CDF curves and reliability indices.
From page 48...
... observed. In this example, a 5-minute interval was used, resulting in a total of 105,120 intervals in 1 year.
From page 49...
... Figure 2.17. 2012 observation frequency pie chart by regime.
From page 50...
... Figure 2.18. 2012 delay pie chart by regime.
From page 51...
... PTI = TT95%TTFreeFlow Planning Time Failure/On-Time Measures: Describes the percentage of trips with travel times within a certain factor of the median travel time. Common thresholds include 1.1 ∗ 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑇𝑇𝑇𝑇𝑀𝑀𝑇𝑇𝑀𝑀𝑇𝑇 𝑇𝑇𝑀𝑀𝑇𝑇𝑀𝑀 1.25 ∗ 𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀𝑀 𝑇𝑇𝑇𝑇𝑀𝑀𝑇𝑇𝑀𝑀𝑇𝑇 𝑇𝑇𝑀𝑀𝑇𝑇𝑀𝑀 Other formulations of these measures denote the percentage of trips with average speeds below a specified threshold: for example, 50 mph, 45 mph, or 30 mph.
From page 52...
... CHAPTER 3 RELIABILITY REPORT Description of Facilities Three study highways were selected for the Minnesota pilot testing of the SHRP 2 reliability products. The first facility analyzed was TH-100, starting at 77th Street in Edina and ending at 57th Avenue in Brooklyn Center.
From page 53...
... Facility Characteristics For each highway presented in the reliability report, a series of roadway characteristics are provided. These begin with a number of basic elements describing the facility's physical attributes and traffic demand.
From page 54...
... • Road Work • Event • Travel Time A key modification to these plots was that records without a given condition present are shown as blank rather than a color. This is intended to avoid confusion that a "None" condition is a part of the data, whereas this method correctly shows the blank areas represent the absence of records in the data.
From page 55...
... Figure 3.2. 2012 TH-100 northbound crash surface plot.
From page 56...
... Figure 3.4. 2012 TH-100 northbound road work surface plot.
From page 57...
... Traffic Data The traffic data is a continuous, rather than a discrete data source, and is therefore displayed differently in the surface plots compared to the nonrecurring conditions data. The traffic data category is comprised of the VMT and travel time observations.
From page 58...
... • 1.5-2.0 times the TTI • 2.0-2.5 times the TTI • 2.5-3.0 times the TTI • 3.0-3.5 times the TTI • 3.5-4.0 times the TTI • Greater than 4.0 times the TTI Figure 3.7. 2012 TH-100 northbound travel time surface plot.
From page 59...
... Figure 3.8. 2012 TH-100 northbound travel time CDF curve.
From page 60...
... Figure 3.9. 2012 TH-100 northbound observation pie chart.
From page 61...
... Figure 3.10. 2012 TH-100 northbound delay pie chart.
From page 62...
... Comparison Bar Charts The comparison bar charts shown in Figure 3.12 display the total delay separated by each year for a particular highway. The solid black bar represents the average volume of daily trips recorded along the facility.
From page 63...
... TH 100 Southbound Southbound TH-100 had higher VMT during the a.m. peak hour than northbound TH-100.
From page 64...
... I-94 Eastbound: Minneapolis to Saint Paul Eastbound I-94 between Minneapolis and Saint Paul consistently had a lower VMT each year than westbound I-94. In addition, the delay caused by events was higher in the eastbound direction compared to I-94 in the westbound direction.
From page 65...
... CHAPTER 4 EVALUATION OF THE PROJECT L07 TOOL Introduction The L07 tool was developed as an economic analysis tool to compare treatments that help mitigate nonrecurring congestion on freeway and major arterial segments. It is designed for use by agencies seeking a tool to assist with the analysis and prioritization of projects addressing nonrecurring congestion.
From page 67...
... • Can the L07 tool accurately replicate travel conditions along the highly congested test segment? • What is the value in developing additional detailed data for use in the L07 tool?
From page 68...
... Figure 4.1. Example incident input data.
From page 69...
... Detailed Scenario Geometry: Same process as the default scenario. Demand: Same process as the default scenario.
From page 70...
... Event data were used in combination with VMT data from the TTRMS database to determine the percent increase in traffic volume during events by hour of the day. VMT from the TTRMS could not be specifically defined to an individual event type, so all events were combined into a single recurring average event that occurred 46 days a year.
From page 71...
... Figure 4.3. Example event input computation for 1 hour of the day.
From page 72...
... Figure 4.4: Example work zone input data. Validation Comparison Validation of the L07 tool was performed by comparing the TTI percentile curves observed by the TTRMS to those produced by the L07 tool for both scenarios.
From page 73...
... Figure 4.5. Hourly travel time index profile: observed field data from L02 analysis.
From page 74...
... Figure 4.7. Hourly travel time index profile: L07 analysis with detailed inputs.
From page 75...
... Figure 4.8. Segment volume comparison of demand computed by L07 method vs.
From page 76...
... Figure 4.10. Morning peak (7:00 a.m.)
From page 77...
... Figure 4.12. Off-peak (3:00 a.m.)
From page 78...
... Figure 4.13. Hourly travel time index profile: L07 analysis with default inputs -- volume test Figure 4.14.
From page 79...
... Reviewing Figure 4.13 and Figure 4.14 shows that, for this particular segment, the 99th percentile curve shape matches the real-life conditions from the TTRMS data fairly closely (Figure 4.5) , but the other TTI curves remain relatively flat.
From page 80...
... Figure 4.16. Afternoon peak (4:00 p.m.)
From page 81...
... Figure 4.17. Speed computation comparison in the L07 tool.
From page 82...
... Figure 4.18. Crash rate calculation in the L07 tool.
From page 83...
... Table 4.1. Treatment Comparison: Low Demand/Low Incident Life Cost Maintenance B/C Ratio Accessible Shoulder 25 $250,000 $2,000 0.21 Alternating Shoulder 25 $150,000 $2,000 0.29 Crash Investigation Site 20 $50,000 $2,000 0.55 Emergency Pull-off 25 $10,000 $500 2.74 Emergency Access 20 $20,000 $1,000 0.89 Emergency Crossovers 30 $5,000 $500 2.61 Gated Turnarounds 20 $10,000 $3,000 0.57 Drivable Shoulders 25 $250,000 $2,000 0.12 Extra High Median Barrier 20 $30,000 $3,000 1.69 Runaway Truck Ramp 20 $50,000 $2,000 0.47 Incident Screen 20 $10,000 $5,000 0.32 Wildlife Crash Reduction 20 $45,000 $1,000 2.09 Anti-icing Systems 10 $50,000 $5,000 0.74 Snow Fence 10 $80,000 $4,000 0.61 Blowing Sand 10 $30,000 $5,000 0.2 It was concluded that benefit-cost (B/C)
From page 84...
... Table 4.2. Treatment Comparison: High Demand/High Incident Life Cost Maintenance B/C Ratio Accessible Shoulder 25 $300,000 $2,400 123.3 Alternating Shoulder 25 $150,000 $2,000 182.69 Crash Investigation Site 20 $50,000 $2,000 292.87 Emergency Pull-Off 25 $10,000 $500 1154.8 Emergency Access 20 $20,000 $1,000 8.61 Emergency Crossovers 30 $5,000 $500 18.18 Gated Turnarounds 20 $10,000 $3,000 6.05 Drivable Shoulders 25 $300,000 $2,400 0.57 Extra High Median Barrier 20 $30,000 $3,000 58.59 Runaway Truck Ramp 20 $50,000 $2,000 3.79 Incident Screen 20 $10,000 $5,000 2.64 Wildlife Crash Reduction 20 $4,500 $1,000 23.91 Anti-icing Systems 10 $50,000 $5,000 5.74 Snow Fence 10 $80,000 $4,000 4.69 Blowing Sand 10 $30,000 $5,000 0.2 Detailed Summary of Findings While using the L07 tool and performing detailed test scenarios, the pilot team discovered several challenges with compiling input data for use in the tool, which are detailed below: Demand Demand calculations have proven to be a challenge in tool calibration.
From page 85...
... analyst should determine the 30th highest hour or the year for each individual time slice. This creates a scenario where adjacent time slices could have demands occurring on different days of the year.
From page 86...
... across the entire 15 years of analysis. Additional guidance should be provided on how to address construction work zones that occur every few years.
From page 87...
... • Guidance stating that demand should be equal to volume over the course of a day. AADT could be used with hourly percentages to accomplish this.
From page 88...
... • Allow the user to input an amount of lane closures equal to the total lanes on the segment to account for work zones that close the entire roadway segment. − This is a common strategy used by MnDOT to accelerate maintenance projects.
From page 89...
... CHAPTER 5 MINNESOTA RELIABILITY WORKSHOP Overview The Minnesota pilot team hosted an interactive workshop on Thursday, February 20, 2014, to share the progress that the team had made on travel time reliability testing since April 2013 as part of the SHRP 2 L38B Reliability program. The purpose of the workshop was to introduce the concept of travel time reliability to stakeholders; demonstrate the utility and effectiveness of tools developed as part of the reliability research programs; share findings discovered while testing the reliability tools; and provide a forum to discuss future policy for making planning and programming decisions as reliability becomes implemented as a performance measure.
From page 90...
... − Benefit-Cost Enhancement − Other Applications • Closing Travel Time Reliability Survey • Next steps Workshop Introduction Presenter: Mike Sobolewski of the Minnesota Department of Transportation Figure 5.1. Welcome slide.
From page 91...
... SHRP 2 Background and Concept Presenter: David Plazak of SHRP 2 Following the introduction to the workshop, background information was provided to help audience members better understand the SHRP 2 Reliability focus area (see Figure 5.2 and Figure 5.3)
From page 92...
... An important concept from this portion of the workshop is that SHRP 2 is a large, targeted research program that has a limited amount of time associated with it and has built on the success of the original SHRP. The original SHRP ended in 1993 and resulted in several technologies, including SuperPave mix design and winter pretreatments.
From page 93...
... Opening Travel Time Reliability Survey Presenter: Renae Kuehl of SRF Consulting Group Once introductions were completed, an opening survey was conducted to gauge the audience's level of knowledge and understanding of travel time reliability. A series of nine questions was posed to the audience to gauge their understanding and use of reliability data.
From page 94...
... Figure 5.5. Reliability background.
From page 95...
... Figure 5.6: Minnesota pilot site. After beginning the reliability study, it took the team a short time to understand exactly what was being evaluated with these tools, using the wide range of data available.
From page 96...
... Figure 5.7. SHRP 2 reliability tools.
From page 97...
... Figure 5.9. SHRP 2 C11 tool.
From page 98...
... Figure 5.11. SHRP 2 L07 tool.
From page 99...
... The Minnesota team evaluated three SHRP 2 reliability products: • Project L02 Guide: Establishing Monitoring Systems for Travel Time Reliability. The purpose of the L02 tool was to compile different data sources into one data set for each study facility and to understand how the system is functioning today.
From page 100...
... Figure 5.13. Project schedule.
From page 101...
... Technical Analysis of the SHRP 2 Tools Project L02 Technical: Monitoring System Presenter: Paul Morris of SRF Consulting Group To begin, the presenter explained that during this part of the workshop, the audience would be looking at numbers and graphics to illustrate how the team performed their analysis. The purpose of this tool is to have a better understanding of travel time when it's not an ideal weather condition, or when there are other events impacting the system (e.g., a crash on the side of the road)
From page 102...
... Figure 5.16. TH-100 northbound (NB)
From page 103...
... Figure 5.17. TH-100 NB travel times.
From page 104...
... Figure 5.18. TH-100 NB 2012 CDF curve.
From page 105...
... Figure 5.19. Pie chart of observations of nonrecurring conditions.
From page 106...
... Figure 5.20. Pie chart of delay by nonrecurring conditions.
From page 107...
... To develop a database using the crash and incident data that was collected, the L02 guide was used. (See Figure 5.22.)
From page 108...
... Figure 5.23. Weather surface plot.
From page 109...
... Figure 5.25. Incident surface plot.
From page 110...
... Figure 5.27. Road work surface plot.
From page 111...
... Figure 5.28. VMT surface plot.
From page 112...
... Figure 5.30. Travel time CDF curve.
From page 113...
... Figure 5.31. Delay pie charts.
From page 114...
... Figure 5.33. Project L02 system monitoring.
From page 115...
... Project L07 Technical: Alternative Analysis Presenter: Ryan Loos of SRF Consulting Group To begin this portion of the workshop, background information about the L07 tool was provided (see Figure 5.34)
From page 116...
... Additional background information is shown in Figure 5.35. Figure 5.35.
From page 117...
... The same elements of nonrecurring congestion defined in the L02 technical portion of the workshop are used in the L07 tool. This tool compares treated versus untreated geometric conditions that the analyst chooses.
From page 118...
... Figure 5.38. Calculating delay.
From page 119...
... The optional detailed user inputs are shown in Figure 5.40. Figure 5.40.
From page 120...
... Figure 5.41. L07 design treatments.
From page 121...
... While it may appear that the L07 tool uses inputs from data sources that may not be available to perform the analysis, at a bare minimum most agencies should be able to use this tool to perform a benefit-cost analysis for these geometric treatments. The scenario that was shown at the workshop was a generic facility type of roadway experiencing nonrecurring congestion.
From page 122...
... Figure 5.43. SHRP 2 reliability tools.
From page 123...
... Figure 5.44. L05 implementing reliability.
From page 124...
... Figure 5.45. Policy and programming discussion.
From page 125...
... Figure 5.46. Performance measures.
From page 126...
... Communicating reliability was the next topic discussed. There are many audiences for the evaluation of travel time reliability, so it is challenging to present the large amount of technical analysis in an effective way that is understandable to the audience and enables them to grasp the implications of the analysis.
From page 127...
... Figure 5.49. Utility of SHRP 2 tools.
From page 128...
... Figure 5.51. Utility of SHRP 2.
From page 129...
... A primary concern of the pilot teams about these tools is whether or not they are providing users with new information. MnDOT, in particular, has established efficient methods for producing congestion and safety reports.
From page 130...
... Loop detectors were the principal source of traffic volumes for the facilities analyzed by the Minnesota team (see Figure 5.54)
From page 131...
... Figure 5.55. Bluetooth.
From page 132...
... SMART Signal data is another source of data for signalized highways. This is a proprietary program where data are processed through special software to provide speed, travel time, and other performance measures.
From page 133...
... Figure 5.58. Crash and incident data sources.
From page 134...
... only affect a portion of it, thus missing the sensors. The Minneapolis-Saint Paul airport data can also provide a reference for weather data.
From page 135...
... Figure 5.61. Work zone data sources.
From page 136...
... Figure 5.62. I-94 westbound example.
From page 137...
... Figure 5.64. L07 lessons learned.
From page 138...
... Figure 5.65. L07 product refinements.
From page 139...
... Figure 5.66. L07 reliability solutions.
From page 140...
... Figure 5.68. Reliability solutions.
From page 141...
... Figure 5.69. Planning and programming.
From page 142...
... Figure 5.70. Implementation issues.
From page 143...
... Figure 5.71. L05 tool applications.
From page 144...
... The presenter explained that there needs to be a balance between minor details and the big picture when new tools are integrated into existing processes. The user needs to step back and "see the forest for the trees." It is anticipated that this will be a difficult transition.
From page 145...
... Conclusions from Utility of SHRP 2 Tools Presenter: Mike Sobolewski of the Minnesota Department of Transportation All of the background information presented up to this point of the workshop was aimed at preparing the audience for the upcoming discussion. There were a few final questions for consideration posed to the audience.
From page 146...
... Figure 5.75. Implementation considerations.
From page 147...
... Figure 5.77. Final thoughts.
From page 148...
... Figure 5.78. Final thoughts.
From page 149...
... Figure 5.79. SHRP 2 reliability tools.
From page 150...
... Figure 5.80. Panelists.
From page 151...
... I-94 Maple Grove to Rogers Presenter: Paul Morris of SRF Consulting Group This is an example of an actual corridor study along I-94 in the northwest metro area that was one of the Minnesota pilot site test segments. This segment is highlighted in Figure 5.81.
From page 152...
... Figure 5.82. I-94 Travel time reliability evaluation.
From page 153...
... Figure 5.83.
From page 154...
... CDF curves were also developed for this example. Figure 5.85 shows the cumulative percentage of traffic that is able to get through the corridor at or below the specified travel time (which is along the x-axis)
From page 155...
... of vehicles on the roadway; it does not take into account whether there is more than one person in a single vehicle. This was one of the criticisms the team had, and the team speculates that there will be future improvements to adjust for occupancy.
From page 156...
... The travel time surface plot for the year 2008 is shown in Figure 5.87. Figure 5.87.
From page 157...
... Figure 5.88. I-94 2009 travel time.
From page 158...
... There was a concrete joint repair project that took place during September, October, and November of 2010, which the tool was able to capture. While this project only decreased the capacity by one third, the backups it caused were several miles long and lasted the entire day.
From page 159...
... Figure 5.91. I-94 annual traffic and delay.
From page 160...
... Figure 5.92. I-35 in Lakeville.
From page 161...
... commuter peak, which is why there is a consistent band of higher VMT between 6:00 a.m.
From page 162...
... Figure 5.95. I-35 in Lakeville travel time.
From page 163...
... Additional comments about the process for this bare minimum analysis are highlighted in Figure 5.97. Figure 5.97.
From page 164...
... Figure 5.98. Level-of-effort graph.
From page 165...
... Figure 5.99. Value of a shoulder.
From page 166...
... Figure 5.101. Value of a shoulder.
From page 167...
... Project assumptions and data sources are highlighted in Figure 5.103. Figure 5.103.
From page 168...
... Figure 5.104. Value of a shoulder analysis results.
From page 169...
... Figure 5.105. Year 2040 hourly nonrecurring delay comparison.
From page 170...
... The conclusions and considerations from this analysis are highlighted in Figure 5.107. Figure 5.107.
From page 171...
... Figure 5.108. Florida reliability.
From page 172...
... Figure 5.110. Reliability indices.
From page 173...
... Transportation (DOT) using this information looks like.
From page 174...
... sources and will apply the results of the analysis to evaluations of projects in spring–summer 2014. Figure 5.113.
From page 175...
... Figure 5.115. Project evaluation process.
From page 176...
... The team selected a group of highway sample sections that would be used to collect and analyze traffic and travel time data to develop this model. The first step was to categorize the highways by road type and facility function, as shown in Figure 5.117.
From page 177...
... Figure 5.118. Highway sample sections.
From page 178...
... Figure 5.119. Annual traffic profile.
From page 179...
... In the end, the team found 109 different unique day types, 25 of which are holiday- or event-related (see Figure 5.121)
From page 180...
... Figure 5.122. INRIX speed data.
From page 181...
... Figure 5.123. INRIX speed data.
From page 182...
... Figure 5.124. Weather/crash/incident data.
From page 183...
... Figure 5.125. Model estimation process.
From page 184...
... Other Applications Presenter: Mike Sobolewski of the Minnesota Department of Transportation There are many other applications where travel time reliability evaluation can be used. There is some functionality of these tools to many different programs, which are highlighted in Figure 5.127 to Figure 5.129.
From page 185...
... Figure 5.128. CMSP secondary screening example application.
From page 186...
... Conclusions and Next Steps Closing Travel Time Reliability Survey Presenter: Renae Kuehl of SRF Consulting Group A travel time survey that was administered at the beginning of the workshop was taken again by the workshop participants, to gauge the level of knowledge they gained after participating in the Minnesota Reliability Workshop. The results from the afternoon survey were compared with the results from the morning survey and are shown (in percentage of total votes)
From page 187...
... Figure 5.131. Question 2 results.
From page 188...
... Figure 5.133. Question 4 results.
From page 189...
... Figure 5.135. Question 6 results.
From page 190...
... Figure 5.137. Question 8results.
From page 191...
... Ongoing SHRP 2 Projects The determination of the reliability ratio is an important factor, as it is an assumed parameter in many reliability analysis tools. This number is different for different highway users, and different users have different needs as far as reliability is concerned.
From page 192...
... Project L07 Tool • Audience members expressed concern about the level of effort required to perform a fully detailed analysis, and they expressed concern that in some cases detailed data would not be available at all. • There was also concern expressed about the level of effort required to perform a systemlevel analysis using this tool.
From page 193...
... CHAPTER 6 REFINED TECHNICAL ANALYSIS Alternative Time Intervals The majority of the reliability analysis performed by the pilot team used 5-minute intervals; however, it was never determined if this was the optimal length. The travel time reliability monitoring system (TTRMS)
From page 194...
... Figure 6.1. Westbound I-94 observation pie charts.
From page 195...
... Figure 6.3. Northbound TH-100 observation pie charts.
From page 196...
... These pie charts show that as the size of the time interval increases, the amount of delay occurring during the periods with nonrecurring conditions increases. This is because the database methodology was to apply nonrecurring conditions to any interval in which they were present for any length of time.
From page 197...
... indicate a strong fit between the data sets. Similarly, correlation values close to one indicate that changes in one data set are reflected in the other.
From page 198...
... Figure 6.6. Total annual delay.
From page 199...
... The team concluded that the ideal time interval appears to be in the 10- to 15-minute range. These time intervals optimize the trade-off between accuracy of aggregate performance measures and staff and computing resources.
From page 200...
... Figure 6.9. Speed-flow plot example.
From page 201...
... Figure 6.11 shows the database the team used to separate the delay caused by nonrecurring factors. The difference between the observed travel time from the nonrecurring congestion (Column B: yellow)
From page 202...
... Figure 6.12. Updated pie chart.
From page 203...
... Figure 6.13. Project L02 example CDF graph with high, medium, and low demand regimes.
From page 204...
... Figure 6.14.
From page 205...
... Figure 6.15. Density vs.
From page 206...
... Figure 6.16. Demand thresholds.
From page 207...
... Figure 6.17. Demand regime thresholds.
From page 208...
... requiring thousands of manual steps to obtain a meaningful sample of data over months or years. Second, along the portion of TH-13 the team was analyzing, only 8 days of data were found to be available in the 2012 to 2013 time frame.
From page 209...
... Table 6.4. L07 Tool Test Scenarios Scenario Specified Information Scenario 1 Number of crashes (default scenario)
From page 210...
... Scenario 3 shows no difference compared to the default scenario. Upon further investigation, it was determined that the L07 tool does not read the number of incidents if the duration is not specified.
From page 211...
... CHAPTER 7 Findings and Recommendations This section highlights the key findings that were discovered through the pilot testing process. These topics are discussed in greater detail throughout this report; however, the following points provide a summary of critical takeaways for individuals and agencies considering adoption or exploration of the SHRP 2 reliability tools.
From page 212...
... Project L07 The L07 project evaluation tool is applicable to freeway facilities and is capable of analyzing one segment with uniform geometry and volume characteristics. When considering use of the L07 tool, it is critical to identify the primary bottleneck location along a congested freeway facility.
From page 213...
... • There is concern over the level of effort to conduct reliability evaluation. In particular, lack of consistency in crash, incident, and road work data sources make linking these congestion causes to unreliable travel times time-consuming.
From page 214...
... References Cambridge Systematics, Inc., Texas A&M Transportation Institute, University of Washington, Dowling Associates, Street Smarts, H Levinson, and H
From page 215...
... APPENDIX A Study Facility Reliability Reports A-1

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.