Skip to main content

Currently Skimming:


Pages 151-170

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 151...
... D-1 General Use of Tool System Requirements • The tool is intended to run in Microsoft Excel 2010 or 2013; macros must be enabled for the tool to run properly. • The tool has been tested in a Windows 7 environment; user experience may differ in other operating system environments.
From page 152...
... D-2 5. Once the project information is entered into the heading of the Project Location worksheet, the remaining headings on subsequent worksheets will be updated to match.
From page 153...
... D-3 Each input form contains stepwise instructions and a key to the color of cells that appear in the form. Color coding identifies cells as: User Steps Default data; editing allowed with rationale User Entered Data Guidance Lookup Data; do not edit cells Warnings The user is expected to enter data for each "User Entered Data" cell at a minimum, and should review the default and reference values to verify that they are appropriate.
From page 154...
... D-4 3. Select the precipitation gage that best represents the project precipitation by using the drop-down menu under "Rain Gages Available in State." Generally, the precipitation gage closest to the project location should be used.
From page 155...
... D-5 concentration" column. Note that if you select "yes" to the default or "yes" to the question above about editing the defaults, the specific pollutant or all pollutant concentrations will be reset to the default concentration(s)
From page 156...
... D-6 Entering Capital and Maintenance Costs Information If detailed capital and maintenance costs are available, selecting "yes" to the previous question about editing these costs will unhide two worksheets: "Capital Costs" and "Maintenance Costs." If including the cost of a bridge deck conveyance system, the costs would be input under these tabs. Use the following steps to update the cost information: 1.
From page 157...
... D-7 better BMP area infiltration rate data are available, such as that obtained from field testing. It is strongly recommended that default infiltration rate values should be updated with site-specific information whenever available.
From page 158...
... D-8 Note: Guidance regarding the individual BMP parameters is not provided in this guide. Please refer to the "Guidance" and "Default Value" columns located within the Tool that provide guidance for each parameter specific to the BMP selected.
From page 159...
... D-9 Figure D-9. Volume performance tabular and graphical results.
From page 160...
... D-10 Error Messages This tool provides volume reduction estimates by referencing tens of thousands of hydrologic simulations. Because an individual simulation is not being run for each individual project, this tool has some inherent limitations.
From page 161...
... D-11 Bridge Deck Drain System Cost Support Tool A separate spreadsheet is provided to aid the practitioner in computing the cost of the deck drain system, if one is needed to convey runoff to the bridge abutment. The capital cost for the conveyance system is added to the estimate computed by the BMP Evaluation Tool by clicking the Project Options tab to reveal the screen shown in Figure D-13: The user should change the blue input field to "yes" for view/edit of the capital and maintenance cost inputs as desired.
From page 162...
... D-12 being modeled. The detailed capital cost screen in the evaluation tool is shown in Figure D-14, and the field highlighted where the bridge deck conveyance system cost can be entered.
From page 163...
... Figure D-16. Inputs and outputs for the bridge deck drainage system cost estimate tool.
From page 164...
... D-14 runoff from the bridge deck if the longitudinal slope will not support a gravity drain system. Note that the pumping cost is provided to aid the practitioner in demonstrating the infeasibility of a pumped system.
From page 165...
... D-15 Figure D-18. Bridge deck inlet.
From page 166...
... D-16 Narrative The spreadsheet is subdivided into four main parts: Part 1: Input -- Bridge Geometry/Rainfall Variables Part 2: Shoulder/Inlet Flow Capacity and Inlets Quantity/Spacing Part 3: Bridge Deck Drainage System Configuration Part 4: Deck Drainage Total Cost/Unit Cost Figure D-21. Collector pipe hanger.
From page 167...
... D-17 Part 1: Input -- Bridge Geometry/Rainfall Variables The user has the flexibility of varying the following input parameters: • Length of bridge • Width of bridge • Width of gutter/shoulder • Deck grade (longitudinal slope) • Deck cross section slope • Rainfall intensity The length of the bridge can be varied from 60 ft to 10,000 ft.
From page 168...
... D-18 sidewalk, that conveys water during a storm runoff event. It may include a portion or all of the shoulder.
From page 169...
... D-19 The distance from the beginning of bridge to the first inlet is then calculated at a point at which the flow width equals the shoulder width. The spacing of the drains is then a resultant of the flow intercepted and width of bridge.
From page 170...
... D-20 The cost of each item is determined based on the weight of the item and a unit cost (including 10% contingency) of $6.10/lb of steel.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.