Skip to main content

Currently Skimming:


Pages 21-46

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 21...
... 21 Introduction The field composite pavement sections used in the structural modeling included a combination of special research sections in the United States and Canada and regularly constructed projects in Europe.
From page 22...
... 22 test Sections at MnrOaD Introduction In May 2010, two full-scale PCC/PCC test sections were constructed on I-94 at MnROAD to emulate best practices of constructing PCC/PCC composite pavements. Before the construction of the mainline test sections, a 200-ft two-lane test strip was constructed at the MnROAD facilities.
From page 23...
... 23 term "low-cost" signifies that the PCC design was such that the lowest possible amount of cement and most inexpensive coarse aggregates were used by the contractor. In addition, various textures were considered for the surface PCC layer.
From page 24...
... 24 Construction of the Test Sections The construction project was awarded to C
From page 25...
... 25 Subgrade Soil Grading and Compaction A string line was set for trimming of the subgrade and the base. The subgrade was cut with a trimming machine (Figure 2.9)
From page 26...
... 26 available natural fine aggregates, and a coarse RCA as a lowcost alternative coarse aggregate. All basic components of the lower-layer PCC were selected in light of a desire to reduce costs, investigate methods of sustainability, and investigate the reuse of materials into structural components.
From page 27...
... 27 cementitious materials including, but not limited to, fly ash. Fly ash replacement of 60% was approved and used in the final mix design for the low-cost PCC mix.
From page 28...
... 28Table 2.4. Aggregate Gradation for PCC Mixes Designation 37.5 mm (1½ in.)
From page 29...
... 29 of the slab. Temperature sensors were located in each of the different pavement structures so that the seasonal, daily, and construction temperature profiles that developed could be documented.
From page 30...
... 30 .5" 1.5" 2.5" 3.25" 4" 6" 8" 9" 13" 17" 20" 26" 6" PCC Special 2 8" Class 5 Existing Clay Subgrade Wheelpath Legend Static Strain Gauge Thermocouple Sensor Fence Centerline Riser BD Pedestal Conduit Dynamic Strain Gauge Moisture Gauge Thermocouple TreeHand hole 12' 10' Bit Shoulder 15' 15' 15' 15' 15' Static PanelsDynamic Panels Spacing PanelNo Sensors ~45' P1P2P3P4P5 3" 2" 3" 2" 4" 4" New Cab 2-4" Passing Lane Driving Lane N 3" PCC Special 1 Figure 2.12. Elevation and plan view of instrumentation layout for PCC/PCC test sections at MnROAD.
From page 31...
... 31 Figure 2.13. Instrumentation installed prior to placement of the PCC to measure pavement responses to temperature and traffic loads (static strain gauge, top left; dynamic strain gauges, bottom left; humidity sensors, top right; temperature sensors [thermocouple tree]
From page 32...
... 32 Figure 2.15. Paving train constructing R21 test sections along I-94 at MnROAD (from left to right: the mixer truck, first paver, belt placer, and second paver)
From page 33...
... 33 Another concern about delays included the integrity of the bond at the interface of the two lifts. An ultrasonic tomography testing device was used to assess the bond at the transverse joints and at midslab locations on the demonstration slab.
From page 34...
... 34 Paving the mainline sections progressed at a rate of between 1 and 4 ft per minute, and the project contractor was confident that this rate would be greatly increased with a larger project and a consistent supply of PCC for paving. While joint cuts sawed to a depth of 3 in.
From page 35...
... 35 to achieve a coarse aggregate of a desired size. Early estimates missed the amount of recycled concrete required, which led to only 275 ft of PCC/PCC using the RCA mix being paved, instead of the originally planned 475 ft.
From page 36...
... 36 of the surface treatment were delayed because of mechanical problems on the finishing platform, which provided insufficient pressure to the spray nozzles. The treatment (Figure 2.23)
From page 37...
... 37 of brushing was determined using a combination of a sand patch test and an aggregate peak counting test (Figure 2.25)
From page 38...
... 38 have good air void distribution for protection against freeze– thaw damage. Noise Measurements Construction of the EAC finish was attempted because of its durability and because it channels water away from the wheel path in multiple directions.
From page 39...
... 39 Figure 2.27. OBSI device.
From page 40...
... 40 Source: Akkari and Izevbekhai 2011.
From page 41...
... 41 Table 2.6. PCC/PCC Composite Pavement Field Sections Composite Pavement Type Location Construction Year and Traffic Comments 3-in.
From page 42...
... 42 Table 2.6. PCC/PCC Composite Pavement Field Sections Composite Pavement Type Location Construction Year and Traffic Comments 3-in.
From page 43...
... 43 Table 2.6. PCC/PCC Composite Pavement Field Sections Composite Pavement Type Location Construction Year and Traffic Comments 3-in.
From page 44...
... 44 Table 2.6. PCC/PCC Composite Pavement Field Sections Composite Pavement Type Location Construction Year and Traffic Comments 1.5-in.
From page 45...
... 45 Table 2.6. PCC/PCC Composite Pavement Field Sections Composite Pavement Type Location Construction Year and Traffic Comments 3-in.
From page 46...
... 46 Table 2.6. PCC/PCC Composite Pavement Field Sections Composite Pavement Type Location Construction Year and Traffic Comments 3-in.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.