... 38 INTRODUCTION As described in Chapter 4, the base project describes the planned project scope, strategy, conditions, and assumptions. However, projects do not always go as planned, particularly when projects involve new or innovative methods like rapid renewal projects do.
From page 41...
... 39 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS RISK IDENTIFICATION • Set the stage for subsequent steps in the risk management process, which include -- Risk assessment (Chapter 6) ; -- Risk analysis, if needed (Chapter 7)
From page 42...
... 40 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS -- What could cause the risk to occur? (What are the causes or triggers, and how would they be recognized?
From page 43...
... 41 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS 2. Circulate base information to the participants beforehand.
From page 44...
... 42 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS To ensure a smooth and effective risk identification exercise, consider the following guidance (which parallels some of the previously identified principles) : • Document all credible possibilities outside the base set of assumptions to develop a comprehensive set of risks and opportunities (separate from potential risk management actions)
From page 45...
... 43 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS develop a more comprehensive, yet still usable, checklist of risk categories, or types of risks, that could occur for rapid renewal projects. This checklist of rapid renewal risk categories is presented in Appendix B: • The Risk Checklist for Traditional Transportation Projects section provides a summary of types or categories of risks for traditional (non–rapid renewal)
From page 46...
... 44 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS -- Table B.3. Environmental Process and Permits -- Table B.4.
From page 47...
... 45 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS Figure 5.2. Forms (Appendix C)
From page 48...
... 46 GUIDE FOR THE PROCESS OF MANAGING RISK ON RAPID RENEWAL PROJECTS Example The hypothetical QDOT case study (see Appendix D) and associated risk management plan (RMP; see Appendix E)