Skip to main content

Currently Skimming:


Pages 70-164

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 70...
... 70 C h a p t e r 3 Overview Sixteen ABC design concepts developed by the R04 team in Phase I have been described with concept sketches and photographs in Chapter 2. They include new concepts, or adaptations of existing concepts, that are proposed as solutions to various ABC problems.
From page 71...
... 71 44 Decked stringer system; and 44 Decked trapezoidal box girders. • Segmental superstructure systems 44 Box girders; 44 Segmental slabs; and 44 Segmental voided slabs.
From page 72...
... 72 equipment. The deck segment concepts incorporate proven elements and details used by several states.
From page 73...
... 73 rapid replacement applications. Omitting the concrete topping and the transverse posttensioning will significantly reduce the on-site time for construction.
From page 74...
... 74 Segmental channel SectionS These sections have not been widely used in the United States, or other markets. They are limited in width (typically two lanes)
From page 75...
... 75 3. If the deck is to be posttensioned, this operation is then performed.
From page 76...
... 76 panels can be designed as either continuous over a series of parallel girders or simply supported over the longitudinal girder. Figure 3.7 depicts an example of precast reinforced concrete panels used by the Utah DOT on the C-437 bridge rehabilitation of the county road over I-80 to Wanship.
From page 77...
... 77 thinner than a CIP deck due to the existence of internal tendons in one or both directions. Thinner panels translate into a lighter-weight deck, which could improve the live-load rating of older bridges.
From page 78...
... 78 Following installation of the full-depth precast deck panels, the panels were adjusted and leveled for grade and a smooth, flush riding surface. UHPC joint material was transported to the joints by power buggy and then dumped directly into the joints without any vibration, which is an acceptable practice for this material.
From page 79...
... 79 Modular superstructure systems are particularly suited to be used as Tier 1 concepts for weekend bridge superstructure replacements or as Tier 2 concepts, when the entire bridge may be scheduled to be replaced within a month using a detour to maintain traffic. DeckeD Stringer SyStemS Prefabricated decked steel stringer systems have been a very popular option for accelerated construction of bridges in this country.
From page 80...
... 80 Generally, low carbon content is a prerequisite to good formability in bent plate applications. Steel plates are more readily formed with the bend axis transverse to the rolling direction of the plate.
From page 81...
... 81 conceptual DeSign for compoSite Bent plate Box girDer SyStem A preliminary load and resistance factor design (LRFD) was performed for a bent plate box girder system.
From page 82...
... 82 AASHTO LRFD Specifications also include limits for the cross-sectional proportions, most of which are based on the thickness of the steel plate. Since the steel plate thickness is fixed at 0.5 in., it is possible to calculate upper-bound values for the depth of the box girder, and also for the upper flange width: • Per AASHTO LRFD 6.11.2.1, maximum depth for the box girder is 75 in.
From page 83...
... 83 required further research, testing, and code development. Headed reinforcing bars, as indicated in NEXT D Beams Standards by the Precast/Prestressed Concrete Institute Northeast, also could be used with closure pours.
From page 84...
... 84 Connections for Modular Superstructure Systems The ease and speed of construction of a prefabricated bridge system is paramount to its acceptance as a viable system for rapid renewal. Additionally, as discussed, connections between the modular segments can affect the live-load distribution characteristics, seismic performance of the superstructure system, and also the superstructure redundancy.
From page 85...
... 85 Two alternates may be considered for passively reinforced joints for modular construction at heavy truck traffic sites: • Full moment connection using ultra-high-performance concrete (UHPC) joints.
From page 86...
... 86 • The compressive strength gain behavior of UHPC is an important characteristic of the concrete. UHPC does not have any compressive strength for nearly 1 day after casting.
From page 87...
... 87 moDerate-to-light truck traffic SiteS: Shear-only connection By WelDing anD grouting Connections that transfer shear only may be adequate for local roads. This detail has the advantage of reduced construction time, lower cost, and easy adaptability to all types of modular systems.
From page 88...
... 88 In-place voided slabs were commonly used during the early period of prestressed concrete bridge development within the span range of 80 to 115 ft and with span-to-depth ratios of up to 20 to 25. Adapting the precasting plant to different deck widths would also be simpler and less expensive.
From page 89...
... 89 certain projects, such as those in which the bridge is so wide that the individual panels are simply too large to be economically transported to the site and installed using moderately sized equipment, or those that are constructed in stages and require the shifting of traffic from one lane to another during replacement of an existing deck. In many heavily traveled bridge replacement scenarios, a structure is closed during overnight or weekend hours for bridge deck replacement and then reopened to traffic in the morning.
From page 90...
... 90 recommendations should be considered for inclusion in future interim specifications: • Guidelines for stress requirement on the panels for stage construction or full construction. It is anticipated that stress requirement for stage construction is higher than that for full construction.
From page 91...
... 91 To the traveling public, the smoothness of the riding surface is a significant riding comfort issue. This is also an important factor for durability and maintenance, as vibrations from an irregular surface can affect the structural steel components of a bridge.
From page 92...
... 92 varies with stress and the age of concrete. The effects of creep on deflections are difficult to estimate.
From page 93...
... 93 to diminish the investment and the mobilization and demobilization costs. A support girder for short bridges would have the following: • Simplified self-launching capability.
From page 94...
... 94 that existed when they were match cast against each other. This is facilitated by the presence of shear keys on the webs and alignment keys on the slabs, which guide the segment into position.
From page 95...
... 95 example illustrating the erection of a segmental solid slab is shown in Figure 3.16. With the span-by-span method, all the segments for a span are positioned before the prestressing tendons are installed and the complete span is lowered onto the bearings.
From page 96...
... 96 often used in this case because of the less stringent geometry tolerances. With long-line match casting, two foundation beams support the entire segmental span during construction.
From page 97...
... 97 In the case of an integral abutment bridge with a longitudinally posttensioning deck, a cast-in-place closure pour is required to create a monolithic connection to the abutment, which provides for moment transfer. In either of these cases, the need for appropriate curing time of the closure pour can significantly affect the time savings expected in accelerated construction and somewhat retards the purpose of rapid construction.
From page 98...
... 98 circumstances, this spacing is based on the fatigue capacity of the studs, and not the ultimate capacity. With precast panels it is beneficial, however, to place the shear connector blockouts at the largest spacing possible.
From page 99...
... 99 When this method is used, the clear distance between the bottom of the panels and the top of the girders can become very large near the ends of the bridge, making it difficult to level the panels and form the haunch region. • Leveling the full-depth panels with the girder profile a short depth above the girder.
From page 100...
... 100 for a typical DOT grade-separation bridge deck, as summarized in Table 3.3. The contractor is assumed to have considerable experience with DOT bridges, but not necessarily with posttensioned deck panels.
From page 101...
... 101 longitudinal joint along the centerline, it may be possible to remove half the deck, replace it with precast panels, switch traffic to the new deck, replace the other half the deck with precast panels posttensioned longitudinally, and finally connect the halves with transverse posttensioning. • Long viaduct deck replacement that cannot be completed in a single, continuous concrete placement.
From page 102...
... 102 11. Contractors would be more willing to make equipment purchases if bridge construction became more standardized or industrialized, and was based on certain methods of erection to speed the assembly.
From page 103...
... 103 Items 4 and 5 There are concerns about the durability of joints and connections in precast elements. There are concerns about seismic performance of precast elements and connections in seismic regions.
From page 104...
... 104 certain methods of erection to speed assembly. Repetitive use will allow contractors to amortize equipment costs over several projects, which is an important component to bring overall costs in line with conventional construction.
From page 105...
... 105 A number of these important topics are currently under investigation by researchers around the country. These needs can be addressed through a combination of theoretical analysis, numerical analysis, or laboratory testing.
From page 106...
... 106 prepared for these systems. Deck bulb tee, deck double tee, and decked steel stringer systems received the highest scores, as these are proven systems for rapid renewal.
From page 107...
... 107 is currently envisioned for short spans with no end continuity. Further research and development will be needed to validate a design approach for the negative bending regions.
From page 108...
... 108 different perspectives when compared with the other superstructure elements presented in this report. First, full-depth precast concrete deck panels, whether posttensioned or used with a variety of cast-in-place joint materials, are the only elements presented that are truly applicable to both the complete replacement of existing bridges and also in the rapid replacement of a deteriorated bridge deck where the underlying superstructure remains in serviceable condition.
From page 109...
... 109 Posttensioning If posttensioning (PT) is used, the following additional recommendations should be considered: • PT force should be applied to only the precast deck to obtain the greatest effective prestressing force in the concrete deck.
From page 110...
... 110 • Precast complete pier systems 44 Whole pieces, footing, shaft, cap; and 44 Support options, piles, shafts, spread footing. • Segmental columns and piers 44 Segmental columns; 44 Pier caps; and 44 Footings.
From page 111...
... 111 Design Concept Descriptions Precast Modular Abutments Precast modular abutments are composed of separate components fabricated off site, shipped, and then assembled in the field into a complete bridge abutment. Precast modular abutments have been constructed in several states.
From page 112...
... 112 reinforcing. Once in place over the wingwall drilled shaft, the wingwall pocket is filled with high early strength concrete.
From page 113...
... 113 transportation regulations and erection equipment. Alternatively, the cap length limitation can be avoided by using multiple short caps combined to function as a single pier cap.
From page 114...
... 114 additional testing such as seismic response and strength tests of connections are recommended to gain confidence from designers nationwide. Over the next several years, these structures will undergo the scrutiny of maintenance inspections.
From page 115...
... 115 piers are constructed by posttensioning the precast cap to the precast column. Additionally, precast caps on cast-in-place columns and complete segmental piers have been used and have proven to be successful on many projects.
From page 116...
... 116 Shear along the joint surface of the column is adequately resisted in most instances by shear friction. Shear keys can be used to enhance the shear resistance of the column at the joint location.
From page 117...
... 117 As is the case with precast modular abutments, the designer should always consider state and local shipping size regulations, as well as erection load limits for typical cranes when designing precast complete pier components. If necessary, consideration should also be given to the pavement capacity of local streets.
From page 118...
... 118 These details include the grouted splice sleeves, but other connection methods are available. The designer should refer to FHWA's Connection Details for Prefabricated Bridge Elements and Systems (Culmo, 2009)
From page 119...
... 119 This research project, as well as those in the future, will begin the standardization process, and standardization will lead to repeatable, cost-effective, and constructible projects. The cost-effectiveness will give the owners the unassisted financial incentive they need to pursue precast substructures for their projects.
From page 120...
... 120 to price that risk. The contractor is in business to make a profit.
From page 121...
... 121 Connection Type I An important aspect of project acceleration is expediting the construction of bridge foundations and substructures. In traditional foundation construction, driven piles are frequently embedded in a cast-in-place footing.
From page 122...
... 122 No literature could be identified that documented previously completed testing of these details. It is anticipated, however, that these details will perform just as well as cast-inplace footings.
From page 123...
... 123 Seismic performance of grouted sleeve couplers is a research area that needs to be further explored before the couplers' use in high seismic zones can gain acceptance. The use of these connectors is common in the precast building market and is being increasingly promoted for bridge construction using precast elements as well.
From page 124...
... 124 with that of the CIP control specimen. Many connection types were tested, including the grouted duct connection and the cap pocket connection.
From page 125...
... 125 strength degradation and exhibiting extensive plastic hinging of the column, limited joint distress, and essentially elastic behavior of the bent cap. Additionally, the report found that the emulative performance is concluded on the basis of closely matching overall behavior to the CIP control specimen, including lateral force–displacement response; plastic hinging; joint shear stiffness; level of joint distress; pattern of joint cracking; strain patterns of bent cap and joint reinforcement; integral behavior between the bedding layer, column, ducts, and bent cap; and minor bar slip.
From page 126...
... 126 recommends that additional testing be conducted for foundation-to-column connections. It also recommends that the grouted splice sleeve connection be further studied and tested for use in high seismic regions.
From page 127...
... 127 testing various foundation-to-column connections for high seismic regions is also needed. The acceptance of precast elements, such as prestressed concrete girders, by state DOTs has been well established for more than 50 years.
From page 128...
... 128 designs or ABC Designs similar to those presented in this report. Costs associated with investment in these technologies will not be addressed nor will they be evaluated at this time, as the intrinsic soft costs driving the need for accelerated or specialized construction equipment and techniques may outweigh the additional project hard costs.
From page 129...
... 129 fully preassembled structures is not practical (although it is possible on a very small scale)
From page 130...
... 130 Figure 3.38. Alternate drilled shaft–to–footing connection.
From page 131...
... 131 Figure 3.39. Alternate column-to-foundation connection -- Option 1.
From page 132...
... 132 Figure 3.40. Alternate column-to-foundation connection -- Option 2.
From page 133...
... 133 Figure 3.41. Alternate column-to-foundation connection -- Option 3.
From page 134...
... 134 Figure 3.42. Alternate drilled shaft to integrated precast abutment cap and backwall connection -- Option 1.
From page 135...
... 135 2. Bridge Designs built with conventional construction a.
From page 136...
... 136 more innovative construction equipment and structural systems are available to provide more rapid renewal and less disruptive construction. The key for owners and their engineering consultants is to define the goals of a renewal project, survey the limits and constraints that could affect the design and construction of the project, evaluate the impact of those limits and constraints, and finally develop a list of design criteria that will be used to prepare plans and specifications for construction.
From page 137...
... 137 44 The matrix would factor in the site and traffic variables and constraints. 44 The matrix would factor in the surrounding environment.
From page 138...
... 138 moving loads. An example of ADDC equipment is shown in Figure 3.46.
From page 139...
... 139 Figure 3.48. Modified ADDC concept used for widening the inside edges of a set of existing twin bridge structures.
From page 140...
... 140 shown in Figure 3.50. Once the modified LTTB has bridged the new span, it would be stabilized and supported at each pier or abutment substructure unit.
From page 141...
... 141 segments can be delivered and preassembled at the site and then delivered as one unit over the span. • Allows work to proceed on multiple fronts (i.e., where multiple-span LTTBs are used, girders can be set while the next girder is delivered)
From page 143...
... 143 As illustrated by the examples below, both launching and lateral shifting technologies involve the use of specialized equipment. To launch a bridge structure, a contractor would potentially require a launching nose, a method of movement (jacks, tuggers, push/pull rams)
From page 144...
... 144 • Minimizes disruption of environmentally sensitive areas under the bridge. • Reduces crane size requirements by pre-erecting the new structure behind the abutment.
From page 145...
... 145 Figure 3.59. Secondary road over mainline–rural (single or twin)
From page 146...
... 146 for ABC Construction Technologies and the matrix directs the user to a new matrix.
From page 147...
... 147 that due to the ability to adjust the traffic flows, ABC Construction Technologies may not be required for the project. The Bridge Widening matrix focuses on the traffic control, the number of bridges, and the type of widening proposed for the project.
From page 148...
... 148 • Is there space adjacent to the proposed bridge location to preassemble the new structure?
From page 149...
... 149 As a result of completing the matrix, owners and engineers will know whether the site and traffic constraints minimize, restrict, or promote the need for ABC Construction Technologies. If ABC Construction Technologies are promoted, they will be categorized in the following set of opportunities: exterior eDgeS • Launching or the use of ADDCs or LTTBs, or explore the use of SPMTs.
From page 150...
... 150 Recommendations for Further Development of ABC Construction Technologies This section focused on the following: • Developing a matrix of questions for owners and their consultants to assist with the proper selection of a construction technology; • Developing a checklist of items that owners and their consultants must address during the design and construction phases of a project; and • Developing of a set of standard conceptual details that owners and their consultants could use as a guide for visualizing the possibilities and defining the limits of the four specified ABC Construction Technologies. Future development of ABC Construction Technologies could evolve around the demonstration of which technologies work best with the ABC Designs (both substructure and superstructure)
From page 151...
... 151 and conceptual details in Phase III are presented under the following headings: • Precast modular abutment systems 44 Integral abutments; 44 Semi-integral abutments; and 44 Precast approach slabs. • Precast complete pier systems 44 Conventional pier bents; and 44 Straddle pier bents.
From page 152...
... 152 Washington State, have already developed extensive sets of pre-engineered bridges for precast construction or rapid renewal. These serve as the team's starting point.
From page 153...
... 153 finish. Testing of the UHPC material for abrasion resistance was completed at Iowa State University in February and March 2011.
From page 154...
... 154 abrasion resistance than did cut surfaces because of the steel fibers present in the UHPC. At the formed surface, the steel fibers were aligned preferentially, parallel with the surface.
From page 155...
... 155 Joint Intersection Detail Recommendations Final inspection of the specimen upon removal from the forms allowed for additional observations and recommendations. The proposed stay-in-place acrylic bulkhead successfully allowed for sequential placement of the UHPC, but also created a possible infiltration plane where water and chemicals could access the embedded steel joint reinforcement.
From page 156...
... 156 interface that was suggested in the strain gauge data, as shown in Figure 3.68. Later, inspection during fatigue testing further confirmed the interfacial debonding and opening occurring below service-level conditions.
From page 157...
... 157 as shown in Figure 3.70, was devised to posttension the deck in this region and minimize tensile stresses in the concrete through Service Level II moments without compromising the accelerated construction aspect of the project. The transverse module-to-module connection detail was modified to include high-strength steel rods mounted just under the deck surface to posttension the entire joint region.
From page 158...
... 158 Figure 3.69. Row 1, top-of-deck embedded strain gauges (static)
From page 159...
... 159 By contrast, applying 70 kips posttensioning force in each of the rods minimized or negated the tensile strain across the interface entirely when loaded to Service Level I All surfacemounted strain gauges spanning the interface registered below the HPC cracking strain until after the Service Level I conditions were exceeded, as shown in Figure 3.71.
From page 160...
... 160 fractures of multiple hairpin reinforcement bars acted as the ultimate mode of failure for the transverse connection. UHPC Testing Conclusions The durability of full-depth deck joints between prefabricated panels has been a major concern for many years.
From page 161...
... 161 strain level relative to regular concrete proved useful for application in this ABC project. While the UHPC displayed several superior material characteristics with respect to the strength of the deck joints themselves, the direct tensile bond strength between the UHPC and the precast HPC deck observed during the strength and serviceability testing raised a durability concern.
From page 162...
... 162 proposed. The bridge was originally designed in-house to be constructed with a planned 13-mi detour (ADT = 4,000)
From page 163...
... 163 Demonstration Project Construction The construction letting for the project was held on February 15, 2011. A total of seven fully responsive bids were received on the Keg Creek Bridge project, with a low bid of $2.65 million submitted by Godbersen–Smith Construction (G-S)
From page 164...
... 164 represented state DOTs, the FHWA, designers, and contractors who shared an interest in accelerated bridge construction. The showcase agenda included presentations from a variety of viewpoints.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.