From page 12...
... 12 Not all projects that receive a good summary rating are necessarily eligible to be approved for funding and an FFGA. In fact, only a few are proposed for an FFGA in a given fiscal year.
From page 13...
... 13 in the planning and project development process for a New Starts project is Alternatives Analysis. It is the only part of the process that does not require FTA approval to begin.
From page 14...
... 14 (i) Initiation of the Study. -- The study is initiated after Systems Planning, during which travel patterns are reviewed and transportation corridors in need of improvements are identified.
From page 15...
... 15 erative, and comprehensive."81 MPOs often have additional responsibilities under state law. Planning literature identifies five core functions of an MPO:82 Establish a setting.
From page 16...
... 16 federal law. If other federal laws do not specify a statute of limitations, a 6-year claims period applies.
From page 17...
... 17 detailed analysis in an EIS of any action located within a floodplain. If a locally preferred alternative is to be in a floodplain, FTA must find that it is the only practicable alternative and must document actions to avoid or reduce adverse impacts on the floodplain.
From page 18...
... 18 access to services are some of the elements to be considered here. Land Use and Development. -- A part of the statutory justification for a New Starts project is that the "Secretary shall -- (A)