Skip to main content

Currently Skimming:


Pages 38-51

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 38...
... 36 CHAPTER SIX ALTERNATE DESIGN/ALTERNATE BID CASE STUDIES INTRODUCTION "MoDOT let 187 ADAB projects worth $2.2 billion. An average of 5.7 bidders competed for ADAB projects as opposed to 4.5 on conventional paving projects.
From page 39...
... 37 INDIANA DEPARTMENT OF TRANSPORTATION INDOT chose the US-31 at Kokomo, Indiana, project for its first ADAB project and constructed it under the SEP-14 program. In the SEP-14 application, the following goals were cited as the motivation for experimenting with ADAB: 1.
From page 40...
... 38 As Table 9 shows, the LCC factor influenced the final outcome as the lowest HMA bid was below the lowest PCC bid price. Nevertheless, both low bids were below the engineer's estimated cost for the pavement types, indicating that the increased competition resulted in reducing the proposed costs of both pavement types.
From page 41...
... 39 • "INDOT saved $3,800,000 immediately at the bid openings; • INDOT saved approximately $10,000,000 over the 50 year service life; • INDOT saved the taxpayers approximately $28,600,000 by being an additional 5.7% under the engineer's estimate" (Duncan and Holtz 2012)
From page 42...
... 40 US-171 ADAB Project • Scope of Work: 4.1-mi section of a four-lane highway overlay • Design Alternatives: HMA Overlay versus PCC Bonded Overlay • Life-Cycle Cost Input Values: – 30-year analysis period for overlays (40 years is typical for new construction) – Current unit prices from LaDOTD database – Discount rate = 4% – NPW analysis with future activities included is shown in Table 12.
From page 43...
... 41 project will be let as an ADAB project. According to Brown (2010)
From page 44...
... 42 TABLE 14 US-31 BID ANALYSIS SUMMARY PCC Bid Price EUAC Lane Rentalb Bid Analysis A+C - Lane Rentala Ramps Freeway A $11,792,980 $725,768 $111,640 $413,502 $11,993,606 B $12,659,041 $775,229 $88,137 $635,140 $12,710,993 C $13,745,871 $837,869 $111,640 $625,216 $13,846,884 D $13,796,513 $840,190 $104,902 $527,629 $14,004,172 HMA E $15,475,645 $961,332 $111,640 $330,802 $15,994,535 Source: Adapted from Mikesell (2012)
From page 45...
... 43 of the project was capped at $535 million and the DB team that proposed the most scope for that price won. Contractors performed the pavement design alternatives.
From page 46...
... 44 • Difference -- $16,647,446 (1.9%) • When the LCC factor is applied, the difference is 5.6%.
From page 47...
... 45 and Smith 1998; Tinni 2013)
From page 48...
... 46 Adjustment Factor: NPW Future Asphalt Rehab – NPW Future Concrete Rehab Low bidder: Low bidder = lower of (PCC Bid Price + NPW Future Concrete M&R)
From page 49...
... 47 FIGURE 15 TxDOT APDAT flowchart (Wimsatt et al.
From page 50...
... 48 The first step involves collecting project specific information and then filtering it through a series of Go/No Go parameters to determine whether to proceed. The initial filters are defined as project characteristics that make the project "unsuitable for offering alternative pavement design" (Wimsatt et al.
From page 51...
... 49 A number of conclusions can be drawn from the case study analysis and are described as follows: 1. In each case study, implementing ADAB increased competition by allowing both HMA and PCC paving contractors to bid on the same job.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.