Skip to main content

Currently Skimming:


Pages 45-92

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 45...
... 37 Appendix D Icebreaker Acquisition Strategy, Design and Cost Projections, and Operating Costs Contents ACQUISITION STRATEGY .................................................................................................... 39 Fixed Price Incentives Contract ............................................................................................
From page 46...
... 38 Basic Work Scope of Medium Icebreaker Compared with Heavy Icebreaker ............ 87 Engineering, Detail Design, and Planning .......................................................................
From page 47...
... 39 ACQUISITION STRATEGY Acquisition strategy will have a significant impact on overall program cost and performance. The objective is to achieve affordable construction and life-cycle costs for the new polar icebreaker fleet.
From page 48...
... 40 Fixed Price Incentives Contract Several contracting methods are typically applied to government shipbuilding projects. The most common are "cost plus fixed fee" and "fixed price incentive fee." Cost plus fixed fee is appropriate for projects involving significant research and development of new technologies.
From page 49...
... 41 Block Purchase A block buy authority for this program will need to contain specific language for economic order quantity purchases for materials, advanced design, and construction activities. A block buy contracting program26 with economic order quantity purchases enables series construction, motivates competitive bidding, and allows for volume purchase and for the timely acquisition of material with long lead times.
From page 50...
... 42 Commonality of Design Commonality of design with existing vessels and between vessels intended for similar service is another factor leading to cost-effective construction. Commonality of design is one of the main reasons large-scale Asian shipyards are able to achieve higher productivity and lower material costs than U.S.
From page 51...
... 43 independent variable27 could be applied to ensure reasonable trade-offs between performance and cost. For example, sewage discharge in ice-covered waters is prohibited by the Polar Code, and a ship must shift to an ice-free location to discharge treated sewage.
From page 52...
... 44 Reduce Risks of Cost Overruns and Delay Many steps can be taken to reduce the risk of cost overruns and delays. They are well established in the commercial shipbuilding industry and should be applied to government construction projects.
From page 53...
... 45 practice (which many say was followed in the United States during the high point in ship construction here from the 1940s to the 1960s) has been reapplied by U.S.
From page 54...
... 46 second ship. Follow-on ships can be more closely spaced, since improvements in the design and construction processes will have been determined.
From page 55...
... 47 USCG has informed the committee that the new heavy polar icebreaker is expected to be classed in accordance with steel vessel rules of the American Bureau of Shipping (ABS) , the U.S.-based classification society.
From page 56...
... 48 FIGURE D-1 Notional timeline for first icebreaker acquisition (Ship 1)
From page 57...
... 49 Keel laying can commence after assembly of an inventory of blocks and grand blocks sufficient for sustaining the planned rate of erection. In general, this milestone is 5 to 6 months after SOC.
From page 58...
... 50 test and trials. A period of 6 months is suggested for trials and trial card31 resolution for the first ship of the class.
From page 59...
... 51 workforce between Ship 1 and Ship 2. Although learning occurs among people and not facilities, it must be documented carefully to attain its full value.
From page 60...
... 52 FIGURE D-2 Notional total timeline, all ships of class, polar icebreaker acquisition 4 × 1 strategy. (BOM = bill of materials; P = production.)
From page 61...
... 53 ICEBREAKER DESIGN AND COST PROJECTIONS One task of the committee was to evaluate cost estimates for the new polar icebreakers. To carry out that task, a notional design that can form the basis for the cost estimate had to be developed.
From page 62...
... 54 accommodation of more persons in a vessel this size is feasible since its length is well in excess of the 128- to 132-meter required stack-up length estimated by the committee. Existing overseas icebreakers are good sources for size data.
From page 63...
... 55 Icebreaker Size The size of heavy polar icebreakers is a strong determinant of the cost of ship acquisition and operation. Foreign heavy icebreakers often have much smaller crews than do USCG cutters.
From page 64...
... 56 Accommodations block 32.3 Foredeck 36.0 Length overall 132.0 NOTE: SRP = stern reference point. SOURCE: Generated by the committee.
From page 65...
... 57 FIGURE D-3 Correlation between lightship weight and cubic number. (Source: Generated by the committee.)
From page 66...
... 58 Installed Propulsion Power Icebreaking capability is in part determined by power provided to the propellers. The Oden's design was groundbreaking.
From page 67...
... 59 estimate of U.S. shipyards bidding on this project, given their current practices and facilities.
From page 68...
... 60 MIL-SPEC procurement of approximately 20 percent of materials and equipment is assumed in accordance with USCG's stated intention for the polar icebreakers. A premium is added for both material and shipyard labor to account for the added cost of purchasing and installing MIL-SPEC equipment.
From page 69...
... 61 The government will incur costs for its own efforts in addition to the design and construction contract price. The committee accounts for these items to allow an "apples-toapples" comparison with USCG estimates but does not have the data needed to validate these figures.
From page 70...
... 62 Total cost, GFM/GFE $102 million/ship Total cost, government PEO, representatives, and SUPSHIP $48 million/ship PDA $15 million/ship NOTE: SUPSHIP = Supervisor of Shipbuilding, Conversion, and Repair. SOURCE: Generated by the committee.
From page 71...
... 63 Change orders 78 30 29 29 Other government expenses 62 63 65 65 Total, government program expenses 162 115 116 116 Grand total per vessel 983 759 729 692 Overall program costs Total program budget, four ships 3,163 Average price, each of two 871 Average price, each of three 824 Average price, each of four 791 NOTE: Costs are in millions of U.S. dollars, 2019.
From page 72...
... 64 Cost of Science Making the new icebreakers science-ready means incorporating design elements that allow costeffective retrofitting of the ships for full science capability if necessary during the ships' service lives. Such design elements could include the following: 1.
From page 73...
... 65 to be determined. In addition, certification for dynamic positioning requires a high level of redundancy and independence of system operation that can have a major impact on propulsion, auxiliary machinery, electric distribution, and controls design, with a significant increase in cost that is difficult to determine.
From page 74...
... 66 Maximum beam (meters) 25 28 19 15.85 24 21 19 Displacement, full load (metric tons)
From page 75...
... 67 Standardization vans can be loaded aboard to provide additional science and workstation capabilities. In April 2012, the Healy escorted a tanker carrying an emergency fuel delivery to Nome, Alaska.
From page 76...
... 68 In striking contrast, the Polaris was commissioned last year at a reported cost of only 125 million euros, or an estimated $150 million (in 2016)
From page 77...
... 69 (meters) Maximum speed (knots)
From page 78...
... 70 ships to the same design) for the first medium icebreaker, but the advantage would apply to the alternative fourth heavy ship.
From page 79...
... 71 exist. They cover interfaces, design, manufacturing, standard practices, and testing.
From page 80...
... 72 Impact of MIL-SPEC on Costs Committee members have been involved in the design and construction of commercial vessels and U.S. government vessels where MIL-SPEC has been invoked and understand the trade-offs.
From page 81...
... 73 Value of MIL-SPEC to Polar Icebreakers The committee believes that the application of MIL-SPEC and MIL-STD, as described above, may not be justified. In view of the unique nature of icebreaker service, the use of applicable international and commercial standards often can achieve better levels of safety and reliability than would be achieved by MIL-SPEC.
From page 82...
... 74 and service. Extensive testing will not make a poorly designed or hard-to-service engine reliable.
From page 83...
... 75 frequent and more just-in-time maintenance, which reduces annual cost. Modern machinery also is more reliable and allows greater time between overhauls.
From page 84...
... 76 strategy reduces up-front acquisition cost, but it could also be more cost-effective for operating costs over the life of the vessel. The three primary drivers of annual operating cost are often the vessel's physical characteristics, the operating and voyage profile, and the maintenance schedule (such as when the vessel is dry-docked)
From page 85...
... 77 • Basic work scope; • Engineering, detail design, and planning; • Material and equipment cost; • Production labor and productivity; • Risk margin applied by the shipyard; • Learning rate assumed by the shipyard; and • Profit margin assumed by the shipyard. Basic Work Scope of Medium Icebreaker Compared with Heavy Icebreaker Variance in the basic work scope will occur if the ship characteristics that the committee assumed differ from those set forth by USCG.
From page 86...
... 78 conservative) cost.
From page 87...
... 79 Risk Margin The committee's cost analysis models applied a risk margin of 7.5 percent to the basic estimate for engineering, detail design, planning, and production labor for Ships 1 and 2, decreasing to 3.75% each for Ship 3 and Ship 4. No risk margin was applied to the material estimate, and in fact, a 5 percent reduction in material costs was assumed for "tasking" the result of aggressive negotiation between the shipbuilder and key suppliers.
From page 88...
... 80 contract is completed, which is often lower than expected. If a shipbuilder bids low on its profit margin, the contract may fail to perform to shareholders' expectations.
From page 89...
... 81 NOTE: The assumed range of uncertainty is ±10 percent of the total shipyard contract for heavy icebreakers and ±15 percent of the total shipyard contract for medium icebreakers. Figures are in millions of U.S.
From page 90...
... 82 If there are two contracts, one for three heavy icebreakers and another for one new medium design, and the first contract is won with a 98 percent bid learning rate while the second for the medium design is won with an 85 percent learning rate, the total cost of Ship 4 will be slightly higher (by $4 million, the difference between $788 million and $792 million) than if four ships to the same design are bought.
From page 91...
... 83 O'Rourke, R

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.