Chapter 2 - Value Engineering Research Results
Pages 54-65

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 54...
... receiving federal assistance with an estimated total cost of $50,000,000 or more and b Bridge projects on the NHS receiving federal assistance with an estimated total cost of $40,000,000 or more – Removes the VE analysis requirement for projects delivered using the design-build method of construction and – Provides VE analysis guidance for projects delivered using the CMGC method of project delivery • The VECP process is typically decoupled from the design-related VE efforts for most agencies. This is generally administered through the construction division and not the design or project C h a p t e r 2 Value Engineering Research Results
From page 55...
... Washington Design Manual Chapter 310: Value Engineering -- M 22-01.10 July 2013 6. Montana Value Analysis Program Manual Updated April 2015 7.
From page 56...
... VE studies performed in-house did not apply function analysis techniques correctly if they applied them at all. Many consultant studies, however, did not leverage function analysis properly to help generate creative ideas.
From page 57...
... Study Days Creative Ideas Function Analysis Comments 1 Knik Arm Crossing AKDOT (Alaska) 2007 Consultant CVS $305 22 / 0 $01 5 99 Correct use.
From page 58...
... 2010 Consultant CVS $65 9 / unknown unknown 4 40 Correct use. No cost function analysis.
From page 59...
... 2013 Consultant CVS $22 4 / unknown unknown 4 33 Correct use. Cost function analysis performed.
From page 60...
... 28 USA Parkway NDOT (Nevada) 2013 Consultant CVS $59 12 / unknown unknown 4 unknown There was no evidence of the proper use of function analysis in the report.
From page 61...
... Cost function analysis performed. FAST diagram developed.
From page 62...
... Study Days Creative Ideas Function Analysis Comments 38 I-5 / Blaine Exit Interchange Improvements WSDOT (Washington) 2006 Consultant CVS $17 10 / unknown unknown 5 83 Correct use.
From page 63...
... Correct - Tied to Creativity 37% Correct Not tied to Creativity 30% Not Used 33% Use of Function Analysis Figure 39. Level of VE alternative development.
From page 64...
... Value Engineering Surveys A formal VE Survey was distributed to agency VE coordinators -- a total of 84 survey requests were distributed. As of August 13, 2015, the research team collected 36 responses, of which 33 were complete.
From page 65...
... That way all the Project Managers can schedule the VE study at the proper time (30% or conceptual phase) ." • "It's important to recognize that VECP is not Value Engineering.