Chapter 4 - Constructability Review Research Results
Pages 73-78

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 73...
... • Very few states have any system in place to track the efficacy of their CR program. States with formal CR policies track whether a CR was conducted or not and some states track the total number of CRs performed, but there is little information being collected regarding the implementation of CR comments, reduction in change orders, or cost and time savings resulting from the CRs.
From page 74...
... Michigan Construction Advisory – Constructability Reviews; and Road Design Manual November 5, 2009; February 18, 2010 22. Massachusetts Highway Division Construction Contract Procurement and Oversight, Internal Audit Report July 22, 2011 23.
From page 75...
... Generally, most transportation agencies do not have a formal CR policy or program. There is typically no prescribed process or procedure for
From page 76...
... The Other areas within a transportation organization were the following: – Both Design and Construction – Central Estimate Support and Construction Offices – Technical Services/Value Management – Asset Management and Performance Bureau • More transportation organizations did not have a formal CR policy (59%) than those that did have a formal policy (41%)
From page 77...
... – Construction Phasing – Biddability – Technical Complexity • The following key project documents for conducting a CR were indicated in order of priority: – Plans – Estimates/Bid Items – Specifications – Construction Contracting Language • When conducting CRs, responding transportation agencies indicated it is common to use a combination of both hard copy and electronic documents, inclusive of the key project documents identified above. • Of the responding transportation agencies with a CR process, the following applied: – Approximately 47% indicated they use a specific documented comment capture and resolution method.
From page 78...
... These shall be organized in such a way that they can be readily applied at various points in the project delivery process to raise relevant CR issues and identify related risks in a timely and effective manner. • Provide guidance to DOTs on how to leverage Risk Response Planning and VE techniques to identify and develop solutions to mitigate or avoid constructability risks.