From page 103...
... 106 Tack Coat Specifications, Materials, and Construction Practices 29% (2/7)
From page 104...
... Summary of Survey Results (Canada)
From page 105...
... 108 Tack Coat Specifications, Materials, and Construction Practices 57% (4/7)
From page 106...
... Summary of Survey Results (Canada)
From page 107...
... 110 Tack Coat Specifications, Materials, and Construction Practices to accommodate not more than 2 hours of production of HMA. HMA shall not be placed on tack coated areas until the tack coat has cured to a proper condition of tackiness.
From page 108...
... 111 A P P E N D I X D Kansas Department of Transportation: Bond Strength Special Provision and Best Management Checklists
From page 109...
... 112 Tack Coat Specifications, Materials, and Construction Practices KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2015 HMA BOND STRENGTH Page 600-2, subsection 602.1. Add the following bid item: BID ITEMS UNITS Emulsified Asphalt Square Yard Page 600-31, delete subsection 602.11c.
From page 110...
... Kansas Department of Transportation: Bond Strength Special Provision and Best Management Checklists 113 If the tensile stress of a test is less than 35 psi, suspend plant production and paving. Follow the Best Management Processes to verify proper placement of tack material.