Skip to main content

Currently Skimming:


Pages 103-136

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 103...
... 4.1 4. INSTALLATION GUIDANCE AND APPRAISAL OF RESEARCH RESULTS 4.1 Overview This chapter presents a summary of information, observations, and recommended guidance for the installation of filters under water.
From page 104...
... 4.2 4.3.1 Construction Constraints: Filter Selection Based on Site Access and Overhead Clearance Construction constraints take into account the different needs and challenges required for placing a filter underwater and/or in flowing water. Construction constraints for filter placement are primarily concerned with site access issues in general, and, particularly when working in and around bridges, the overhead clearance between the water surface during construction and the low chord of the bridge deck section.
From page 105...
... 4.3 Figure 4.1. Selection based on access and clearance.
From page 106...
... 4.4 Figure 4.2. Selection based on velocity and depth.
From page 107...
... 4.5 4.3.3 Additional Considerations Additional issues to consider when selecting a filter to be placed under water include: Granular Filters: • Availability of filter material of the required size and gradation • Haul distance All Filter Types: • Site access • Equipment requirements, including barge if necessary • Environmental and water quality issues and permitting requirements • Habitat and/or migration issues for threatened and endangered species • Traffic control during construction activities Lastly, materials and installation costs will be a factor in the selection of a filter when more than one filter type and/or construction technique is viable at a particular site: 1. Initial construction materials and delivery costs 2.
From page 108...
... 4.6 4.4.2 Installation Underwater installation of granular filters should only be performed by clamshell bucket or tremie, with the filter material being released on or very near the bed. The tremie method of placement can be accomplished using either rigid pipe from the surface, or a flexible hose through which the filter material is pumped in a water slurry to divers at the end of the hose.
From page 109...
... 4.7 Table 4.1. Recommended Tests and Allowable Values for Aggregate Quality (modified from FHWA HEC-23, Lagasse et al.
From page 110...
... 4.8 Table 4.2. Standard Coarse Aggregate Gradations From ASTM C33.
From page 111...
... 4.9 Aggregate quality: Aggregate for granular filters should be hard, dense, durable, and should conform to the allowable values for the standard tests in Table 4.1. Filter layer thickness: For practicality of placement, the nominal filter layer thickness when placed under water should be no less than 6 inches.
From page 112...
... 4.10 Quality Control: Quality control procedures for the underwater placement of granular filters include the following checklist items: 1. Checking contractor's submittals for material quality testing and size gradation in conformance with project specifications.
From page 113...
... 4.11 In considering environmental impacts and permitting of a countermeasure which includes a granular filter placed in flowing water, issues that could be of concern would likely be limited to potential short term increases in turbidity and changes in the characteristics of the stream substrate. Here, a concern for the physical habitat would be infilling of interstices in the existing substrate (e.g., impacts on spawning habitat)
From page 114...
... 4.12 4.5.3 Inspection and Maintenance Immediately after placing the geotextile filter, and before the armor layer is installed on top of it, the filter should be inspected for sufficient areal coverage and overlaps. Underwater inspection is best accomplished by divers.
From page 115...
... 4.13 Table 4.3. Recommended Tests and Allowable Values for Geotextile Properties.
From page 116...
... 4.14 4.5.6 Quality Assurance / Quality Control In construction, the quality assurance program focuses on the procedures to ensure that the design meets quality standards. This includes design calculations, construction plans and detail drawings, and specifications for required material properties.
From page 117...
... 4.15 4.5.7 Environmental and Permitting Considerations As noted in Section 4.4.7, for aquatic organisms, habitat includes the stream, its boundaries (bed and banks) , and existing vegetation.
From page 118...
... 4.16 4.6 Applications In the following sections, two projects involving underwater placement of geotextile filters are used to illustrate and supplement the discussion of the current state of practice in the U.S.
From page 119...
... 4.17 Although the DOT intended that the scour holes would be filled with clean gravel, an environmental resource agency prohibited this even though the intent was to use a washed gravel. As a result the A-Jacks® modules were placed on the streambed and in some cases where the scour holes were extremely deep, the A-Jacks® modules were placed in tiers.
From page 120...
... 4.18 Idaho DOT (IDT) required that the Contractor: • Fit modules as close as possible to each other and to the pier structure.
From page 121...
... 4.19 Figure 4.6. Applying the geotextile filter to an A-Jacks® module.
From page 122...
... 4.20 Figure 4.8. Installation at the bridge started downstream and proceeded upstream.
From page 123...
... 4.21 Figure 4.10. Diver inspecting in-place A-Jacks® module at Ferry Butte Bridge.
From page 124...
... 4.22 NCDOT, with collaboration and cooperation of other agencies and private contractors, stabilized the scour condition allowing the bridge to be reopened on Sunday, December 15, 2014. Restoring traffic to the Outer Banks was crucial in advance of the holiday influx of tourists headed south to the 60 miles of barrier islands, seven historic villages, and gateway to Ocracoke Island.
From page 125...
... 4.23 December 5th: NC Governor issues Emergency Declaration which will facilitate negotiations with other agencies and contractors. USACE has a contract maintenance dredging project of the navigation channel through the inlet bar.
From page 126...
... 4.24 December 12th: Divers confirm consolidation of dredge placed sand at Bent 166. First shipment of A-Jacks® elements (Figure 4.12)
From page 127...
... 4.25 Assembly area Stockpile of assembled A-Jacks Figure 4.13. A-Jacks® assembly area and stockpile at Bonner Bridge (Henderson 2014)
From page 128...
... 4.26 Figure 4.15. Contractor apparatus for A-Jacks® module placement (Henderson 2014)
From page 129...
... 4.27 Figure 4.17. Placement of geotextile containers around Bent 166 at Bonner Bridge (Henderson 2014)
From page 130...
... 4.28 The final numbers for work performed were: 78 - 3'x3'x3' geotextile bags 158 - 4'x4'x4' geotextile bags 980 - A-Jacks® elements Cost = $1.79 million (excluding dredge activity estimated at +/- $1 million) Summary Observations.
From page 131...
... 4.29 4.7.2 Observations From the Survey of Practitioners • A total of 138 survey forms were distributed to practitioners across a wide variety of local, state, and federal agencies in the United States. Of the 42 responses received, 31 were from state government personnel (primarily DOTs)
From page 132...
... 4.30 Two flow rates were established for the divers to work in; the first was a relatively modest approach velocity of 0.6 feet per second, while the second was more severe with an approach velocity of 3.5 feet per second. At all times the divers were tethered and in communication with each other as well as with line handlers topside.
From page 133...
... 4.31 4.8.2 The Market The market or audience for the results of this research are hydraulic engineers and maintenance and inspection personnel in local, state, and federal agencies with responsibility for countermeasures for scour and erosion control at bridges and highway facilities, including: • State Highway Agencies / Departments of Transportation • FHWA • City/County Bridge Engineers • U.S. Army Corps of Engineers • U.S.
From page 134...
... 4.32 AASHTO. The American Association of State Highway and Transportation Officials is the developer and sanctioning agency for standards, methods, and specifications.
From page 135...
... 4.33 courses. A supplemental critique sheet could be used during Course 135048 or 132013 to provide feedback on the applicability of the guidance and suggestions for improvement.
From page 136...
... 4.34 Learning Outcomes At the end of Part I, Participants will be able to: • Describe the purpose, need, and functions of geotextile and granular filters • Identify sources of design guidance for geotextile and granular filters • Discuss experience with and local agency guidance for installing filters underwater • Describe and list several techniques currently used to install filters underwater for typical armoring countermeasures (e.g., riprap, ACBs, etc.) • List and discuss the lessons learned from a recent U.S.

Key Terms



This material may be derived from roughly machine-read images, and so is provided only to facilitate research.
More information on Chapter Skim is available.