... 65 Chapter 6 Cost-Benefit Analysis The design and function of ferric oxide-sand filters evaluated in this study are largely the same as traditional sand filters designed for stormwater runoff treatment. As such, planning level life cycle costs of proposed ferric oxide-sand filters can be readily estimated using the life cycle costing tool provided as part of NCHRP 792.
From page 66...
... 66 Table 6-1 Highway 36/61 site and tributary watershed parameter inputs to the NCHRP 792 sand filter evaluation tool. Variables and Project Location  Assumptions  Value  Units  Source  Location  Maplewood, MN (1)
From page 67...
... 67 Capital and operations and maintenance costs can be generated by the Tool or if site-specific capital and operation and maintenance costs are known they can be used as user defined inputs. As an example, project-specific capital costs (for the Highway 36/61 ferric oxide filer)
From page 68...
... 68 Table 6-4 Highway 36/61 life cycle cost analysis assumptions and inputs to the NCHRP 792 sand filter evaluation tool. Variables NCHRP Tool Inputs Value Units Source Cost Inputs Location Adjustment Factor Y 100 Minnesota factor per RS Means (105)
From page 69...
... 69 Table 6-5 Highway 36/61 ferric oxide-sand whole life cycle cost estimate analysis. Constituent Condition1 Loading (lb yr-1)