... 63 A P P E N D I X A This appendix contains useful information that is specific to implementing ATCs on DB projects. The appendix contains • Generic flowchart for implementing ATCs (Figure A.1)
From page 64...
... 64 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods A.1 DB ATC Flowchart Design-Build ATC Process Pre-Advertising Conceptual Evaluation Approved Pr oj ec t D ev el op m en t a nd D el iv er y Ph as e YES * NOTE: There may be several one-on-one meetings with the contractors to clarify both CATCs and ATCs if required.
From page 65...
... DB ATC Information 65 A.2 DB CATC Submittal Forms Vermont Agency of Transportation Conceptual Alternative Technical Concept Submittal Form Design-Build Project Proposer ATC Number Advantages and Disadvantages: A listing and brief description of the comparative advantages and disadvantages of the Conceptual ATC including: Effects on the service life, safety, durability, reliability, economy of operation, ease of maintenance; other factors significantly altered by the Conceptual ATC; and rationale for the proposed deviation(s) from the BTC.
From page 66...
... 66 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods A.3 DB Formal ATC Submittal Forms California and North Carolina Departments of Transportation Each Formal ATC submittal shall include the following information: 1) Description.
From page 67...
... DB ATC Information 67 New York State Department of Transportation Proposer: ATC Title: Project Title: ATC No.: Contract #: Date: A Description: Provide a detailed description of the configuration of the ATC or other appropriate descriptive information. B Usage: Describe where and how the ATC would be used on the Project C1 Deviations: Provide references to any requirements of the RFP Documents or to any elements of the Contract Documents that are inconsistent with the proposed ATC.
From page 68...
... 68 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods Massachusetts Department of Transportation DB Entities shall submit an Executive Summary to the MassDOT Construction Contracts Engineer at least three (3) Business Days prior to each one-on-one meeting.
From page 69...
... DB ATC Information 69 A.4 DB ATC Evaluation and Response Forms Vermont Agency of Transportation Conceptual Alternative Technical Concept Response Form Project Name: Date Received: Project Number: Design-Build Team: Date Responded: Subject: Reviewer Comments: Deviation: By providing XX there (is or is not) a deviation from standards.
From page 70...
... 70 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods Final Alternative Technical Concept Response Form Subject: Reviewer Comments: Deviation: By providing XX there (is or is not) a deviation from standards.
From page 71...
... DB ATC Information 71 Georgia Department of Transportation ATC Responsiveness Checklist Proposer: ATC Number: Brief Description: 1. ATC is labeled appropriately as designated in the ITP Section 3.1.2 (a)