... 85 A P P E N D I X E Example ATC Solicitation and Contract Clauses E.1 Nondisclosure Agreements Metropolitan Washington Airports Authority 2012 Except as may be required by applicable law or court order, I will not divulge any Designated Confidential Information to the media, any member of the public or any other Offeror. I understand that a list of the signatories to this type of agreement shall be maintained by the Owner.
From page 86...
... 86 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods Project and/or Project proposals ("Proposals") , information regarding Project cost estimates, Proposal prices, Project development or financing plans, alternative technical concepts, proposer qualifications, or any other documents or information that might be considered sensitive which I have heard, seen or reviewed (collectively, the "Confidential Information")
From page 87...
... Example ATC Solicitation and Contract Clauses 87 personnel to participate in the One-on-One ATC discussion meeting. The purpose of the One-on-One ATC discussion meeting is to discuss the ATC proposals, answer questions that the Department may have related to the ATC proposal, review other relevant information and when possible establish whether the proposal meets the definition of an ATC thereby requiring the submittal of a formal ATC submittal.
From page 88...
... 88 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods e. Impacts: A preliminary analysis of potential impacts on vehicular traffic (both during and after construction)
From page 89...
... Example ATC Solicitation and Contract Clauses 89 Approved Design Exceptions or Design Variations required as part of an approved ATC will result in the issuance of an addendum to the RFP notifying all Shortlisted Design-Build Firms of the approved Design Exception(s) or Design Variation(s)
From page 90...
... 90 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods For Work unrelated to an ATC, Differing Site Conditions shall mean (a) actual subsurface or latent physical conditions encountered at the Site that are substantially or materially different from the conditions identified in the GBR, the GDR, or the SGDR (if any)
From page 91...
... Example ATC Solicitation and Contract Clauses 91 in response to MnDOT's requests for further information concerning a prior submittal shall be received by MnDOT by 1:00 p.m., Central Time, within seven Days of MnDOT's request. All PAE submittals and resubmittals shall be delivered to MnDOT's Project Manager specified in Section 3.3.
From page 92...
... 92 Guidebook for Implementing Alternative Technical Concepts in All Types of Highway Project Delivery Methods E.5 One-on-One Meeting Opening Discussion Statement Minnesota DOT One-on-One Meeting Discussion Checklist The following is a standard checklist used by MnDOT to open each one-on-one meeting as a means to ensure that contractors are aware of the limitations and constraints on the confidentiality of discussions held during each meeting.