5 Project Management Metrics
Pages 62-78

The Chapter Skim interface presents what we've algorithmically identified as the most significant single chunk of text within every page in the chapter.
Select key terms on the right to highlight them within pages of the chapter.


From page 62...
... In addition to cost and schedule, the PARS II system helps with tracking project specific metrics.2 This system provides up-to-date and reasonably 1  Project management metrics necessarily roll up into program performance metrics. However, this interim report focuses on project metrics; a future report by this committee will examine and discuss in detail EM's program performance metrics.
From page 63...
... GAO states that: EM manages most of its cleanup work as operations activities, under less strin gent oversight requirements than capital asset projects. EM manages its cleanup work under different requirements, depending on whether it classifies the work as a capital asset project or an operations activity.
From page 64...
... • Contract and project performance metrics and targets • Progress reports to Congress In general, EVMS is an organization's system for monitoring project/­ program management that integrates a defined set of associated work scopes, schedules, and budgets. An organization's leadership uses performance management information, produced from the EVMS, to plan, direct, and control the execution and accomplishment of contract/project cost, schedule, and technical performance objectives (scope of work)
From page 65...
... Performance Metrics."12 REPORTING OF PROJECT METRICS The committee has reviewed sample copies of EM's project management reports,13 among other provided documents. These reports show EM extensively using EVM project control practices along with capital asset project dashboards, and corporate performance measures.
From page 66...
... Contract/Project Management Contract/Project Management Performance Performance Metrics FY 2020, 2nd Qtr Metrics FY 2008 Target FY 2008 Actual Actual FY18-FY20 Comment 1. Capital Asset Project Success: Complete 1.
From page 67...
... /Corrective Action Plan (CAP) Performance Metrics," https://www.energy.gov/sites/prod/ files/2020/05/f74/FY%202020%20Q2%20Project%20Management%20Performance%20Metrics%20 Report.pdf; "FY 2008 4th Quarter Metrics: Overall Contract and Project Management Performance Metrics and Targets," https://www.energy.gov/sites/prod/files/FY2008%204th%20Quarter%20RCA_ GAO_OMB%20Attachmentv02%202008-11-17.pdf, accessed August 11, 2020.
From page 68...
... NOTE: BCWP = budgeted cost of work performed; BCWS = budgeted cost of work scheduled; STWP = scheduled time of work performed; ATWP = actual time of work performed, SPI(t) is the ratio of STWP to ATWP.
From page 69...
... All of these issues indicate the need for a robust, reliable, effective, and efficient governance process for EVMS. Therefore, for the second phase of this study, the committee plans to review EVMS governance in more detail, including: • Current EVMS governance process, the involved parties, and their roles and responsibilities; • Current EVMS certification process and enforcement of such certification; • Current data collection processes for EVMS to ensure they are current, accurate, complete, repeatable, and auditable; and • Current project control systems that EM actively uses.
From page 70...
... 15  See Whole Building Design Guide, "CAD/BIM Technology Center: A/E/C CAD Standard," https://www.wbdg.org/ffc/army-coe/cad-bim-technology-center. 16  See DOE, Environmental Management Consolidated Business Center, "CPCC Section H IDIQ," https://www.emcbc.doe.gov/SEB/CPCC/Documents/RFP/CPCC_Section_H_IDIQ.pdf.
From page 71...
... developing and maintaining an integrated master schedule using GAO best practices; and (2) establishing project-reporting systems/databases to provide a clear picture of project performance to management and to keep the contractor accountable.
From page 72...
... This section will focus on performance metrics and benchmarks and the ability to define project outcomes and performance measures. As noted previously, EM is familiar with KPP principles as they are referenced in two of their documents (DOE, 2015, 2018a)
From page 73...
... The executing program strategy is implemented by an organization through program-wide performance metrics and key performance indicators (KPIs) that measure project components.
From page 74...
... The major takeaway concerning project metrics is that the relationship and importance of key metrics to driving program strategy is central to overall strategy attainment. The IDIQ delivery approach places greater emphasis on EM's program management staff to establish metrics that improve performance and complement strategy.
From page 75...
... FINDING: Joint task forces are common to military operations and are now used throughout the government. 26 Anne Marie White Assistant Secretary for Environmental Management, Written Statement Before the Subcommittee on Strategic Forces Committee on Armed Services United States House of Representatives April 9, 2019, https://docs.house.gov/meetings/as/as29/20190409/109269/hhrg-116as29-wstate-whitea-20190409.pdf.
From page 76...
... Its four lines of business are major projects, real estate services, infrastructure lending, and commercial projects. As such, it is the program manager for most large projects in Ontario.a IO's procurement process (request for qualifications [RFQ]
From page 77...
... Due to these similarities, EM may want to form a "joint task force" or less formal cooperative structure with Naval Facilities Engineering Systems Com mand (NAVFAC) and other BRAC and FUDS program management organizations to share experiences and best practices with their indefinite delivery/indefinite quantity (IDIQ)
From page 78...
... should implement a modification to its earned value management system that captures the project's temporal status more clearly and explicitly. Specifically, EM should immediately require that a revised Schedule Performance Index, SPI(t)