... 142 Undertake Detailed Assessments of Exposed Assets and New Projects (Step 8C) Step 7 identified and prioritized existing assets that are potentially vulnerable to hazards and threats.
From page 143...
... Undertake Detailed Assessments of Exposed Assets and New Projects (Step 8C)
From page 144...
... 144 Mainstreaming System Resilience Concepts into Transportation Agencies: A Guide and duration due to climate change. The chances of adverse change are greater for longer-lived assets like bridges.
From page 145...
... Undertake Detailed Assessments of Exposed Assets and New Projects (Step 8C) 145   reflect the degree to which future-oriented projected data on the frequency, magnitude, and scope of hazards and threats are used as input into project analyses.
From page 146...
... 146 Mainstreaming System Resilience Concepts into Transportation Agencies: A Guide • Level 3: As standard practice for project design, we utilize a scenarios-based approach such as ADAP to better understand the range of uncertainty in the natural hazards that might affect our projects (and its implications)
From page 147...
... Undertake Detailed Assessments of Exposed Assets and New Projects (Step 8C) 147   user costs when an asset or facility is out of service that can also be included as avoided costs (benefits)
From page 148...
... 148 Mainstreaming System Resilience Concepts into Transportation Agencies: A Guide as buildings and other structures that are part of an agency providing its services. A facility management plan provides the means to continue monitoring asset performance to ensure it meets expectations.
From page 149...
... Maturity Factor Level 1 (1 point) Level 2 (2 points)
From page 150...
... Maturity Factor Level 1 (1 point) Level 2 (2 points)
From page 151...
... Undertake Detailed Assessments of Exposed Assets and New Projects (Step 8C) 151   • Continue to monitor asset performance.
From page 152...
... 152 Mainstreaming System Resilience Concepts into Transportation Agencies: A Guide Chapter 13 Reference FHWA.
From page 153...
... Undertake Detailed Assessments of Exposed Assets and New Projects (Step 8C)