Below is the uncorrected machine-read text of this chapter, intended to provide our own search engines and external engines with highly rich, chapter-representative searchable text of each book. Because it is UNCORRECTED material, please consider the following text as a useful but insufficient proxy for the authoritative book pages.
12 The rights to sue go beyond design services alone. They also relate to the designerâs other activities. In Shoffner Indus., Inc. v. W.B. Lloyd Constr. Co.,42 the court found that a contractor had a right of action against the design professional for negligence in approving the work of a supplier who furnished defec- tive trusses. The plaintiff alleged that the architect had inspected and approved the trusses before they were incorporated into the roof structure and that the contractor had relied on that approval. The contrac- tor further argued that the architect, as an expert, should have known that the trusses were defective and not installed in a workmanlike manner. In reject- ing the architectâs argument that it did not owe a duty of care to the contractor, the court stated: The [architect] here entered upon performance of an under- taking and, by doing so, entered into a relationship with the contractor and others giving rise to a duty to those who must reasonably rely upon his professional performance. The arrangement presented here of an architect having general supervisory responsibility over the contractor and other subcontractors on a construction project of this nature is a normal one in this commercial age. Each of the various participants must, to some degree, rely upon the profes- sional performance of the other and each therefore has the responsibility of performing his task with due care. Clearly, the incidental fact of the existence of the contract between the architect and the property owner should not negative [sic] the responsibility of the architect when he enters upon a course of affirmative conduct which may be expected to effect the interest of third parties.43 As a result, the case was reversed and remanded for retrial on the merits as to whether the architect breached its duties of supervision and inspection. Another activity related to contract administra- tion is the use of items considered to be the âequalsâ to those specified in the contract documents. Con- sider Waldinger Corp. v. CRS Group Engâr, Inc.,44 which involved an action by a mechanical contractor against an engineer on a wastewater treatment facility. The mechanical contractor claimed that the engineer was negligent in drafting restrictive speci- fications for filter presses required on the project. The specifications for these presses detailed perfor- mance capabilities and mechanical components, which the mechanical contractorâs original supplier believed it could meet. The engineer refused to accept the original supplierâs product and insisted that another supplier be used. The trial court concluded that the engineer intentionally prepared exclusionary specifications and insisted without justification that the original supplier and mechanical contractor comply literally with the specifications. It further found that only one manufacturer could literally comply with the specifi- cations as interpreted by the engineer and that the engineer intended to use such equipment in disre- gard of the U.S. Environmental Protection Agencyâs requirements for free and open competition. A similar issue arose in Waldor Pump and Equip. Co. v. Orr-Schelen-Mayeron & Assoc., Inc.,45 where the engineer prepared specifications for a municipal project and rejected Waldorâs pumps as not conform- ing to the specifications. As a result, Waldor brought an action against the engineer alleging negligence in drafting and interpreting the specifications. The project specifications required that the gen- eral contractor supply eight sludge pumps and that they be âself-primingâ and use a âcoil spring.â Waldor claimed that the only functional purpose of a coil spring was to render the pump self-priming and that the salient characteristic of the pump was that it was âself-priming.â The trial jury agreed and found the engineer to be negligent, having violated the municipal public bidding laws regarding restrictive specifications. The appellate court affirmed the judg- ment of the trial court and concluded that the engi- neer would be liable in negligence to Waldor, a third party who foreseeably relied upon the engineerâs professional obligation to reasonably draft and interpret the project specifications. III. DESIGNâBUILD CONTRACT CLAUSES AFFECTING LIABILITY One of the most important functions of any con- tract is to address what happens if something goes wrong. This section provides an overview of five topics commonly addressed in transportation- related designâbuild contracts that will affect lia- bility for design, construction, and acquisition issues: 1) disclaimers associated with owner-furnished information, 2) design development, 3) standard of care and warranty, 4) indemnification, and 5) limi- tations of liability.46 Section VI discusses some of the common disputes associated with these topics and how courts and boards of contract appeals have resolved those disputes. To illustrate the type of contract language used on the topics in this section, this digest cites to provi- sions taken from specific contracts. Unless stated otherwise, these provisions are not presented as being representative of the transportation agencyâs 42 42 N.C. App. 259, 257 S.E.2d 50 (1979). 43 Id. at 272, 257 S.E.2d at 59. 44 775 F.2d 781 (7th Cir. 1985). 45 386 N.W.2d 375 (Minn. Ct. App. 1986). 46 Although many other contract clauses affect liabil- ityâsuch as safety, site inspection, and environmental remediationâthe topics addressed in this section were chosen because they create some unique concerns and challenges under designâbuild relationships. Right-of-way acquisition contract issues will be addressed in Section V.
13 philosophy relative to this issue on all of its projects. Readers should further note that designâbuild con- tracts are lengthy and often contain multiple cross- references among clauses. As a consequence, the ultimate contractual intent and interpretation of a provision may be influenced by other language in the contract. A. Disclaimers of Responsibility for Owner- Furnished Information Owners typically provide a substantial amount of information to proposers during the designâbuild procurement process, including geotechnical reports, site and survey data, and preliminary design infor- mation. Consistent with their approach on designâ bidâbuild and other project delivery systems, most owners attempt to absolve themselves from liability for such information. They do this by using contrac- tual disclaimers that, among other things, warn bid- ders that their use of such information is âat their own risk,â âwithout any liability to the owner,â and that the bidder âshould independently determine the accuracy of the information.â On designâbidâbuild procurements, it is common to see these types of disclaimers used for geotechni- cal reports, as-built drawings, and other background and reference information. On designâbuild pro- curements, disclaimers are used not only for back- ground and reference information but also for the preliminary design documents provided by owners as part of the Request for Proposals (RFP). An example of how disclaimers are used is found in the following excerpts from the designâbuild con- tract released by Washington State Department of Transportation (WSDOT) on its State Route (SR) 99 Alaskan Way Viaduct Replacement Project.47 This contract makes it clear that, except for some limited exceptions, 1) reference documents are informa- tional and will not form a basis for a claim by the designâbuilder; and 2) the designâbuilder is not entitled to a change order for errors in the concep- tual documents provided as part of the RFP. Section 3.1.2 (Obligation to Correct Errors) states: DesignâBuilder agrees that it has full responsibility for the design of the Project, regardless of the fact that certain con- ceptual design work occurred and was provided to Designâ Builder prior to the date of execution of the Contract. DesignâBuilder specifically acknowledges and agrees that: (a) DesignâBuilder is not entitled to rely on and has not relied on (i) the Reference Documents or (ii) any other documents or information provided by WSDOT, except to the extent specifically permitted in the Contract Documents. (b) The Conceptual Design, including the Basic Configura- tion, is preliminary and conceptual in nature, may contain errors, and may not be suitable as the basis for the final design. (c) DesignâBuilder is responsible for providing Released for Construction Documents that comply with the require- ments of the Contract Documents, regardless of any errors, omissions, deficiencies or other defects in the Conceptual Design, without any increase in compensation or extension of a Completion Deadline, subject only to the right to a Change Order for Necessary Basic Configuration Changes. Section 3.3 (Reference Documents)48 reinforces these disclaimers by stating, in relevant part: â¦DesignâBuilder understands and agrees that WSDOT shall not be responsible or liable in any respect for any loss, damage, injury, liability, cost or cause of action whatsoever suffered by any DB-Related Entity by reason of any use of any information contained in the Reference Documents or any action or forbearance in reliance thereon, except to the extent that WSDOT has specifically agreed herein that DesignâBuilder shall be entitled to an increase in its com- pensation and/or extension of a Completion Deadline with respect to such matter. DesignâBuilder further acknowl- edges and agrees that (a) if and to the extent Designâ Builder or anyone on DesignâBuilderâs behalf uses any of said information in any way, such use is made on the basis that DesignâBuilder, not WSDOT, has approved and is responsible for said information, and (b) DesignâBuilder is capable of conducting and obligated hereunder to conduct any and all studies, analyses and investigations as it deems advisable to verify or supplement said information, and that any use of said information is entirely at Designâ Builderâs own risk and at its own discretion.49 On WSDOTâs Interstate 405 (I-405)/Northeast 6th Street to Interstate 5 (I-5) Widening and Express Toll Lanes Project, it articulated the designâbuild- erâs responsibility for design work as follows: It is the intent of the Contract Documents that Designâ Builder undertake full responsibility for delivery of the Project. The Contract Documents do not provide details of the design necessary to carry out the intent of the Contract Documents. Such detailed designs are the sole responsibil- ity of the DesignâBuilder to develop. If the Contract Docu- ments omit or mis-describe the Work necessary to be per- formed in order to deliver the Project in accordance with the intent of the Contract Documents and the standards and criteria for performance of the Project, the DesignâBuilder 47 SR 99 Bored Tunnel Alternative DesignâBuild Project Request for Proposal, Washington State Depât of Transp. (2010), available at http://www.wsdot.wa.gov/ biz/contaa/DESIGNBUILDCONTRACTS/SR99AWV Boredtunnel/WSDOTAWVDBContractAppendices5. 25.10.pdf (last visited June 29, 2015). 48 This contract defined the term âReference Docu- mentsâ to include Geotechnical Memoranda for Design, which were defined as those Reference Document(s) âpro- viding an interpretation of available geologic data that shall not be used to determine differing site conditions, resolve contractual disputes, or in any way interpret the contract, intents, or obligations of the parties.â 49 SR 99 Bored Tunnel Alternative DesignâBuild Project Request for Proposal Section 3.3, Washington State Depât of Transp. (2010), available at http://www. wsdot.wa.gov/biz/contaa/DESIGNBUILDCONTRACTS/ SR99AWVBoredtunnel/WSDOTAWVDBContract Appendices5.25.10.pdf (last visited June 29, 2015).
14 shall not be excused from performing such omitted Work (no matter how extensive) or mis-described details of the Work, and such Work shall be performed as if fully and cor- rectly set forth and described in the Contract Documents, without entitlement to a Change Order hereunder except as specifically allowed by the Contract Documents. Designâ Builder specifically acknowledges and agrees that: (a) The Conceptual Design is preliminary and conceptual in nature and has not been signed or sealed. (b) The DesignâBuilder is responsible for correcting any errors, omissions, inconsistencies and other defects in the Conceptual Design through the design and/or construction process. There will be no increase in the Contract Price or extension of the Contract Time for correcting any errors, omissions, inconsistencies and other defects in the Concep- tual Design, except as provided herein with respect to Nec- essary Basic Configuration Changes.50 Texas Department of Transportation (TxDOT) offers a similar provision on its Loop 1604 Western Extension Project. This designâbuild contract has several clauses that shift risk away from TxDOT relative to liability for reference documents and the RFPâs preliminary design information.51 For exam- ple, Section 1.7 (Reference Information Documents) states as follows: 1.7.1 TxDOT has provided and disclosed the Reference Information Documents to DB Contractor. Except as pro- vided in Section 1.2.3: (a) the Reference Information Docu- ments are not mandatory or binding on DB Contractor, and (b) DB Contractor is not entitled to rely on the Reference Information Documents as presenting design, engineering, operating or maintenance solutions or other direction, means or methods for complying with the requirements of the DBA Documents, Governmental Approvals or Law. 1.7.2 TxDOT shall not be responsible or liable in any respect for any causes of action, claims or Losses whatso- ever suffered by any DB Contractor-Related Entity by rea- son of any use of information contained in, or any action or forbearance in reliance on, the Reference Information Docu- ments, except any schedule or monetary relief available hereunder as set forth in Section 13 of this DBA.52 The definition for âReference Information Docu- mentsâ states that such documents were provided to the designâbuilder âfor informational purposes only and without representation or warranty by TxDOT.â Importantly, Section 3.3 (Responsibility for Design), reinforces that the designâbuilder is, with certain limited exceptions, unable to rely upon the design documents furnished by TxDOT with the RFP: DB Contractor agrees that it has full responsibility for the design of the Project and that DB Contractor will furnish the design of the Project, regardless of the fact that prior to the date of the execution of this DBA certain conceptual design work occurred and was provided to DB Contractor as part of the Schematic Design as a preliminary basis for DB Contractorâs design. DB Contractor specifically acknowl- edges and agrees that: (a) DB Contractor is not entitled to rely on: (i) the Schematic Design except as specified in Section 3.3.2, (ii) the Reference Information Documents, or (iii) any other documents or information provided by TxDOT, except to the extent spe- cifically permitted in the DBA Documents. (b) DB Contractor is responsible for correcting any Errors in the Schematic Design through the design and/or construc- tion process without any increase in the Price or extension of a Completion Deadline, subject only to the right to a Change Order with respect to Necessary Basic Configura- tion Changes to the extent permitted by Section 13.8.5. (c) TxDOTâs liability for Errors in the Schematic Design is limited to its obligations relating to Necessary Basic Con- figuration Changes as set forth in Section 2.1.3.3 and provi- sion of access to parcels within the Schematic ROW limits, and is subject to the requirements and limitations of Sec- tion 13.53 The foregoing shall not be deemed to limit TxDOTâs obligations with respect to Differing Site Condi- tions as set forth in Section 13.8. This contract contains a specific disclaimer that reinforces the notion that (with some limited excep- tions) the design-builder is unable to claim for dam- ages caused by defective owner-furnished informa- tion. Section 3.4 (Disclaimer) reads as follows: 50 I-405/NE 6th St. to I-5 Widening and Express Toll Lanes Project Request for Proposal Section 1-02.1, Washington State Depât of Transp. (2011), available at http://www.wsdot.wa.gov/biz/contaa/DESIGNBUILD CONTRACTS/NE%206TH%20ST%20TO%20I-5/ RFP%20CHAPTER%201.pdf (last visited June 29, 2015). 51 Loop 1604 Western Extension Project DesignâBuild Agreement Request for Proposals, Texas Depât of Transp. (2013), available at http://ftp.dot.state.tx.us/pub/txdot- info/sat/ loop1604_western/rfp/addendum4/dba- addendum4.pdf (last visited June 29, 2015). 52 Id. § 1.7. 53 Section 2.1.3.3 of the Contract explains the limited remedy that the designâbuilder has in the event TxDOTâs schematic design has errors: DB Contractor shall be responsible for any cost increases and/or delays which affect the duration of a Critical Path resulting from changes in requirements and obligations of DB Contractor relating to the Project due to inaccuracies in the Schematic Design. Notwith- standing the foregoing, DB Contractor shall be entitled to a Change Order to account for any additional costs incurred as a result of required modifications to any Environmental Approval due to any Hazardous Materi- als Management on and any additional Utility Adjust- ment Work on Additional Properties required due to a Necessary Basic Configuration Change to the extent set forth in Section 13.8.5. Further, any right, title or inter- est in real property DB Contractor must acquire as a result of such Necessary Basic Configuration Change shall be considered Additional Properties, and TxDOT shall be responsible for the purchase price therefor. Any changes in the Basic Configuration, including a Neces- sary Basic Configuration Change due to an Error in the Schematic Design that does not require the acquisition of Additional Properties, shall be the responsibility of DB Contractor with the exception of a TxDOT-Direct- ed Change involving more than $10,000 in additional direct costs or involving a delay to a Critical Path.
15 DB Contractor understands and agrees that TxDOT shall not be responsible or liable in any respect for any Losses whatsoever suffered by any DB Contractor-Related Entity by reason of any use of any information contained in the Schematic Design or Reference Information Documents, or any action or forbearance in reliance thereon, except to the extent that TxDOT has specifically agreed in Section 13 that DB Contractor shall be entitled to an increase in the Price and/or extension of a Completion Deadline with respect to such matter. DB Contractor further acknowledges and agrees that: (a) if and to the extent DB Contractor or anyone on DB Contractorâs behalf uses any of said information in any way, such use is made on the basis that DB Contractor, not TxDOT, is responsible for said information, and (b) DB Contractor is capable of conducting and obligated hereunder to conduct any and all studies, analyses and investigations as it deems advisable to verify or supplement said informa- tion, and that any use of said information is entirely at DB Contractorâs own risk and at its own discretion. The preceding clauses are examples of the com- peting goals that occur when an agency attempts to broadly disclaim responsibility for information it provides during the bidding process. Although the agencyâs primary goal is to avoid claims arising from this information, its secondary goals are to encour- age marketplace competition and avoid excessive bid contingencies. As a consequence, even the most one-sided contractual disclaimers generally provide designâbuilders with some limited relief for differ- ing site conditions and major changes in alignment from that shown in the RFP design. This can lead to confusion, as the contract may not clearly establish what remedies are available to the designâbuilder for errors in owner-furnished information. As discussed in detail in Section VI, there is some question as to whether the type of disclaimers dis- cussed in this section are enforceable. Substantial designâbidâbuild case law supports the view that broad disclaimers of geotechnical information are generally not effective, particularly when the dis- claimer is in direct conflict with the purpose and language of a differing site conditions clause.54 Those cases that have enforced the disclaimers generally have done so when the disclaimer is narrowly drafted to cover only specific site conditions.55 Confronted with any major flaw in the ownerâs RFP documents that increases their time or cost of perfor- mance, designâbuilders will almost certainly argue that the disclaimers should not be construed to shift the consequences of these flaws away from the owner. If the owner disagrees, an impasse will develop and relations will likely be negatively impacted. Although only a few of these disputes have resulted in reported decisions, the case law to date has generally found in favor of the designâbuilder, as discussed in Section VI. The Virginia Department of Transportation (VDOT) has developed a thoughtful way to address this issue. VDOT recognized that if the risk of defec- tive owner-furnished information was shifted to the designâbuilder, designâbuild proposal prices would be higher because bidders would put in contingen- cies to cover this risk. Because of the uncertainty over whether a court would enforce the disclaimer, however, VDOT believed it could still be obligated to pay the designâbuilder if the risk materialized, and relations on the project could be jeopardized. VDOT decided to confront this issue directly by balancing its need for effective risk transfer and price certainty with the reality that pre-award dis- claimers may not be fair to designâbuild proposers or enforceable. VDOTâs process is called âscope vali- dation.â It establishes a period of time (âscope vali- dation periodâ) where the designâbuilder can, dur- ing the design development process, present claims that relate to deficiencies in owner-furnished infor- mation. The scope validation period is generally 120 days after contract award, although this can be adjusted for more complicated projects. After the end of the scope validation period, the designâbuild- erâs claim rights are waived for items not previously raised. VDOTâs standard designâbuild contract tem- plate now includes the following clause:56 2.2 Scope Validation and Identification of Scope Issues 2.2.1 Scope Validation Period. The term âScope Validation Periodâ is the period of time that begins on DesignâBuild- erâs receipt of Departmentâs Notice to Proceed and extends for one hundred twenty (120) days from such date of receipt, unless otherwise stated in Exhibit 1. During the Scope Vali- dation Period, DesignâBuilder shall thoroughly review and compare all of the then-existing Contract Documents, including without limitation the RFP Documents and the Proposal, to verify and validate DesignâBuilderâs proposed design concept and identify any defects, errors, or inconsis- tencies in the RFP Documents that affect DesignâBuilderâs ability to complete its proposed design concept within the Contract Price and/or Contract Time(s) (collectively referred to as âScope Issuesâ). The term âScope Issueâ shall not be deemed to include items that DesignâBuilder should have reasonably discovered prior to the Agreement Date. 54 DouglAs D. grAnsberg & michAel c. loulAkis, geo- TechnicAl informATion prAcTices in DesignâbuilD proJ- ecTs (National Cooperative Highway Research Program Synthesis 429, Transportation Research Board, 2012) available at http://onlinepubs.trb.org/onlinepubs/nchrp/ nchrp_syn_429.pdf (last visited June 29, 2015), referenc- ing michAel c. loulAkis, b. p. wAAgner, & h. c. splAn, Dif- fering Site Conditions in consTrucTion clAims Deskbook (John Wiley & Sons, Inc., 1996). 55 Id. 56 VDOT DesignâBuild, Innovative Project Delivery Division, DesignâBuild Standard Template Documents, Part 4, General Conditions of Contract between Depart- ment and DesignâBuilder (2010) (hereinafter VDOT DesignâBuilder General Conditions) available at http:// www.virginiadot.org/business/resources/ipd/2010_ TemplateDocuments_100511.pdf (last visited June 29, 2015).
16 2.2.2 Scope Validation Period for Non-Accessible Areas of the Site. The Parties recognize that DesignâBuilder may be unable to conduct the additional geotechnical evaluations contemplated by Section 4.2.2 below because it will not have access to certain areas of the Site within the Scope Validation Period set forth in Section 2.2.1 above. Designâ Builder shall notify Department at the meeting set forth in Section 2.1.2 of all such non-accessible areas and the dates upon which such areas are expected to become accessible. If Department agrees that such areas are non-accessible, then, for the limited purpose of determining Scope Issues that directly arise from geotechnical evaluations for such areas, the term âScope Validation Periodâ shall be deemed to be the thirty (30) day period after the date the specified area becomes accessible for purposes of conducting the geotech- nical evaluation. 2.2.3 Submission Requirements for Scope Issues. If DesignâBuilder intends to seek relief for a Scope Issue, it shall promptly, but in no event later than the expiration of the Scope Validation Period, provide Department in writ- ing with a notice (âGeneral Noticeâ) of the existence of such Scope Issue, which General Notice shall generally explain the basis for such Scope Issue. Within twenty-one (21) days of the General Notice of a Scope Issue, Designâ Builder shall provide Department with documentation that specifically explains its support for the Scope Issue (âSupporting Documentationâ), which Supporting Docu- mentation shall include, among other things: (a) the assumptions that DesignâBuilder made during the prepa- ration of its proposal that form the basis for its allegation, along with documentation verifying that it made such assumptions in developing its proposal; (b) an explanation of the defect, error or inconsistency in the RFP Documents that DesignâBuilder could not have reasonably identified prior to the Agreement Date: and (c) the specific impact that the alleged Scope Issue has had on DesignâBuilderâs price and time to perform the Work. For the avoidance of doubt: (1) DesignâBuilder shall not be entitled to raise in its Supporting Documentation any Scope Issues that were not previously addressed in a General Notice; and (2) DesignâBuilder shall have no right to seek any relief for any Scope Issues that have not been specifically identified in a General Notice provided to Department during the Scope Validation Period. 2.2.4 Resolution of Scope Issues. Within a reasonable time after Departmentâs receipt of the Supporting Documenta- tion described in the Section 2.2.3 above, the Parties shall meet and confer to discuss the resolution of such Scope Issues. If Department agrees that DesignâBuilder has iden- tified a valid Scope Issue that materially impacts Designâ Builderâs price or time to perform the Work, a Work Order shall be issued in accordance with Article 9 hereof. If Department disagrees that DesignâBuilder has identified a valid Scope Issue that materially impacts DesignâBuilderâs price or time to perform the Work, then DesignâBuilderâs recourse shall be as set forth in Article 10. Notwithstanding anything to the contrary in the Contract Documents or as a matter of law, DesignâBuilder shall have the burden of proving that the alleged Scope Issue could not have been reasonably identified prior to the Agreement Date and that such Scope Issue materially impacts its price or time to per- form the Work. 2.2.5 DesignâBuilderâs Assumption of Risk of Scope Issues. The Parties acknowledge that the purpose of the Scope Validation Period is to enable DesignâBuilder to identify those Scope Issues that could not reasonably be identified prior to the Agreement Date. By executing this Agreement, DesignâBuilder acknowledges that the Scope Validation Period is a reasonable time to enable Designâ Builder to identify Scope Issues that will materially impact DesignâBuilderâs price or time to perform the Work. After the expiration of the Scope Validation Period, with the sole exception of those Scope Issues made the subject of a General Notice during the Scope Validation Period and subject to valid requests for Work Orders in accordance with Section 2.2.3 above, the Parties agree as follows: .1 DesignâBuilder shall assume and accept all risks, costs, and responsibilities of any Scope Issue arising from or relating to the Contract Documents, including but not limited to conflicts within or between the RFP Documents and Proposal; .2 DesignâBuilder shall be deemed to have expressly war- ranted that the Contract Documents existing as of the end of the Scope Validation Period are sufficient to enable DesignâBuilder to complete the design and construction of the Project without any increase in the Contract Price or extension to the Contract Time(s); and .3 Department expressly disclaims any responsibility for, and DesignâBuilder expressly waives its right to seek any increase in the Contract Price or extension to the Contract Time(s) for, any Scope Issue associated with any of the Contract Documents, including but not limited to the RFP Documents. 2.2.6 Waiver of Rights. The failure of DesignâBuilder to meet the submission requirements required under Section 2.2.3 above for a Scope Issue, including but not limited to the times for providing notice and documentation of the Scope Issue, shall conclusively constitute a waiver of DesignâBuilderâs rights to seek relief for such Scope Issue. To date, VDOT has experienced a number of scope validation claims on its designâbuild proj- ects, including inaccurate survey information on a railroad line and subsurface conditions that differ from those in the RFP documents. There has yet to be any litigation arising out of this clause that is the subject of a reported decision, although there is at least one dispute that is at the formal dispute resolution stage. The American Association of State Highway and Transportation Officials (AASHTO) Guide for DesignâBuild Procurement (2008) notes that the approach used by VDOT has also been used by other agencies: Some agencies, including the U.S. Army Corps of Engineers, use a contractual scope validation period. With such provi- sions, the agency retains the risks of differing site condi- tions/changed conditions until the designâbuilder has had the appropriate opportunity to validate the information provided in the request for proposals and to further define the scope of the project. The risks of differing site condi- tions/changed conditions are then shifted to the designâ builder following such scope validation period. It is sug- gested that agencies conduct initial investigations necessary
17 to prepare an appropriate scope, schedule and price esti- mate for the work.57 VDOTâs original (2006) scope validation clause is included as an example in the Guide.58 B. Design Development Among the most important and unique features of a designâbuild contract are the provisions addressing the design development process. These provisions not only serve as a contract administra- tion guideline for the parties, but also have legal implications relative to the potential transfer of liability to the owner of design deficiencies. This section will discuss some typical clauses that address these issues. Section VIâs case law review offers several reported decisions that elaborate on the rights and responsibilities of the parties during design development. 1. Impact of Ownerâs Involvement in Design Review A common concern of owners is that their involve- ment in the design review process could shift liabil- ity away from the designâbuilder if there is a flaw in the design. To address this issue, most designâbuild contracts include a clause similar to the following example from VDOTâs standard designâbuild con- tract, which attempts to absolve the owner from liability for design errors: Departmentâs review, comment and/or approval of interim design submissions and the Construction Documents are for the purpose of establishing DesignâBuilderâs compli- ance with the requirements of the Contract Documents and mutually establishing a conformed set of Contract Documents compatible with the requirements of the Work. Departmentâs review, comment and/or approval of any interim or final design submission (including but not limited to the Construction Documents) shall not be deemed to transfer any liability from DesignâBuilder to Department.59 This clause is virtually identical to those spon- sored by the DesignâBuild Institute of America (DBIA) and EJCDC.60 Because the designâbuilder is the designer-of- record, and the owner performs only a review func- tion, it would seem inappropriate to implicate the owner if the design contained calculation errors (e.g., undersized structural elements) or other details that are not readily observable. The answer might be different if the drawings specifically showed the designâbuilderâs interpretation of a design element (e.g., location of stairways that are compliant with code but not compliant with the RFPâs design documents), and the owner did not object to this element during the design review. The case law discussed in Section VI seems to support these views. Contract documents often contain a clause that requires the designâbuilder to develop a design that meets the requirements of the contract. Consider the following clause from the Tappan Zee Hudson River Crossing Project designâbuild contract: It is the DesignâBuilderâs sole responsibility to provide Design Plans, Project Specifications and Working Plans enabling development of a finished product in accordance with the Contract requirements. The DesignâBuilder shall verify pertinent dimensions in the field prior to the develop- ment and preparation of Design Plans, Project Specifica- tions and Working Plans. Review and/or approval of the DesignâBuilderâs Design Plans, Project Specifications and/ or Working Plans by the Agencies shall not relieve the DesignâBuilder of the responsibility for the completion of the Work in accordance with Contract requirements.61 The TxDOT Loop 1604 Western Extension Proj- ect discussed in the preceding section has similar language: DB Contractor agrees that it has full responsibility for the design of the Project and that DB Contractor will furnish the design of the Project, regardless of the fact that prior to the date of the execution of this DBA certain conceptual design work occurred and was provided to DB Contractor as part of the Schematic Design as a preliminary basis for DB Contractorâs design.62 This design responsibility is also contained in indemnity clauses, as is evident from the WSDOT Alaskan Way Viaduct Replacement Project clause set forth in Section D later in this section. Note that these clauses address a very different issue from that of a designâbuilder discovering errors during the design development process, cor- recting the errors, and then seeking recovery for the consequences of the errors. As discussed in Section VI, there is case law favoring the designâbuilder in 57 AASHTO, AASHTO guiDe for DesignâbuilD pro- curemenT 33 (2008). 58 Id., App. C, Example 18. 59 VDOT DesignâBuilder General Conditions. 60 See, e.g., DBIA Standard Form of General Conditions of Contract Between Owner and DesignâBuilder § 2.4.3 (2d ed. 2010): Ownerâs review and approval of interim design submissions, meeting minutes, and the Construction Documents is for the purpose of mutually establish- ing a conformed set of Contract Documents compatible with the requirements of the Work. Neither Ownerâs review nor approval of any interim design submis- sions, meeting minutes, and Construction Documents shall be deemed to transfer any design liability from DesignâBuilder to Owner. 61 Tappan Zee Hudson River Crossing Project, DB Con- tract Documents Part 2, Addendum No. 9, § DB-111-0, New York State Thruway Authority (2012). 62 Loop 1604 Western Extension Project DesignâBuild Agreement Request for Proposals, § 3.3.1, Texas Depât of Transp. (2013), available at http://ftp.dot.state.tx.us/pub/ txdot-info/sat/loop1604_western/rfp/addendum4/dba-ad- dendum4.pdf (last visited June 29, 2015).
18 these circumstances, notwithstanding disclaimer language. The intent of the preceding clauses is to ensure that the designâbuilder can stand behind the design it develops as meeting the contractâs requirements. Given that the designâbuilder is responsible for the efficacy of the design, the designâbuilder would likely have difficulty in claiming that it developed its design based on the ownerâs defective RFP or preliminary design, as might be the case if the preliminary design had a code or permit violation and the designâbuilder failed to verify that its design was code or permit compliant. The authors are unaware of any case precedent where the designâbuilder has ever pre- vailed on this argument. C. Standard of Care and Warranty Two major, interrelated topics in any designâ build contract pertain to the designâbuilderâs stan- dard of care and its warranty on that performance. Although warranty clauses are typical for any con- struction contract, these warranties generally relate to the contractorâs obligations to furnish 1) materi- als and equipment that are new; and 2) construction that is of good quality, in conformance with the con- tract documents, and free of defects in materials and workmanship. As discussed in Section II, a contrac- tor working on a designâbidâbuild project does not warrant that its work will meet the ownerâs needs, as it has no responsibility for the design. As also dis- cussed in Section II, a designer does not warrant that its work will meet the ownerâs needs eitherâit simply agrees to provide a design that meets the ordinary industry standard of care. Designâbuild contracts offer an owner an ability to shift greater responsibility to the designâbuilder than it can under other delivery systems. Although standard form contracts developed by trade and pro- fessional associations (e.g., American Institute of Architects (AIA), EJCDC) express this in different ways, they all have separate design and construc- tion standards of care and do not expressly have warranties that cover design. For example, DBIAâs standard of care for design services states, âThe standard of care for all design professional services performed to execute the Work shall be the care and skill ordinarily used by members of the design pro- fession practicing under similar conditions at the same time and locality of the Project.â63 As noted in Section II, this standard is no differ- ent than what one might expect from a designer on a typical designâbidâbuild project. DBIA, however, offers the owner an ability to require a higher stan- dard of care if performance specifications are used, based on the following âcheck-box optionâ in the con- tract, âNotwithstanding Section 2.3.1 of the General Conditions of Contract, if the parties agree upon specific performance standards in the Basis of Design Documents, the design professional services shall be performed to achieve such standards.â64 By exercising this âcheck-box option,â an owner would eliminate a designâbuilderâs potential argu- ment that its failure to meet an agreed-upon perfor- mance standard was caused by the need for a design that was higher than the âordinaryâ design standard of care. As discussed in Section VI, the language from DBIAâs âcheck-box optionâ was specifically used to hold the designâbuilder liable for breaching its performance obligations to the owner in Appeal of ECC, International.65 As for warranty, the DBIA does not specifically call for the designâbuilder to warrant the design, but only requires that it warrant construction- related services: DesignâBuilder warrants to Owner that the construction, including all materials and equipment furnished as part of the construction, shall be new unless otherwise specified in the Contract Documents, of good quality, in conformance with the Contract Documents and free of defects in materi- als and workmanship. DesignâBuilderâs warranty obligation excludes defects caused by abuse, alterations, or failure to maintain the Work in a commercially reasonable manner. Nothing in this warranty is intended to limit any manufac- turerâs warranty which provides Owner with greater war- ranty rights than set forth in this Section 2.9 or the Contract Documents. DesignâBuilder will provide Owner with all manufacturersâ warranties upon Substantial Completion.66 Designâbuild contracts developed by state trans- portation agencies widely vary in terms of how they express standards of care and warranty on design services. VDOTâs approach broadens the standard of care by requiring that the work (which includes design services) be performed to the greater stan- dards required by the contract documents, applica- ble law, and the âordinaryâ standard of care: DesignâBuilder shall perform the Work in accordance with: (a) the Contract Documents; (b) applicable Legal Require- ments and Governmental Approvals; and (c) the degree of skill and judgment prevailing on the Agreement Date that is expected to be exercised by prudent, skilled and experi- enced contractors and design professionals on similar projects in the Commonwealth of Virginia, taking into 63 DBIA Standard Form of General Conditions of Con- tract Between Owner and DesignâBuilder, Art. 2, § 2.3.1, Document 535 (2d ed. 2010). 64 DBIA Standard Form of Agreement Between Owner and DesignâBuilderâLump Sum Section, Art. 11, § 11.1, Document 530 (2d ed. 2010). 65 ASBCA No. 55781, 2013-1 B.C.A. ¶ 35207, 2012 ASBCA LEXIS 106 (Dec. 28, 2012). 66 DBIA, Standard Form of General Conditions of Con- tract Between Owner and DesignâBuilder, Art. 2, § 2.9.1, Document 535 (2d ed. 2010).
19 consideration safety, operational requirements, level of ser- vice, and life cycle costs. Notwithstanding the above, if any of (a), (b) or (c) in the preceding sentence conflict, Designâ Builder shall be obligated to perform the Work in accor- dance with the more stringent standard.67 VDOTâs warranty provision is essentially identi- cal to the DBIA clause cited above and does not address design whatsoever. Contrast this with WSDOTâs warranty clause on the I-405/Northeast 6th Street to I-5 Widening and Express Toll Lanes Project, where the designâ builder provided a comprehensive warranty associ- ated with the projectâs design:68 The following general Warranty is in addition to any express Warranties provided for elsewhere in the Contract Docu- ments. The DesignâBuilder shall represent and warrant the following: ⢠All design work performed pursuant to the Contract, including work performed by Subcontractors and manufac- turers, conforms to all professional engineering principles generally accepted as industry standard in the state of Washington. ⢠The Project is free of defects, including design errors, omissions, inconsistencies, and other defects. ⢠Materials, plants, and equipment furnished under the Contract are of good quality, and were new when installed, unless otherwise approved by WSDOT. ⢠The work meets all of the requirements of the Contract. ⢠The specifications and/or drawings selected or prepared for use during construction are appropriate for their intended use. ⢠The Project has been constructed so that it can be used for the intended function. These warranties impose substantially more lia- bility on the designâbuilder than the VDOT exam- ple, as they require that: 1) the project be free of defects, and 2) the specifications and drawings be appropriate for their intended purpose. Warranties such as those required in the WSDOT example have the potential for creating a strict liabil- ity standard on the designâbuilder, where it will be responsible for any problem, even if it followed indus- try design standards and the contract documents. This has the potential to trigger specific remedies for the benefit of the ownerâsuch as the right to termi- nate the designâbuilder for default and the award of attorneyâs fees. It can also create some major chal- lenges for designers working on designâbuild teams. It would not be unusual for terms like this to be âflowed-downâ in the designerâs subcontract so that the warranty becomes the designerâs obligation. D. Indemnification Indemnification clauses obligate one party to compensate another party for losses or damages set out in the indemnity provision. Because this obliga- tion is separate and distinct from other contractual obligations and damages, it is among the most important liability-related provisions in any con- tract, including designâbuild contracts. In addition, because most indemnity clauses require the indem- nitor to 1) defend the indemnified party from third party claims, and 2) pay the indemnified partyâs legal fees, it can have major financial consequences on the indemnitor if something goes wrong. Designâbuild contracts often contain a number of indemnification obligations on the designâbuilder, including indemnities for patent infringement, tax liability, payment claims, and liens of subcontrac- tors. One of the most significant indemnity provi- sions is often called the âgeneral indemnityâ and focuses on the designâbuilderâs liability for claims, losses, and costs incurred by the agency arising out of the designâbuilderâs conduct. Section VII has a broader discussion of the legal issues and enforceability of indemnity clauses. From a commercial perspective, suffice it to say that the breadth of the indemnity (e.g., the events triggering the indemnity and the type of damages recoverable) are key points of concern for designâbuilders. For example, does the indemnity cover only third-party claims or does it also cover economic losses incurred by the agency? Does the designâbuilder have to be negligent to trigger the indemnity? Does the indem- nity only extend to the âextentâ of the designâbuild- erâs negligence, or will it cover all losses âif the designâbuilder is negligent in whole or in part?â Most designâbuilders would prefer an indemnity similar to that used by VDOT, which reads as follows: DesignâBuilder, to the fullest extent permitted by law, shall indemnify, hold harmless and defend State Indemnitees from and against claims, losses, damages, liabilities, includ- ing attorneysâ fees and expenses, for: (i) bodily injury, sick- ness or death, and property damage or destruction (other than to the Work itself) to the extent resulting from the neg- ligent acts or omissions of DesignâBuilder, Design Consul- tants, Subcontractors, anyone employed directly or indi- rectly by any of them or anyone for whose acts any of them may be liable; and (ii) any violation of Sections 2.5, 2.6, or 2.8 hereof by DesignâBuilder, Design Consultants, Subcon- tractors, anyone employed directly or indirectly by any of them or anyone for whose acts any of them may be liable.69 67 VDOT DesignâBuilder General Conditions, § 2.1.9. 68 I-405/NE Sixth St. to I-5 Widening and Express Toll Lanes Project Request for Proposal § 1-05.16(1), Washing- ton State Depât of Transp. (2011), available at http://www. wsdot.wa.gov/biz/contaa/DESIGNBUILDCONTRACTS/ NE%206TH%20ST%20TO%20I-5/RFP%20CHAPTER %201.pdf (last visited June 29, 2015). 69 VDOT DesignâBuilder General Conditions, § 7.3.1.
20 This clause is essentially the same as what one might find in a designâbidâbuild construction con- tract. The indemnity obligations are triggered based upon the âextentâ of the designâbuilderâs negligence, focused on third-party claims, and cov- ered by most commercial general liability insur- ance policies. The three violations referenced in the clause refer to the designâbuilderâs responsibility for compliance with legal requirements, govern- mental approvals, and safety. A clause that shifts slightly more risk to the designâbuilder is Florida Department of Transpor- tationâs (FDOT) standard general indemnity provi- sion, which reads as follows: The Contractor shall indemnify and hold harmless the Department, its officers and employees from liabilities, dam- ages, losses and costs, including, but not limited to, reason- able attorneyâs fees, to the extent caused by the negligence, recklessness, or intentional wrongful misconduct of the Con- tractor and persons employed or utilized by the Contractor in the performance of the construction Contract.70 This provision does not limit the designâbuilderâs liability to third-party personal injury or property damage. As a consequence, it could be used by FDOT to recover its economic losses (e.g., administrative costs, claims paid to other contractors) arising from the designâbuilderâs wrongdoing. WSDOT used a very broad indemnity for the Alaskan Way Viaduct Replacement Project, as it directly addressed any losses (third-party or inter- nal) arising from design defects: Subject to Section 18.1.3,71 DesignâBuilder shall release, indemnify, defend and hold harmless the Indemnified Par- ties from and against any and all claims, causes of action, suits, judgments, investigations, legal or administrative pro- ceedings, penalties, fines, damages, losses, liabilities, costs and expenses, including any injury to or death of persons or damage to or loss of property (including damage to utility facilities), and including attorneysâ, accountantsâ and expert witness fees and costs, arising out of, relating to or resulting from errors, omissions, deficiencies or defects in the Design Documents, regardless of whether such errors, omissions, deficiencies or defects were also included in the Basic Con- figuration, Conceptual Design or Reference Documents. DesignâBuilder agrees that, because the Basic Configura- tion, Conceptual Design and Reference Documents are nec- essarily subject to validation, review and modification by DesignâBuilder, it is appropriate for DesignâBuilder to assume liability for errors, omissions, deficiencies or defects in the completed Project even though they may be related to errors, omissions, deficiencies or defects in the Basic Con- figuration, Conceptual Design or Reference Documents.72 This clause reinforces the perspective that the designâbuilder is fully responsible, as the projectâs designer, for the efficacy of the design documents, and cannot shift this liability as a result of defective owner-furnished information. This is consistent with the discussion previously addressed in Section B. It also makes the designâbuilder potentially responsi- ble for WSDOTâs internal costs, as well as liable for âerrorsâ and âomissionsâ in the design, regardless of whether the designâbuilder was negligent. TxDOTâs Loop 1604 Western Extension Project uses a different twist on the designâbuilderâs indem- nity obligations for design. Although the designâ builder is obligated to indemnify TxDOT for âerrors, inconsistencies or other defects in the design or con- struction of the Project,â the indemnity does not apply to any third-party loss to the extent caused by: An unsafe requirement inherent in prescriptive design or prescriptive construction specifications of the Technical Provisions, but only where prior to occurrence of the third party Loss: (i) DB Contractor complied with such specifica- tions and did not actually know, or would not have known, while exercising reasonable diligence, that the requirement created a potentially unsafe condition or (ii) DB Contractor knew of and reported to TxDOT the potentially unsafe requirement.73 This is a significant provision. It contemplates that there may be problems associated with the agencyâs design about which the designâbuilder could not have reasonably known, and does not require the designâ builder to indemnify TxDOT for third-party claims (e.g., injured drivers) for these problems. E. Limitations of Liability As suggested by the name, limitation of liability (LoL) clauses attempt to limit or eliminate a partyâs exposure to financial loss or damages as a result of that partyâs conduct. These clauses take many forms and can: 70 FDOT Division 1 General Requirements and Cov- enants § 7.12-1 (2014), available at http://www.dot.state. fl.us/specificationsoffice/Implemented/DesignBuild/ HistoryDB/January15/Default.shtm (last visited June 29, 2015) (follow âThe DesignâBuild Boilerplateâ hyperlink). 71 Section 18.1.3 (Losses Due to Negligence of Indemni- fied Parties) contains a typical provision stating that the indemnity does not apply if it is caused by the sole negli- gence or willful misconduct of an Indemnified Party: DesignâBuilderâs obligation to indemnify, defend, or save harmless an Indemnified Party under Sections 18.1.1 and 18.1.2 shall not extend to any loss, damage or cost to the extent that such loss, damage or cost was caused by the sole negligence or willful misconduct of such Indemnified Party or its agents, servants or independent contractors who are directly responsible to such Indemnified Party. 72 SR 99 Bored Tunnel Alternative DesignâBuild Proj- ect, DesignâBuild Contract § 18.1.2, Washington State Depât of Transp. (2010). 73 Loop 1604 Western Extension Project DesignâBuild Agreement Request for Proposals, § 18.1.2, Texas Depât of Transp. (2013), available at http://ftp.dot.state.tx.us/ pub/txdot-info/sat/loop1604_western/rfp/addendum4/dba- addendum4.pdf (last visited June 29, 2015).
21 ⢠Establish a ceiling on the total amount of damages for which a party will be liable (e.g., 50 percent of the contract price). ⢠Exclude liability for consequential damages. ⢠Establish liquidated damages for certain breaches of contract (e.g., performance guarantees or delays). ⢠Limit recovery for certain events (e.g., no dam- ages for delay). LoL clauses that have a ceiling on total liability are commonly seen in specialty engineering con- tracts, such as those for geotechnical and inspec- tion services. With these contracts, an engineer can face millions of dollars of potential liability if it is negligent but receive only a nominal fee. Although LoL clauses that impose a ceiling on a designâbuilderâs total liability are not frequently used on public sector projects, exceptions have been seen on very large designâbuild contracts, where the designâbuilder faces substantial poten- tial liability. For example, the $3.9-billion Tappan Zee Hud- son River Crossing Project designâbuild contract has the following LoL clause:74 Subject to the exclusions set forth in Article 9.1(2), the entire liability of DesignâBuilder for any damages arising from the DesignâBuilderâs performance or non-performance of any Work under the Contract Documents, regardless of the form of action (whether in contract, tort including negli- gence, indemnification, strict liability or otherwise, and including all liquidated damages assessable under the Con- tract Documents), shall not exceed the caps specified below, and the Authority released DesignâBuilder from all liabil- ity in excess of the specified caps: a. $ [insert 50% of the Contract Price] with respect to costs incurred by Authority or any Person acting on Authorityâs behalf in completing or correcting the Work or having the Work completed or corrected by another Person, including the cost of the work required or arising under the Warran- ties; and b. $350,000,000 with respect to any and all other costs. Section 9.1(2) contains three exclusions to this LoL. They generally relate to: 1) any type of damage or loss covered by insurance; 2) any liability for dam- ages to the extent arising from fraud, willful miscon- duct, recklessness, bad faith, gross negligence, or criminal acts; and 3) damages or compensation pay- able to the employees of the designâbuilder or its subcontractors. This type of LoL clause is similar to those found in other big-dollar transportation designâbuild con- tracts, including the Dulles Rail Corridor Project (i.e., the Silver Line) being developed by the Metro- politan Washington Airports Authority (MWAA). Phase One of the Silver Line had an initial contract price of approximately $1.6 billion and a $500 mil- lion liability cap. Phase Two had an initial contract price of approximately $1.3 billion and a $750 mil- lion liability cap. Both liability caps had exclusions similar to those described in the LoL for the Tappan Zee Bridge project. WSDOTâs Alaskan Way Viaduct Replacement Project, which had an initial contract value in excess of $1 billion, did not have any overall contractual liability cap. In addition to LoL clauses that provide an aggre- gate monetary cap on the designâbuilderâs liability, LoL clauses that provide for waivers of consequen- tial damages are often found in designâbuild con- tracts, particularly on large projects. For example, on the Alaskan Way Viaduct Replacement Project, the contractâs waiver reads as follows: Under no circumstances will either party be entitled to con- sequential damages arising out of the otherâs performance of (or failure to perform) under the Contract Documents, and each party hereby releases the other from such liability, provided that this limitation shall not excuse liability for fraud, gross negligence, intentional misconduct, or criminal acts and shall not limit the partiesâ ability to obtain recov- ery for liabilities, costs and losses covered by the insurance required hereunder. The term âconsequential damagesâ shall mean those special, indirect or incidental damages that do not flow directly and immediately from an injurious act but that result indirectly from an action or failure to act, such as revenue losses, loss of use, cost of capital, debt ser- vice, loss of profit on related contracts, administrative costs, loss of bonding capacity, lost opportunity, claims of taxpay- ers and other indirect damage. Liabilities, costs and losses incurred by either party due to failure by the other to pro- cure and maintain insurance policies required hereunder, as well as any amounts that this Contract expressly states are to be reimbursed from one party to the other (including interest, late charges, fees, penalties, and similar charges), shall be considered direct damages. This provision shall apply to limit liability under actions brought under any theory of law, including actions in tort (including negli- gence) as well as in contract.75 This clause provides an excellent description of the type of damages that might be considered âcon- sequential damages.â Another example of a consequential damages waiver is found in VDOTâs standard form designâ build contract, which reads as follows:76 Notwithstanding anything herein to the contrary (except as set forth in Section 10.4.2 below), neither designâbuilder nor department shall be liable to the other for any conse- quential losses or damages, whether arising in contract, warranty, tort (including negligence), strict liability or 74 Tappan Zee Hudson River Crossing Project DB Con- tract Documents Part 1, Addendum No. 11, Article 9.1, New York State Thruway Authority (2012). 75 SR 99 Bored Tunnel Alternative DesignâBuild Proj- ect, Design-Build Contract § 16.2.2.8, Washington State Depât of Transp. (2010). 76 VDOT DesignâBuilder General Conditions, § 10.4.